HomeMy WebLinkAboutR05-103 Bid award for grading and drainage improvements for future runway 7/25 extension
.
Commissioner moved adoption of the following resolution:
BOARD OF COUNTY COMMISSIONERS
COUNTY OF EAGLE, STATE OF COLORADO
RESOLUTION NO. 2005- /D:!J
RESOLUTION AUTHORIZING THE CHAIRMAN OF THE BOARD OF
COUNTY COMMISSIONERS TO EXECUTE DOCUMENTS ASSOCIATED WITH A
BID AWARD FOR AlP PROJECT NO. 3-08-0020-37 SCHEDULE I, GRADING AND
DRAINAGE IMPROVEMENTS FOR THE FUTURE RUNWAY 7/25 EXTENSION
WHEREAS, the Board of County Commissioners ("Board") of Eagle County, Colorado
has recognized a need for a runway extension at the Eagle County Regional Airport; and
WHEREAS, with the assistance of its engineer, Carter & Burgess, Eagle County,
Colorado issued a request for bids for the runway extension AIP Project No. 3-08-0020-37. The
bid was issued with one schedule with alternates A, B, and C; and
WHEREAS, pursuant to the bid documents should the Board wish to make an award
under the current bid documents such award must be made no later November 6,2005; and
WHEREAS, Carter & Burgess has issued a letter of recommendation concerning the
responses to the bid request which is attached hereto and incorporated herein. Carter & Burgess
recommends that Eagle County award the improvements for Schedule I, Alternate Bid A to Kelley
Trucking, Inc.; and
WHEREAS, FAA concurrence and funding are anticipated but to date have not been
received; and
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY
COMMISSIONERS OF THE COUNTY OF EAGLE, STATE OF COLORADO:
THAT the Board hereby authorizes the Chairman of the Board of County Commissioners
to execute on its behalf any and all documents, instruments, papers or other forms necessary for
the award of all or a portion of Schedule I, Alternate Bid A to Kelley Trucking, Inc. in an amount
up to $13,998,865 subject to FAA concurrence and funding availability; and
THAT this resolution shall not be deemed a notice of award; and
THAT this resolution is necessary for the health, safety and welfare of the citizens of
Eagle County, Colorado.
MOVED, READ AND ADOPTED by the Board of County Commissioners of the County
of Eagle, State of Colorado, at its regular meeting held this
COUNTY OF EAGLE, STATE OF COLORADO
By and T rough its Board of County
Com rs
By:
/1
Commissioner II~t/1A/vf.r1r"1 seconded adoption of the foregoing resolution. The roll
having been called, the vote was as follows:
Commissioner Am M. Menconi
Commissioner Tom C. Stone
Commissioner Peter Runyon
This Resolution passed by vote of the Board of County
Commissioners of the County of Eagle, State of Colorado.
Carter:: Burgess 303 8205240
August 9, 2005
Mr. Phillip M. Bowman, P.E. AUG 1 0 2005
Project Engineer
Eagle County Engineering Department ENGINEERING
500 Broadway
Eagle, Colorado 81631
(970) 328-3560
Subject: Eagle County Regional Airport
Eagle, Colorado
AlP Project No. 3-08-0020-37
Schedule I - Grading and Drainage Improvements for the Future Runway 7/25 Extension
Letter of Recommendation
Dear Mr. Bowman:
Bid proposals for the above referenced project were received and opened on August 8, 2005, in the
Garden Level Classroom at the Eagle County Building. Three Contractors submitted fonnal bids for
Schedule I, with Alternate Bids "A", "B", & "C". The bids were tabulated for mathematical correctness
and are summarized in the following table:
Schedule I - Grading and Drainage Improvements for the Future Runway 7/25 Extension
,...-- !
.
I Bidder Alternate" A" Alternate "8" Alternate "C"
I
Kelley Trucking, Inc. $13,998,865.00 $12,499,590.00 $12,072,290.00
,
Ames Construction, Inc. $15,638,678.00 $13,686,978.00 $12,803,678.00 i
I
Sema Construction, Inc. $24,177,037.00 $13,887,037.00 $12,279,737.00
Engineer's Estimate $12,458,475.00 $10,616,475.00 $10,271,975.00
~~-_.~_.'-'~- -,.__.~ ~...
