Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutC99-094 Gonzales Construction CompanyC' q(q -'� 4 - S-to
AGREEMENT
THIS AGREEMENT is dated as of the= day of / , in the year 1999 b and
Y Y
between
Board of County Commissioners
Eagle County, Colorado
(hereinafter called OWNER)
and
Gonzales Construction Company, Inc.
(hereinafter called CONTRACTOR)
OWNER and CONTRACTOR, in consideration of the mutual covenants set forth, agree as
follows:
ARTICLE 1 - WORK
'ftw✓ CONTRACTOR shall complete all work as specified or indicated in the Contract
Documents. The work is generally described as follows:
Installation of approximately 3,900 linear feet of guardrail with end
anchorages at various locations
ARTICLE 2 - ENGINEER
The Project has been designed by the Eagle County Engineer (an employee of Eagle
County), who is hereinafter called ENGINEER, and will assume all duties and
responsibilities, and will have the rights and authority assigned to ENGINEER in the
Contract Documents in connection with completion of the work in accordance with the
Contract Documents.
\"or, Agreement Page 1
14w/
r5
ARTICLE 3 - CONTRACT TIME
3.1 The work will be substantially completed on or before September 15, 1999, and
completed and ready for final payment in accordance with paragraph 14.13 of the
General Conditions on or before'September 16, 1999.
3.2 LIQUIDATED DAMAGES: OWNER and CONTRACTOR recognize that time is of
the essence of this Agreement and that OWNER will suffer financial loss if the
work is not substantially complete within the time specified in paragraph 3.1 above,
plus any extensions thereof allowed in accordance with Article 12 of the General
Conditions. They also recognize the delays, expense, and difficulties involved in
proving a legal or arbitration proceeding the actual loss suffered by OWNER if the
work is not substantially complete on time. Accordingly, instead of requiring such
proof, OWNER and CONTRACTOR agree that as liquidated damages for delay
(but not as a penalty) CONTRACTOR shall pay OWNER Five Hundred Forty
dollars ($540.00) for each day that expires after the time specified in paragraph
3.1 for substantial completion until the work is substantially complete.
ARTICLE 4 - CONTRACT PRICE
4.1 The funds appropriated for this project are equal to or in excess of the contract
amount. OWNER shall pay CONTRACTOR for performance of the work in
accordance with the Contract Documents in current funds as follows:
Item
1.
2.
Description Qt Unit Unit Price Amount
Guardrail, Type 3
Frying Pan Road
End Anchorage
Type 3 E
3. Construction Zone
Traffic Control
*(All Locations)
4. Credit to County for
Re -used posts
(TBD=To be determined
during construction)
TOTAL
Agreement
3,900 L.F.
20 Each
1 Lump
Sum
TBD Each
$ 9.65 $37,635.00
$ 585.00 $11,700.00
$6,100.00 $ 6,100.00
$ 12.00 $ -0-
$55,435.00
Page 2
ARTICLE 5 - PAYMENT PROCEDURES
`fto' CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER as
provided in the General Conditions.
5.1 PROGRESS PAYMENTS: OWNER shall make monthly progress payments on
account of the Contract Price on the basis of CONTRACTOR' Applications for
Payments as recommended by ENGINEER, as provided. below. All progress
payments will be on the basis of the progress of the work measured .by the
schedule of values provided for in paragraph 14.1 of the General Conditions.
5.1.1 Prior to Substantial Completion, progress payments will be in an amount equal
to:
90% of the work completed until fifty percent (50%) of the work is
performed, after which no additional retainage shall be withheld, and
90% of materials and equipment not incorporated in the work but
delivered and suitably stored, less in each case the aggregate of
payments previously made.
5.1.2 Upon Substantial Completion, OWNER shall pay an amount sufficient to
,..r increase total payments to CONTRACTOR to 95% of the Contract Price, less
such amounts as ENGINEER shall determine in accordance with paragraph
14.7 of the General Conditions.
5.2 FINAL PAYMENT: Upon final completion and acceptance in accordance with
paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of
the Contract Price as recommended by ENGINEER as provided in said paragraph
14.13. The final payment shall not be made until after final settlement of this
contract has been duly advertised at least ten days prior to such final payment by
publication of notice thereof at least twice in a public newspaper of general
circulation published in Eagle County, and the Board of County Commissioners
has held a public hearing, thereupon and complied with the Revised Statutes
1973, Section 38-26-107 as amended. Final payment shall be made in
accordance with the requirements of aforesaid statute.
