HomeMy WebLinkAboutR93-151 second extension of SIA for McGrady Acres/NottinghamCOUNTY OF EAGLE, STATE OF COLORADO
RESOLUTION NO. 93 - _5�_ _
AUTHORIZING THE SECOND EXTENSION OF THE
SUBDIVISION IMPROVEMENTS AGREEMENT
AND PARTIAL RELEASE OF COLLATERAL
McGRADY ACRES /NOTTINGHAM
WHEREAS, on or, about July 23, 1991, pursuant to Section 30 -28-
137, C.R.S., the Board of County Commissioners of the County of
Eagle, State of Colorado ( "Board ") entered into a Subdivision
Improvements Agreement ( "Agreement ") with Nottingham Ranch Company,
a Limited Partnership and Susan Nottingham ( "Subdivider ") as a
condition of final plat approval of McGrady Acres; and
WHEREAS, in order to guarantee the faithful completion of
certain public improvements required under the Agreement, the Board
accepted as collateral Irrevocable Letter of Credit #144, dated
July 23, 1991, in the amount of $348,000.00, with an expiration
date of July 1, 1994; and
WHEREAS, the Subdivision Improvements Agreement will expire on
April 4, 1994; and Letter of Credit No. 144 for $348,000.00 will
expire on July 1, 1994; and
WHEREAS, the Subdivider has by letter dated November 3, 1993,
(Exhibit A) requested an extension on the Subdivision Improvements
Agreement for a period of five (5) months or until September 1,
1994, to allow accomplishment of the temperature sensitive bridge
repairs; and the County agrees to said extension, (Exhibit B) for
the mutual benefit to be derived by said extension; and
WHEREAS, the Subdivider has requested, and the County agrees,
to a reduction of collateral in the amount of $251,400 to $67,100
for completion of bridge repairs plus $31,400 for a 10% retainage
on the work completed. The $29,500 retainage on the work completed
should be retained for a two -year warranty period which should run
from May 28, 1993 to May 28, 1995; and
WHEREAS, the Subdivider will provide to the County a new
letter of credit in the amount of $98,500.
�i
526085 B -630 P -26 01/14/94 11:20A PG 1 OF 4 REC DOC
Sara J. Fisher Eagle County Clerk & Recorder 0.00
�. .
m
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY
COMMISSIONERS OF THE COUNTY OF EAGLE, STATE OF COLORADO:
THAT, the Board hereby authorize the extension of the
Subdivision Improvements Agreement to September 1, 1994.
THAT, the Board hereby authorize the partial release of
collateral to $31,400 for a 10% retainage on the work completed and
$67,100 for the completion of bridge repairs, for a total of
$98,500 to be held as collateral.
MOVED, READ AND ADOPTED by the Board of County Commissioners
of the County of Eagle, State of Colorado, this day of
December 1993.
ATTEST:
La— Q-46== By:
Clerk to the Board of
County Commissioners
Commissioner
foregoing re:
follows:
COUNTY OF EAGLE, STATE OF
COLORADO, By and Through Its
BOARD OF COUNTY COMMISSIONERS
George e . Gates, Chairman
Commissioner George A. Gates _
Commissioner Johnnette Phillips
Commissioner James E. Johnson, Jr. 4 2 -c
This Resolution passed by vote of the Board of
County Commissioners of the County of Eagle, State of Colorado.
Attachments 91 -39 Mcgrady. ext
526085 B -630 P -26 01/14/94 11:20A PG 2 OF 4
C)
C
O
�w
Xov©mber 3, 1993
I
V'(" LE
Board of county co=isciarers
P.O. Box 850
pEgle, co 81631
REs McGrady Acres Subdivision rtprovcmcnts Agreerent
Dear sirlmada= :
1 � �
�.
To
It is r equested that subdivision =prove= - Uts Agreement be extended by five
Monty.&, to September 1 1954, and that the amount of Lhe letter of credit
required for the subdivision .improvements ggreen:exit be reduced to the =wmnt
needed for bridge repairs, in tho amount of $67' is
• Fo1l0ving is a summary
;,f events which supports the- approval: of the req[u
1. Por attached trap raittal dated V. 39, 1993, utility companies
provided letters stating that th-Dy will tare ownership of their respective
utility. This leaves the bridge repair an the remaining item to be
completed for the Subdivision zmpr evements Agreemnt.
2. Zn rk►y, 1993, it was r egaest €d to rtducs Cho letter of credit to the
amount needed to repair the bridge. Larry Metternick requested that tha
bridge be rev VjMd Lad rp- aa.>xended repairs be updated. It scat intended to
obtain an updated estimate of bridge repairs, and reduce thQ letter of
credit accordingly.
3. During the insgect?on process, zazry xetternick asked that the
passibility of replaci the bridge be researched. Tjbia process took as
additional month or two to complete. THE eoNCLUSION OF THE R$SMCH WAS
TERT THE PRIDGB SHOULD BE REPAIRED, A[JD NOT ASS.
r,oat that the scope of work
�. for bridge repairs is knows, it is too late need to be
in the�s.eason to begin, re a:.r. requiring heref orn $a e�z c the 1 6abdivisiaa
couple,.ed next tt.r=_ (1994),
improvements )Lgr
5. zoACO, Inc. the consulz;ng engineer whc inspected the bridg©,
astim,atod the Cost of re airs to ba $61,000. 2f a .0s Conti a �a i=
included, the total• costa repairs ie escpetted to be S67,100. 0, o�biah
the �ouat that. is zeaueatecl to reduce the. letter of credit 6o the
is Scbdivisions 2mprosremaats AgrCemerit.
sincerely,
c
Nottingham Invc nt CCMPa ly
cc Larry mettsrn&ck, Eagle coua Enciaaar
Gle= Palma=, Alpine E. cinccrring, Iti
EXHIBIT
1 (rk V--�
,, /
U I'll V6
N
0
Co
Cn
I
W
0
MEMORANDUM D
EAGLE COUNTY ENGINEERING INOV 1 9 1193
EAGLE COUNTY ATTORNEY
TO: Nancy Lewis, County Attorney's Office
FROM: Larry Metternick, County Engineer
DATE: November 17, 1993
RE: McGrady Acres
Attached please find a request from Nottingham Investment Company
requesting a reduction of collateral to $67,100 and requesting an
extension of time for five months to September 1, 1994.
The work outlined in Exhibit A to the Subdivision Improvements
Agreement is complete and acceptable, except the bridge work.
The work complete totals $295,000 and the new estimate of bridge
repairs is $67,100..
We concur with the request for extension of time to September 1,
1994 to allow accomplishment of the temperature sensitive bridge
repairs during the warm weather months. We concur with the
reduction in collateral except that the collateral should be
reduced to $67,100 for completion of bridge repairs plus $29,500
for a loo retainage on the work completed. The $29,500 retainage
on the work completed should be retained for a two year warranty
period which should run from May 28, 1993 to May 28, 1995. The
new collateral amount at this time would then be $67,100 plus
$29,500 equals $96,600.
526085 B -630 P -26 01/14/94 11:20A PG 4 OF 4
cc: W.E'. Nottingham, Nottingham Investment Co.
Glen Palmer, Alpine Engineering
Jack Lewis, County Manager