Based upon the above information, Kelley Trucking, Inc. is the lowest bidder for Bid Alternate "1\", "B",
& "C" of this project. Their bid is $13,998,865.00 is approximately 12.4% percent higher than the
Engineer's estimate. The substantial difference between the Engineer's Estimate and Kelley Trucking
Inc.'s bid on Alternate "A" can be directly linked to the unit cost of Item P-152a Embankment.
The primary factor that contributed to only having three bidders is that the majority of the project is
associated with having available material borrow sources, which are scarce in the region.
"
Mr. Phillip Bowman
August 9,2005
Page 2
Kelley Trucking, Inc. has stated in their Bid Proposal that they will meet the required Disadvantaged
Business Utilization commitment of 1.02%.
We reviewed the bid proposal for compliance with the "Instructions to Bidders". Kelley Trucking, Inc.
submitted the required forms, including the EEO Statements, Certification of Non-Segregated Facilities,
Buy American Verification, Statement of Qualifications, Proposed Equipment List, and Proposal
Guaranty. We have reviewed the Contractor's qualifications and consider this firm capable of completing
the proposed work.
Based on the information provided by the Contractor, we recommend that Eagle County award the
planned improvements for Schedule I, Alternate Bid "A" to Kelley Trucking, Inc. in the amount of
$13,998,865.00, subject to FAA concurrence and funding availability
The following documents have been enclosed for your records:
Planholders List
Tabulation of Bids
Contractor's Original Proposals
If you need additional information, please feel free to contact us.
Sincerely,
Carter & Burgess
~
~
Jason Virzi, P.E.
Project Engineer
Enclosures
cc: Mr. Chris Schaffer, FAN ADO
Carter & Burgess, inc. Carter & Burgess Architects/Engineers, inc. Carter & Burgess Consultants, inc.
C&B Architects/Engineers, inc. C&B Architects/Engineers, PC C&8 Nevada, lac.
.
~
Project # 071184.102
Bid Date: 81812005
TABULATION OF BIDS
EAGLE COUNTY REGIONAL AIRPORT
GYPSUM,COLORADO
AlP PROJECT NUMBER: 3-08-0020-37
SCHEDULE I
Grading and Drainage for the Future Runway 7/25 Extension
Engineer's Estimate Kelley Trucking, Inc. Ames Construction, Inc. Serna Construction, Inc.
Bid Bond X X X X
DBE Goals 1.02% 1.02% 1.02% 1.27%
Addendum No.1 X X X X
Schedule I (Alt. A) $12.458.475.00 $13,998,865.00 $15,638,678.00 $24,177,037.00
Schedule I (All. B) $10,616.475.00 $12,499,590.00 $13,686,978.00 $13,887,037.00
Schedule I (All. C) $10,271,975.00 $12,072,290.00 $12,803,678.00 $12.279,737.00
EGE 102_BidTab_AIP 37.xls Page 1 of 4
.
,
TABULATION OF BIDS Proj. # 071184.102 .
EAGLE COUNTY REGIONAL AIRPORT Bid Date: 8/8/2005
GYPSUM, COLORADO ,
AlP PROJECT NUMBER: 3-08-0020-37
SCHEDULE I ALTERNATE A Engineer's Estimate Kelley Trucking, Inc. Arnes Construction, Inc. Serna Construction, Inc.