ARTICLE 6 - CONTRACTOR'S REPRESENTATIONS
In order to induce OWNER to enter into this Agreement CONTRACTOR makes the
following representations:
Agreement
Page 3
6.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract
Documents, work, locality, and with all local conditions, and federal, state, and
`"►' local laws, ordinances, rules and regulations that in any manner may affect cost,
progress, or performance of the work.
6.2 CONTRACTOR has studied carefully all reports of investigations and tests of
subsurface and latent physical conditions at the site or otherwise affecting cost,
progress, or performance of the work which were relied upon by ENGINEER in the
preparation of the Drawings and Specifications, and which have been identified in
the Supplementary Conditions.
6.3 CONTRACTOR has made, or caused to be made, examinations, investigations,
and tests and studies of such reports and related data in addition to those referred
to in paragraph 6.2 as he deems necessary for the performance of the work at the
Contract Price, within the Contract Time, and in accordance with other terms and
conditions of the Contract Documents; and no additional examinations,
investigations, tests, reports, or similar data are, or will be required by
CONTRACTOR for such purposes.
6.4 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, tests, reports, and data with the terms and conditions of the
Contract Documents.
'"Wp� 6.5 CONTRACTOR has given ENGINEER written notice of all conflicts, errors, or
discrepancies that he has discovered in the Contract Documents and the written
resolution thereof by ENGINEER is acceptable to CONTRACTOR.
ARTICLE 7 - CONTRACT DOCUMENTS
The Contract Documents which comprise the entire Agreement, made a part hereof, and
consist of the following:
7.1 This Agreement (Pages 1 to 6, inclusive).
7.2 Invitation to Bid consisting of 1 page.
7.3 , Instructions to Bidders (Pages 1 to 7, inclusive).
7.4 Performance and other Bonds, identified as exhibits , and consisting of
pages.
7.5 Notice of Award, Notice to Proceed.
Agreement
Page 4
7.6 General Conditions (Pages 1 to 50, inclusive).
Iftwo' 7.7 Specifications bearing. the title and consisting of 4 divisions and 8 pages,
as listed in the table of contents thereof.
7.8 Drawings, consisting of 10 sheets.
7.9 Addenda numbers to , inclusive.
7.10 Documentation submitted by CONTRACTOR prior to Notice of Award (Pages _
to , inclusive).
7.11 Any modification, including Change Orders, duly delivered after execution of
Agreement.
There are no Contract Documents other than those listed above in this Article 7. The
Contract Documents may only be altered, amended, or repealed by a Modification (as
defined in Section 1 of the General Conditions).
ARTICLE 8 - MISCELLANEOUS
8.1 The terms used in this Agreement which are defined in Article 1 of the General
Conditions shall have the meanings indicated in the General Conditions.
8.2 No assignment by a party hereto of any rights under, or interests in the Contract
Documents will be binding on. another party hereto without the written consent of
the party sought to be bound; and specifically, but without limitation, moneys that
may become due and moneys that are due may not be assigned without such
consent (except to the extent that the effect of this restriction may be limited by
law), and unless specifically stated to the contrary in any written consent to an
assignment, no assignment will release or discharge the assignor from any duty
or responsibility under the Contract Documents.
8.3 OWNER and CONTRACTOR each binds himself, his partners, successors,
assigns and legal representatives to the other party hereto, in respect to all
covenants, agreements, and obligations contained in the Contract Documents.
8.4 ATTORNEYS FEES: In the event of litigation between the parties hereto
regarding the interpretation of this Agreement, or the obligations, duties or rights
of the parties hereunder, or if suit otherwise is brought to recover damages for
breach of this Agreement, or an action be brought for injunction or specific
performance, then and in such events, the prevailing party shall recover all
Agreement
Page 5
reasonable costs incurred with regard to such litigation, including reasonable
attorney's fees.
8.5 APPLICABLE LAW: This Agreement shall be governed by the laws of the State
of Colorado. Jurisdiction and venue of any suit, right, or cause of action arising
under, or in connection with this Agreement shall be exclusive in Eagle County,
Colorado.
