HomeMy WebLinkAboutR82-045 Yarmony Bridge Certificate of Intent to ProceedRESOLUTION
OF THE
BOARD OF COUNTY COMMISSIONERS
COUNTY OF EAGLE, STATE OF COLORADO
RESOLUTION No. 82- -�
YARMONY BRIDGE, PROJECT No. EAG- 028 -03.6 - CERTIFICATE
OF INTENT TO PROCEED - SPECIAL BRIDGE MONEY FROM THE
SPECIAL HIGHWAY COMMITTEE
WHEREAS, the Board of County Commissioners of
the County of Eagle, State of Colorado, hereinafter
referred to as the "Board ", did on June 22, 1982, receive
notification from the Special Highway Committee approving
Eagle County's Yarmony Bridge project, structure number
EAG- 028 -03.6, for State funding from the Special Bridge
Account in the maximum amount of $ 148,800.00; and
WHEREAS, the aforesaid approval is subject to the
Board submitting within 45 days after receipt of the
notification of project approval, a certificate of
intent to proceed with the project, and a project budget
cost estimate; and
WHEREAS, the Board is desirous of proceeding with
the subject project.
NOW, THEREFORE, be it resolved by the Board of
County Commissioners of the County of Eagle, State of
Colorado:
THAT, the Board hereby certifies to the Special
Highway Committee that it intends to proceed with the
Yarmony Bridge project, structure number EAG - 028 -03.6.
THAT, the Board further certifies that it presently
has the required twenty percent local matching funds
necessary for the aforesaid project.
THAT, the current estimated total project cost
is $ 313,600.00 which was derived by using an estimated
$ 80.00 per square foot for a bridge with a 140 foot span
and 28 feet wide. Furthermore, the subject bridge is proposed
to be constructed of a material recommended by a design
engineer using concrete or steel, or a combination of both.
THAT, the proposed time schedule for commencement
and completion of the Yarmony Bridge project is as
follows:
a) Selection of design engineer .September 15, 1982
b) Acceptance of design and bid
documents . . . . . . . . . January 2, 1983
c) Completion of bidding process
and award of contract . . . March 1, 1983
d) Commencement of construction. April 1, 1983 or
as soon as weather
permits after
contract execution
e) Anticipated project
completion . . . . . . . . October 30, 1983
THAT, the Board hereby requests and directs the
County Administrator, Brad Jones, to transmit an original
of this Resolution to the Special Highway Committee, and
to perform all other necessary steps in order to receive the
State funding from the Special Bridge Account in the maximum
amount of $ 148,000.00 for the Yarmony Bridge project.
THAT, this Resolution is necessary for the public
health, safety and welfare of the citizens and residents
of the County of Eagle, State of Colorado.
MOVED, READ AND UNANIMOUSLY ADOPTED by the Board
of County Commissioners of the County of Eagle, State
-2-
r�
of Colorado, at its regular meeting held the
of July, 1982.
ATTEST:
By . r_,
/glerk to the ard of
County Commissioners
-3-
a!-?'- day
COUNTY OF EAGLE, STATE OF COLORADO
By and Through its
BOARD OF COUNTY COMMISSIONERS
By:
Dale F. Grant, vChairman
- r
Dan Wi iams, Commissioner
Keit Troxe ommissioner