Gradina and Drainage for the Future Runway 7/25 Extension
Item No. Description Estimated Unit Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost
Quantitv
P100a Mobilization LS 1 $1,133,000.00 $1,133,000.00 $1,315,000.00 $1,315,000.00 $1,080,000.00 $1,080,000.00 $800,000.00 $800.000.00
P152a Embankment, All. A. Off Site Borrow CY 1750000 $5.00 $8,750,000.00 $5.53 $9,677,500.00 $6.70 $11.725.000.00 $11.00 $19,250,000.00
P152c Unclassified Excavation CY 27000 $2.00 $54,000.00 $5.60 $151.200.00 $1.60 $43.200.00 $2.50 $67.500.00
0701a Install 12 Inch SOR 35 Sanitary Sewer LF 1320 $50.00 $66,000.00 $44.00 $58,080.00 $86.00 $113,520.00 $55.00 $72,600.00
0701b Install 18 Inch RCP, CI. III LF 825 $45.00 $37,125.00 $44.00 $36,300.00 $50.00 $41,250.00 $55.00 $45,375.00
..",
0701c Install 24 Inch RCP, CI. III LF 140 $70.00 $9,800.00 $61.00 $8,540.00 $90.00 $12,600.00 $125.00 $17.5'
0701d Remove Existing 72 Inch CM. with Headwall LF 1000 $45.00 $45.000.00 $36.00 $36.000.00 $44.00 $44,000.00 $55.00 $55,000.00
0701e Remove Existing Sanitary Sewer Line LF 1300 $20.00 $26,000.00 $16.00 $20,800.00 $30.00 $39,000.00 $10.00 $13.000.00
0705a Install 6 Inch Perforated Underdrain, Complete LF 3220 $25.00 $80,500.00 $32.00 $103.040.00 $27.00 $86.940.00 $40.00 $128.800.00
0710a Install Type "M" Grouted Rock Riprap SY 100 $100.00 $10.000.00 $88.00 $8,800.00 $200.00 $20,000.00 $250.00 $25.000.00
0751a Adjust Existing Sanitary Manhole EA 2 $2.000.00 $4.000.00 $1,750.00 $3,500.00 $600.00 $1.200.00 $500.00 $1,000.00
0751b Construct Box Culvert LF 1325 $750.00 $993.750.00 $1,015.00 $1,344,875.00 $1.015.00 $1.344,875.00 $1,950.00 $2,583.750.00
0751c Install Box Culvert Inlet Structure EA 1 $20,000.00 $20,000.00 $17,000.00 $17,000.00 $30,000.00 $30,000.00 $27,500.00 $27,500.00
0751d Install Box Culvert Outlet Structure EA 1 $30,000.00 $30.000.00 $27.000.00 $27.000.00 $60.000.00 $60.000.00 $35.000.00 $35,000.00
0751e Install Inlet/Manhole Type I Single EA 7 $15,000.00 $105,000.00 $10,000.00 $70,000.00 $9,000.00 $63.000.00 $6.500.00 $45.500.00
0751f Install Sanitary Sewer Manhole EA 3 $5.000.00 $15,000.00 $3.200.00 $9.600.00 $4,000.00 $12.000.00 $4,500.00 $13.500.00
0751g Remove Existing Sanitary Manholes EA 3 $1,500.00 $4,500.00 $1,900.00 $5,700.00 $1,100.00 $3,300.00 $500.00 $1,500.00
0800a Install Retaining Wall Complete SF 7321 $50.00 $366.050.00 $67.50 $494.167.50 $53.00 $388,013.00 $67.00 $490.507.00
F162a Chain-Link Fence ~"'.""'.~,
LF 8700 $30.00 $261,000.00 $20.00 $174,000.00 $20.00 $174,000.00 $20.00 $174,Or
F162b Install 24 Foot Double Swing Gate EA 3 $1,000.00 $3,000.00 $1,500.00 $4,500.00 $2.000.00 $6,000.00 $1,300.00 $3.900.00
F162c Remove Existing 8 Foot Electric Animal Control Fence LF 5150 $5.00 $25,750.00 $2.75 $14,162.50 $3.20 $16.480.00 $2.70 $13,905.00
T901a Install Erosion Control Blankets SY 43000 $2.00 $86,000.00 $1.20 $51.600.00 $1.20 $51,600.00 $1.50 $64,500.00
T901b Seeding With Hydromulch AC 35 $2,000.00 $70,000.00 $1,100.00 $38,500.00 $1,100.00 $38,500.00 $900.00 $31,500.00
L103a Remove/Reinstall Airport Light Towers EA 5 $20,000.00 $100,000.00 $38,000.00 $190,000.00 $20,000.00 $100.000.00 $20.000.00 $100.000.00
::00T304. Class 6 Road Base CY 4600 $30.00 $138,000.00 $25.00 $115,000.00 $27.00 $124,200.00 $22.00 $101.200.00
M606a Install Guardrail LF 1000 $25.00 $25,000.00 $24.00 $24,000.00 $20.00 $20,000.00 $15.00 $15.000.00
TOTAL SCHEDULE I $12,458,475.00 $13.998,865.00 $15,638.678.00 $24,177,037.00
EGE I02..BidTab.AIP 37.xls Page 2 of 4
-
TABULATION OF BIDS Proj. # 071184.102
EAGLE COUNTY REGIONAL AIRPORT Bid Date: 8/8/2005
GYPSUM,COLORADO
AlP PROJECT NUMBER: 3-08-0020-37
SCHEDULE I AL TERNA TE B Engineer's Estimate Kelley Trucking, Inc. Ames Construction, Inc. Serna Construction, Inc.