IN WITNESS WHEREOF, the parties hereto have signed this Agreement in triplicate. One
counterpart each has been delivered to OWNER, CONTRACTOR, and ENGINEER. All
portions of the Contract Documents have been signed or identified by OWNER and
CONTRACTOR, or by ENGINEER on their behalf.
This Agreement will be effective on / 1999.
OWNER: Eagle County Board of CONTRACTOR:
County Commissioners
BY:
ohnnette Phillips, Cha
V
ATTEST _dfl_a�
Address for giving notices:
Eagle County Board of
County Commissioners
P.O. Box 850
Eagle, Colorado 8163'
JT_(�
(CORPORATE SEAL)
Address fo giving notices:
Agreement Page 6
Bonds Executed in (4) Counterparts
N%./ AIA Document A312 %we
Performance Bond U2703805
../ Conforms with the American Institute of Architects, AIA Document A312.
Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
GONZALES CONSTRUCTION COMPANY, INC.
29996 Highway 184, Dolores, Colorado 81323
SURETY (Name and Principal Place of Business):
United Pacific Insurance Company
Three Parkway, 10th Floor, Philadelphia, PA 19102
OWNER (Name and Address):
Board of County Commissioners
Eagle County Colorado
P.O. Box 850 g��g�
C&SeT)tUCTION CONTRACT-0850
Date: April 19, 1999
Amount: Fifty -Five Thousand Four Hundred Thirty -Five and No/100-------- —---------- ($55,435.00)
Description (Name and Location): Eagle County 1999 Guardrail Project
BOND
Date (Not earlier than Construction Contract Date): April 29, 1999
Amount: Fifty -Five Thousand Four Hundred Thirty -Five and No/100-------------------- ($55,435.00)
Modifications to this Bond:
( TRACTOR AS PRINCIPAL
C'M*any: GONZALES CONSTRUCTION (Corporate Seal)
COMPANY, INC.
Signature:
Name and Title: Franki hales, President
(Any additional signorreelippear on page 2.)
(FOR INFORMATION ONLY - Name, Address and
Telephone) AGENT or BROKER: Lockton Companies of
Colorado, Inc., 4500 Cherry Creek Drive South, Suite 400
Denver, Colorado 80246-1532
1 The Contractor and the Surety, jointly and severally, bind themselves,
their heirs, executors, administrators, successors and assigns to the Owner for
the performance of the Construction Contract, which is incorporated herein
by reference.
2 If the Contractor performs the Construction Contract, the Surety and the
Contractor shall have no obligation under this Bond, except to participate in
conferences as provided in Subparagraph 3.1.
3 If there is no Owner Default, the Surety's obligation under this Bond
shall arise after:
3.1 The Owner has notified the Contractor and the Surety at its address
described in Paragraph 10 below that the Owner is considering
declaring a Contractor Default and has requested and attempted to
arrange a conference with the Contractor and the Surety to be held not
later than fifteen days after receipt of such notice to discuss methods of
performing the Construction Contract. If the Owner, the Contractor and
he Surety agree, the Contractor shall be allowed a reasonable time to
® None ❑ See Page 2
SURETY
Company: United Pacific Insurance (Corporate Seal)
Company
Signaturw—,-/,
Name and Title: Kimb rly ffJohnson, ttorney-in-Fact
OWNER'S REPRESENTATIVE (Architect, Engineer or other
part'):
perform the Construction Contract, but such an agreement shall
not waive the Owner's right, if any, subsequently to declare a
Contractor Default; and
3.2 The Owner has declared a Contractor Default and formally
terminated the Contractor's right to complete the contract. Such
Contractor Default shall not be declared earlier than twenty days
after the Contractor and the Surety have received notice as
provided in Subparagraph 3.1; and
3.3 The Owner has agreed to pay the Balance of the Contract
Price to the Surety in accordance with the terms of the
Construction Contract or to a contractor selected to perform the
Construction Contract in accordance with the terms of the
contract with the Owner.
4 When the Owner has satisfied the conditions of Paragraph 3, the
Surety shall promptly and at the Surety's expense take one of the
following actions:
SURETY 5026 (6-92)
S-1852/GEEF2/98 Page 1 of 2
4.1 Arrange for the Contractor, with consent Pr *he Owner, to perform
and complete the Construction Contract; or
4.2 Undertake to perform and complete thewt-,'onstruction Contract
itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors
1cceptable to the Owner for a contract for performance and
impletion of the Construction Contract, arrange for a contract to be
lqw�repared for execution by the Owner and the contractor selected with
the Owner's concurrence, to be secured with performance and payment
bonds executed by a qualified surety equivalent to the bonds issued on
the Construction Contract, and pay to the Owner the amount of
damages as described in Paragraph 6 in excess of the Balance of the
Contract Price incurred by the Owner resulting from the Contractor's
default; or
4.4 Waive its right to perform and complete, arrange for completion,
or obtain a new contractor and with reasonable promptness under the
circumstances:
.1 After investigation, determine the amount for which it
may be liable to the Owner and, as soon as practicable
after the amount is determined, tender payment therefor to
the Owner; or
.2 Deny liability in whole or in part and notify the Owner
citing reasons therefor.
5 If the Surety does not proceed as provided in Paragraph 4 with
reasonable promptness, the Surety shall be deemed to be in default on this
Bond fifteen days after receipt of an additional written notice from the
Owner to the Surety demanding that the -Surety perform its obligations
under this Bond, and the Owner shall be entitled to enforce any remedy
available to the Owner. If the Surety proceeds as provided in Subparagraph
4.4, and the Owner refuses the payment tendered or the Surety has denied
liability, in whole or in part, without further notice the Owner shall be
entitled to enforce any remedy available to the Owner.
6 After the Owner has terminated the Contractor's right to complete the
Construction Contract, and if the Surety elects to act under Subparagraph
4.1, 4.2, or 4.3 above, then the responsibilities of the Surety to the Owner
shall not be greater than those of the Contractor under the Construction
Contract, and the responsibilities of the Owner to the Surety shall not be
g- r than those of the Owner under the Construction Contract. To the
li..,,hf the amount of this Bond, but subject to commitment by the Owner
of -the Balance of the Contract Price to mitigation of costs and damages on
the Construction Contract, the Surety is obligated without duplication for:
6.1 The responsibilities of the Contractor for correction of defective
work and completion of the Construction Contract;
6.2 Additional legal, design professional and delay costs resulting
from the Contractor's Default, and resulting from the actions or failure
to act of the Surety under Paragraph 4; and
6.3 Liquidated damages, or if no liquidated damages are specified in
the Construction Contract, actual damages caused by delayed
performance or non-performance of the Contractor.
MODIFICATIONS TO THIS BOND ARE AS FOLLOWS:
7 The Surety shall not " liable to the Owner or others for obligations of
the Contractor that are !lated to the Construction Contract, and the
Balance of the ContracN�e shall not be reduced or set off on account of
any such unrelated obligations. No right of action shall accrue on this Bond
to any person or entity other than the Owner or its heirs, executors,
administrators or successors.
8 The Surety hereby waives notice of any change, including changes of
time, to the Construction Contract or to related subcontracts, purchase
orders and other obligations.
9 Any proceeding, legal or equitable, under this Bond may be instituted
in any court of competent jurisdiction in the location in which the work or
part of the work is located and shall be instituted within two years after
Contractor Default or within two years after the Contractor ceased working
or within two years after the Surety refuses or fails to perform its
obligations under this Bond, whichever occurs first. If the provisions of this
Paragraph are void or prohibited by law, the minimum period of limitation
available to sureties as a defense in the jurisdiction of the suit shall be
applicable.
10 Notice to the Surety, the Owner or the Contractor shall be mailed or
delivered to the address shown on the signature page.
11 When this Bond has been furnished to comply with a statutory or
other legal requirement in the location where the construction was to be
performed, any provision in this Bond conflicting with said statutory or
legal requirement deleted herefrom and provisions conforming to such
statutory or other legal requirement shall be deemed incorporated herein.
The intent is that this Bond shall be construed as a statutory bond and not
as a common law bond.
12 DEFINITIONS
12.1 Balance of the Contract Price: The total amount payable by the
Owner to the Contractor under the Construction Contract after all
proper adjustments have been made, including allowance to the
Contractor of any amounts received or to be received by the Owner in
settlement of insurance or other claims for damages to which the
Contractor is entitled, reduced by all valid and proper payments made
to or on behalf of the Contractor under the Construction Contract.