GradinQ and DrainaQe for the Future Runway 7/25 Extension
Item No. Description Estimated Unit Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost
Quantitv
P100a Mobilization LS 1 $965,000.00 $965,000.00 $1,233,500.00 $1,233.500.00 $1.180.000.00 $1.180,000.00 $800,000.00 $800.000.00
P152b Embankment. All. A. On and Off Site Borrows CY 1750000 $4.00 $7.000.000.00 $4.63 $8,102,500.00 $5.50 $9,625,000.00 $5.10 $8,925,000.00
P152c Unclassified Excavation CY 40000 $2.00 $80,000.00 $5.40 $216.000.00 $1.60 $64.000.00 $2.00 $80.000.00
D701a Install 12 Inch SDR 35 Sanitary Sewer LF 1320 $50.00 $66,000.00 $44.00 $58,080.00 $86.00 $113.520.00 $55.00 $72.600.00
0701b Install 18 Inch RCP, CI. III LF 825 $45.00 $37,125.00 $44.00 $36,300.00 $50.00 $41,250.00 $55.00 $45.37~..QO
0701c Install 24 Inch RCP, CI. III LF 140 $70.00 $9,800.00 $61.00 $8.540.00 $90.00 $12,600.00 $125.00 $17,5
..:.
0701d Remove Existing 72 Inch CM, with Headwall LF 1000 $45.00 $45,000.00 $36.00 $36,000.00 $44.00 $44,000.00 $55.00 $55.000.00
D701e Remove Existing Sanitary Sewer Line LF 1300 $20.00 $26,000.00 $16.00 $20,800.00 $30.00 $39,000.00 $10.00 $13,000.00
D705a Install 6 Inch Perforated Underdrain, Complete LF 3220 $25.00 $80,500.00 $32.00 $103,040.00 $27.00 $86,940.00 $40.00 $128.800.00
0710a Install Type "M" Grouted Rock Riprap SY 100 $100.00 $10,000.00 $88.00 $8.800.00 $200.00 $20,000.00 $250.00 $25.000.00
0751a Adjust Existing Sanitary Manhole EA 2 $2,000.00 $4.000.00 $1,750.00 $3.500.00 $600.00 $1,200.00 $500.00 $1,000.00
D751b Construct Box Culvert LF 1325 $750.00 $993.750.00 $1,064.00 $1.409,800.00 $1.015.00 $1,344.875.00 $1,950.00 $2.583,750.00
D751c Install Box Culvert Inlet Structure EA 1 $20,000.00 $20,000.00 $17,000.00 $17 .000.00 $30.000.00 $30,000.00 $27.500.00 $27,500.00
0751d Install Box Culvert Outlet Structure EA 1 $30.000.00 $30,000.00 $27,000.00 $27.000.00 $60,000.00 $60.000.00 $35.000.00 $35,000.00
0751e Install Inlet/Manhole Type I Single EA 7 $15,000.00 $105,000.00 $10,000.00 $70,000.00 $9,000.00 $63.000.00 $6,500.00 $45,500.00
0751f Install Sanitary Sewer Manhole EA 3 $5,000.00 $15,000.00 $3,200.00 $9.600.00 $4,000.00 $12.000.00 $4.500.00 $13,500.00
0751g Remove Existing Sanitary Manholes EA 3 $1,500.00 $4,500.00 $1,900.00 $5.700.00 $1,100.00 $3,300.00 $500.00 $1,500.00
D800a Install Retaining Wall Complete SF 7321 $50.00 $366.050.00 $67.50 $494.167.50 $53.00 $388,013.00 $67.00 $490,507.00