12.2 Construction Contract: The agreement between the Owner and
the Contractor identified on the signature page, including all Contract
Documents and changes thereto.
12.3 Contractor Default: Failure of the Contractor, which has
neither been remedied nor waived, to perform or otherwise to comply
with the terms of the Construction Contract.
12.4 Owner Default: Failure of the Owner, which has neither been
remedied nor waived, to pay the Contractor as required by the
Construction Contract or to perform and complete or comply with the
other terms thereof.
(Space is provided below for additional signatures of added parties, other than those appearing on the cover page.)
CONTRACTOR AS PRINCIPAL
Company:
mature:
Name and Title:
Address:
SURETY
(Corporate Seal) Company:
Signature:
Name and Title:
Address:
(Corporate Seal)
S-1852/GEEF 2198 Page 2 of 2
Bonds Executed in (4) Counterparts
`,r AIA Document A312 \r
U2703805
Payment Bond
Conforms with the American Institute of Architects, AIA Document A312.
Any singular reference to Contractor Surery, Owner or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
GONZALES CONSTRUCTION COMPANY, INC.
29996 Highway 184, Dolores, Colorado 81323
OWNER (Name and Address):
Board of County Commissioners
Eagle County Colorado
P.O. Box 850
Eagle, Colorado 81631-0850
CONSTRUCTION CONTRACT
SURETY (Name and Principal Place of Business):
United Pacific Insurance Company
Three Parkway, 10th Floor, Philadelphia, PA 19102
Date: April 19, 1999
Amount: Fifty -Five Thousand Four Hundred Thirty -Five and No/1 00 -------------------- ($55,435.00)
Description (Name and Location): Eagle County 1999 Guardrail Project
BOND
Date( Not earlier than Construction Contract Date): April 29, 1999
Amount: Fifty -Five Thousand Four Hundred Thirty -Five and No/100------------ —------ ($55,435.00)
Modifications to this Bond:
a� TRACTOR AS PRINCIPAL
L� any: GONZALES CONSTRUCTION (Corporate Seal)
COMPANY; INC. i1r
Signature: �fLG
Name and Title: Fran zales, President
(Any additional sigaatur pear on page 2.)
(FOR INFORMATION ONLY - Name, Address and
Telephone) AGENT or BROKER: Locaton Companies of
Colorado, Inc., 4500 Cherry Creek Drive South, Suite 400
Denver, Colorado 80246-1532
1 The Contractor and the Surety, jointly and severally, bind themselves,
their heirs, executors, administrators, successors and assigns to the Owner to
pay for labor, materials and equipment fumished for use in the performance
of the Construction Contract, which is incorporated herein by reference.
2 With respect to the Owner, this obligation shall be null and void if the
Contractor:
2.1 Promptly makes payment, directly or indirectly, for all sums due
Claimants, and
2.2 Defends, indemnifies and holds harmless the Owner from claims,
demands, liens or suits by any person or entity whose claim, demand,
lien or suit is for the payment for labor, materials or equipment
famished for use in the performance of the Construction Contract,
provided the Owner has promptly notified the Contractor and the
Surety (at the address described in Paragraph 12) of any claims,
demands, liens or suits and tendered defense of such claims, demands,
*m/ liens or suits to the Contractor and the Surety, and provided there is no
Owner Default.
® None
:Ytlt]3W4
❑ See Page 2
Company: United Pacific Insurance (Corporate Seal)
Company
Signet e
Name and Tit e: Kimbe ly . ohnson, or ey-in-Fact
OWNER'S REPRESENTATIVE (Architect, Engineer or other
party):
3 With respect to Claimants, this obligation shall be null and void if
the Contractor promptly makes payment, directly or indirectly, for all
sums due.
4 The Surety shall have no obligation to Claimants under this Bond
until:
4.1 Claimants who are employed by or have a direct contract with
the Contractor have given notice to the Surety (at the address
described in Paragraph 12) and sent a copy, or notice thereof, to
the Owner, stating that a claim is being made under this Bond and,
with substantial accuracy, the amount of the claim.
4.2 Claimants who do not have a direct contract with the
Contractor:
1 Have furnished written notice to the Contractor and sent a
copy, or notice thereof, to the Owner, within 90 days after
having last performed labor or last fumished materials or
equipment included in the claim stating, with substantial
accuracy, the amount of the claim and the name of the party
to whom the materials were fumished or supplied or for
whom the labor was done or performed; and
SURETY 5026 (6-92)
5-1653/GEEF 2/98 Page 1 of 2
.2 Have either received a rejection in wh or in part from the
Contractor, or not received within 3G,,,,,Is of furnishing the
above notice any communication from the Contractor by which
the Contractor has indicated the claim will be paid directly or
indirectly; and
3 Not having been paid within the above 30 days, have sent a
\*m,r written notice to the Surety (at the address described in
Paragraph 12) and sent a copy, or notice thereof, to the Owner
stating that a claim is being made under this Bond and
enclosing a copy of the previous written notice furnished to the
Contractor.
5 If a notice required by paragraph 4 is given by Owner to the
Contractor or to the Surety, that is sufficient compliance.
6 When the Claimant has satisfied the conditions of Paragraph 4, the
Surety shall promptly and at the Surety's expense take the following
actions:
6.1 Send an answer to the Claimant, with a copy to the Owner,
within 45 days after receipt of the claim, stating the amounts
that are undisputed and the basis for challenging any amounts
that are disputed.
6.2 Pay or arrange for payment of any undisputed amounts.
7 The Surety's total obligation shall not exceed the amount of this Bond,
and the amount of this Bond shall be credited for any payments made in
good faith by the Surety.
8 Amounts owed by the Owner to the Contractor under the Construction
Contract shall be used for the performance of the Construction Contract and
to satisfy claims, if any, under any Construction Performance Bond. By the
Contractor furnishing and the Owner accepting this Bond, they agree that
all funds earned by the Contractor in the performance of the Construction
Contract are dedicated to satisfy obligations of the Contractor and the
Surety under this Bond, subject to the Owner's priority to use the funds for
the completion of the work.
9 The Surety shall not be liable to the Owner, Claimants or others for
obligations of the Contractor that are unrelated to the Construction
C- :t. The Owner shall not be liable for payment of any costs or
exlprdes of any Claimant under this Bond, and shall have under this bond
no obligations to make payments to, give notices on behalf of, or otherwise
have obligations to Claimants under this Bond.
10 The Surety hereby waives notice of any change, including changes of
time, to the Construction Contract or to related subcontracts, purchase
orders and other obligations.
11 No suit or action shall be commenced by a Claimant under this Bond
other than in a court of competent jurisdiction in the location in which
MODIFICATIONS TO THIS BOND ARE AS FOLLOWS:
the work or part of the -k is located or after the expiration of one year
from the date (1) on �/ the Claimant gave the notice required by
Subparagraph 4. 1 or Clain 4.2.3, or (2) on which the last labor or service
was performed by anyone or the last materials or equipment were furnished
by anyone under the Construction Contract, whichever of (1) or (2) first
occurs. If the provisions of this Paragraph are void or prohibited by law,
the minimum period of limitation available to sureties as a defense in the
jurisdiction of the suit shall be applicable.
12 Notice to the Surety, the Owner or the Contractor shall be mailed or
delivered to the address shown on the signature page. Actual receipt of
notice by Surety, the Owner or the Contractor, however accomplished,
shall be sufficient compliance as of the date received at the address shown
on the signature page.
13 When this Bond has been furnished to comply with a statutory or other
legal requirement in the location where the construction was to be
performed, any provision in this Bond conflicting with said statutory or
legal requirement shall be deemed deleted herefrom and provisions
conforming to such statutory or other legal requirement shall be deemed
incorporated herein. The intent is that this Bond shall be construed as a
statutory bond and not as a common law bond.
14 Upon request by any person or entity appearing to be a potential
beneficiary of this Bond, the Contractor shall promptly furnish a copy of
this Bond or shall permit a copy to be made.
15 DEFINITIONS
15.1 Claimant: An individual or entity having a direct contract
with the Contractor or with a subcontractor of the Contractor to
furnish labor, materials or equipment for use in the performance of
the Contract. The intent of this Bond shall be to include without
limitation in terms "labor, materials or equipment" that part of water,
gas, power, light, heat, oil, gasoline, telephone service or rental
equipment used in the Construction Contract, architectural and
engineering services required for performance of the work of the
Contractor and the Contractor's subcontractors, and all other items for
which a mechanic's lien may be asserted in the jurisdiction where the
labor, materials or equipment were furnished.