F162a Chain-Link Fence LF 8700 $30.00 $261.000.00 $20.00 $174,000.00 $20.00 $174,000.00 $20.00
F162b Install 24 Foot Double Swing Gate EA 3 $1,000.00 $3,000.00 $1,500.00 $4,500.00 $2,000.00 $6,000.00 $1,300.00 $3,900.00
F162c Remove Existing 8 Foot Electric Animal Control Fence LF 5150 $5.00 $25,750.00 $2.75 $14,162.50 $3.20 $16.480.00 $2.70 $13,905.00
T901a Install Erosion Control Blankets SY 43000 $2.00 $86,000.00 $1.20 $51.600.00 $1.20 $51,600.00 $1.50 $64,500.00
T901b Seeding With Hydromulch AC 60 $2,000.00 $120.000.00 $1,100.00 $66,000.00 $1.100.00 $66.000.00 $900.00 $54,000.00
L1 03a Remove/Reinstall Airport Light Towers EA 5 $20,000.00 $100,000.00 $38,000.00 $190,000.00 $20.000.00 $100,000.00 $20.000.00 $100,000.00
,.;DOT304. Class 6 Road Base CY 4600 $30.00 $138,000.00 $25.00 $115,000.00 $27.00 $124.200.00 $22.00 $101,200.00
M606a Install Guardrail LF 1000 $25.00 $25,000.00 $24.00 $24.000.00 $20.00 $20.000.00 $15.00 $15.000.00
TOTAL SCHEDULE I $10,616,475.00 $12,499,590.00 $13.686,978.00 $13.887.037.00
EGE I02_BidTab_AJP 37.xls Page 3 of 4
TABULATION OF BID5 Proj. # 071184.102
EAGLE COUNTY REGIONAL AIRPORT Bid Date: 8/812005
GYPSUM,COLORADO
AlP PROJECT NUMBER: 3-08-0020-37
SCHEDULE I ALTERNATE C Engineer's Estimate Kelley Trucking, Inc. Ames Construction, Inc. Sema Construction, Inc.
Grading and Drainaoe for the Future Runwav 7/25 Extension
Item No. Description Estimated Unit Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost
Quantitv
P100a Mobilization LS 1 $934,000.00 $934,000.00 $1,200,000.00 $1,200,000.00 $1,180,000.00 $1,180,000.00 $800.000.00 $800,000.00
P152b Embankment, All. A, On and Off Site Borrows CY 1750000 $3.75 $6,562,500.00 $4.29 $7,507,500.00 $4.95 $8,662,500.00 $4.15 $7,262.500.00
P152c Unclassified Excavation CY 62000 $2.00 $124,000.00 $5.25 $325,500.00 $1.60 $99.200.00 $1.60 $99.200.00
D701a Install 12 Inch SOR 35 Sanitary Sewer LF 1320 $50.00 $66,000.00 $44.00 $58,080.00 $86.00 $113.520.00 $55.00 $72.600.00
0701b Install 18 Inch RCP. CI. III LF 825 $45.00 $37,125.00 $44.00 $36,300.00 $50.00 $41,250.00 $55.00 $45,375.00
" "'\,
0701c Install 24 Inch RCP, CI.III LF 140 $70.00 $9.800.00 $61.00 $8,540.00 $90.00 $12.600.00 $125.00 $17,5C
D701d Remove Existing 72 Inch CM, with Headwall LF 1000 $45.00 $45,000.00 $36.00 $36,000.00 $44.00 $44,000.00 $55.00 $55,000.00
0701e Remove Existing Sanitary Sewer Line LF 1300 $20.00 $26,000.00 $16.00 $20,800.00 $30.00 $39,000.00 $10.00 $13,000.00