15.2 Construction Contract: The agreement between the Owner
and the Contractor identified on the signature page, including all
Contract Documents and changes thereto.
15.3 Owner Default: Failure of the Owner, which has neither been
remedied nor waived, to pay the Contractor as required by the
Construction Contract or to perform and complete or comply with
the other terms thereof.
(Space is provided below for additional signatures of added parties, other than those appearing on the cover page.)
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corporate Seal) Company:
Siftwme: Signature:
Name and Title: Name and Title:
Address: Address:
(Corporate Seal)
S-18531GEEF 2/98 Page 2 of 2
RELIANCE SURETY COMPANY
sLIANCE INSURANCE COMPANY
UNITED PACIFIC INSURANCE COMPANY RELIANCE NATIONAL INDEMNITY COMPANY
ADMINISTRATIVE OFFICE, PHILADELPHIA, PENNSYLVANIA
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS, that RELIANCE SURETY COMPANY is a corporation duly organized under the laws of the State of Delaware,
and that RELIANCE INSURANCE COMPANY and UNITED PACIFIC INSURANCE COMPANY, are corporations duly organized under the laws of the
Commonwealth of Pennsylvania and that RELIANCE NATIONAL INDEMNITY COMPANY is a corporation duly organized under the laws of the Slate of
Wisconsin (herein collectively called "the Companies") and that the Companies by virtue of signature and seals do hereby make, constitute and appoint
Debbie Poppe, William M. O'Connell, Jr., Sarah Finn, Sue Wood, Brad C. Gibson, Kimberly D. Johnson, Shelley Czajkowski, of Denver,
Colorado their true and lawful Attomey(s)-in-Fact, to make, execute, seal and deliver for and on their behalf, and as their act and deed any and all
bonds and undertakings of suretyship and to bind the Companies thereby as fully and to the same extent as if such bonds and undertakings and other
writings obligatory in the nature thereof were signed by an Executive Officer of the Companies and sealed and attested by one other of such officers, and
hereby ratifies and confirms all that their said Attomey(s)-in-Fad may do in pursuance hereof.
This Power of Attorney is granted under and by the authority of Article VII of the By -Laws of RELIANCE SURETY COMPANY, RELIANCE
INSURANCE COMPANY, UNITED PACIFIC INSURANCE COMPANY, and RELIANCE NATIONAL INDEMNITY COMPANY which provisions are now in
full force and effect, reading as follows:
ARTICLE VII - EXECUTION OF BONDS AND UNDERTAKINGS
1. The Board of Direamm, the President, the Chairman of the Board, any Senior Vice Presdem, any Vice President or Assistant Vice President or rather officer designeand by the Board of Directors shall have
power and authority to (a) appoint Atrorney(s)-in-Fan and to authorize them to execs¢ on behalf of the Company, bolls and undmmkings, recogniances, contracts of indemnity and other writings obligatory in the netare
thereof, and (b) I. remove any such Aumneyu)-in-Fact at my time and revoke he power and authority given to them.
2. Anorce h)-in-Fact shall have power and authority, subject to the terms and limitations of the Ponver of Anorncy issued to them, to execute all deliver on behalf of the Company, bonds and undertakings,
recrogniarces, contracts of indemnity and other writings obligatory in the nature thereof. The corporate seal is tort necessary for the validity of any bonds and underukings remgniesnces, contracts of indemnity and other
writinp,s obligatory, in the nature thereof.
d. Atu rnens)-in-Fact aball have we, all authority to exaeum affidavits required to be attached to bonds, recvgnianam, contracts of indemnity or other conditions] or obligatory undertakings and they shall
also have power and authority to certify the financial smmmcnt of dse Company and to copies of the By -Laws of the Company or any article or section thereof.
This Power of Attorney is sigrudi and sealed by facsimile under and by authority of the following resolution adopted by the Executive all Finance Committees of the Boards of Directors of Reliance Iran.= Company,
United Pacific Imutancc Company all Reliance National Indemnity Company by Unanimous Comem dated as, of February 29. 19%1 and by the Executive and Financial Committee of die Board of Direcmrs of Rcharnee
Surety Company by Unanimous Consent dated as of Mardi 2I, 1990.