0705a Install 6 Inch Perforated Underdrain, Complete LF 3220 $25.00 $80,500.00 $32.00 $103,040.00 $27.00 $86,940.00 $40.00 $128,800.00
0710a Install Type "M" Grouted Rock Riprap SY 100 $100.00 $10,000.00 $88.00 $8,800.00 $200.00 $20,000.00 $250.00 $25,000.00
0751a Adjust Existing Sanitary Manhole EA 2 $2,000.00 $4,000.00 $1,750.00 $3,500.00 $600.00 $1,200.00 $500.00 $1,000.00
0751b Construct Box Culvert LF 1325 $750.00 $993.750.00 $1,100.00 $1,457,500.00 $1.015.00 $1,344,875.00 $1,950.00 $2,583,750.00
0751c Install Box Culvert Inlet Structure EA 1 $20,000.00 $20,000.00 $17.000.00 $17,000.00 $30,000.00 $30.000.00 $27.500.00 $27,500.00
0751d Install Box Culvert Outlet Structure EA 1 $30.000.00 $30,000.00 $27,000.00 $27,000.00 $60,000.00 $60,000.00 $35.000.00 $35,000.00
0751e InstalllnleVManhole Type I Single EA 7 $15,000.00 $105,000.00 $10,000.00 $70,000.00 $9.000.00 $63,000.00 $6.500.00 $45,500.00
0751f Install Sanitary Sewer Manhole EA 3 $5,000.00 $15,000.00 $3,200.00 $9,600.00 $4,000.00 $12,000.00 $4.500.00 $13.500.00
0751g Remove Existing Sanitary Manholes EA 3 $1.500.00 $4,500.00 $1,900.00 $5,700.00 $1,100.00 $3,300.00 $500.00 $1,500.00
0800a Install Retaining Wall Complete SF 7321 $50.00 $366,050.00 $67.50 $494,167.50 $53.00 $388.013.00 $67.00 $490.507.00
F162a Chain-Link Fence ""."",,\'0
LF 8700 $30.00 $261,000.00 $20.00 $174,000.00 $20.00 $174.000.00 $20.00 $174,Or
F162b Install 24 Foot Double Swing Gate EA 3 $1,000.00 $3,000.00 $1.500.00 $4,500.00 $2,000.00 $6,000.00 $1.300.00 $3,900.00
F162c Remove Existing 8 Foot Electric Animal Control Fence LF 5150 $5.00 $25,750.00 $2.75 $14,162.50 $3.20 $16.480.00 $2.70 $13,905.00
T901a Install Erosion Control Blankets SY 43000 $2.00 $86,000.00 $1.20 $51.600.00 $1.20 $51.600.00 $1.50 $64,500.00
T901b Seeding With Hydromulch AC 100 $2.000.00 $200,000.00 $1.100.00 $110.000.00 $1,100.00 $110,000.00 $900.00 $90,000.00
L103a Remove/Reinstall Airport Light Towers EA 5 $20,000.00 $100,000.00 $38,000.00 $190,000.00 $20,000.00 $100,000.00 $20.000.00 $100.000.00
:00T304s Class 6 Road Base CY 4600 $30.00 $138.000.00 $25.00 $115,000.00 $27.00 $124.200.00 . $22.00 $101.200.00
M606a Install Guardrail LF 1000 $25.00 $25,000.00 $24.00 $24,000.00 $20.00 $20,000.00 $15.00 $15,000.00
TOTAL SCHEDULE I $10,271,975.00 $12,072,290.00 $12,803,678.00 $12,279.737.00
EGE I02_BidTab_AIP 37.xls Page 4 of4