-Resolved that the signatures of such director and M. and the seal of the Company may nd strand many such Power of Attorney or any «nifinam relating thereto by facsimile, all any such
Power of Attorney or certif te bearing such facsimile signesures or facsimile sal shill be valid all billing upon the Company aid any such Power so executed aril ceniftd by facsimile sigmmres
all facsimile sal shall be valid and binding upon do, Co.,,. in she future with respect to any bond or undertaking I. which it is attached.'
IN WITNESS WHEREOF, the Companies have caused these presents to be signed and their corporate seals to be hereto affixed, this June 9, 1998.
RELIANCE SURETY COMPANY
0*00
,„au.�, `o�µ,,goEbRELIANCE INSURANCE COMPANY
UNITED PACIFIC INSURANCE COMPANY
u wPtt�"' _�SEAL'"2nRELIANCE NATIONAL NDEMNITY COMPANY
SEAL _iy 41959� s°q, ra y0�jy�`9CON5�D My b . n
STATE OF Washington } �!2/4� 410. Ate
— e
COUNTY OF King ) SS.
On this, June 9, 1998, before me, Laura L. Wadsworth, personally appeared Mark W. Alsup , who acknowledged himself to be the Vice President of
the Reliance Surety Company, Reliance Insurance Company, United Pacific Insurance Company, and Reliance National Indemnity Company and that as
such, being authorized to do so, executed the foregoing instrument for the purpose therein contained by signing the name of the corporation by himself as
its duly authorized officer.
In witness whereof, I hereunto set my hand and official seal.
Notary Public in and for the State of Washington
Residing at Puyallup
I, Robyn Laying, Assistant Secretary of RELIANCE SURANY, RELIANCE INSURANCE COMPANY, UNITED PACIFIC INSURANCE
COMPANY, and RELIANCE NATIONAL INDEMNITY COMPANY do hereby certify that the above and foregoing is a true and correct copy of the Power
2f Attorney executed by said Companies, which is still in full force and effect.
N WITNESS WHEREOF, I have hereunto set my hand and affixed the seals of said Companies this 29 day of April year of 1999
eURfry <MayRa_ 4pp Oggp 4trPPOa�)*(a
° CSEA' - _—SEATp99840£°°atnwnwe 1''^ranvrss�
6��
Assistant Secretary
acoRo
. �
DATE
BNCO01 04/28/9 9
PRODUCER
THIS CERTIFICATE IS ED AS A MATTER OF INFORMATION
'
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
Lockton Companies of Colorado
4500 Cherry Creek Dr. S . , #400
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
D--ver CO 80246-1532
COMPANIES AFFORDING COVERAGE
�j
Phone No. 303-753-2000 Fax No. 303-753-2099
COMPANY
A C 4A Insurance Companies
INSURED
COMPANY
B
COMPANY
Gonzales Construction Co., Inc
C
29996 Hwy 184 M1
Dolores CO 81323
COMPANY
D
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
CO
LTR
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE
DATE (MM/DD/YY)
POLICY EXPIRATION
DATE (MM/DD/YY)
LIMITS
GENERAL LIABILITY
GENERAL AGGREGATE
$2 , 000, 000
A
X COMMERCIAL GENERAL LIABILITY
CBP1076733347
03/01/99
03/01/00
PRODUCTS -COMPIOPAGG
52,000,000
CLAIMS MADE FRI OCCUR
PERSONAL BADVINJURY
$1,000,000
EACH OCCURRENCE
S 1 , 000 , 000
OWNER'S & CONTRACTOR'S PROT
FIRE DAMAGE (Any one fire)
$ 3 0 0, 0 0 0
MED EXP (Any one person)
$ 10 0 0 0
AUTOMOBILE
LIABILITY
ANY AUTO
COMBINED SINGLE LIMIT
$
BODILY INJURY
(Per person)
$
ALL OWNED AUTOS
SCHEDULED AUTOS
BODILY INJURY
(Per accident)
_
HIRED AUTOS
NON -OWNED AUTOS
PROPERTY DAMAGE
$
GARAGE LIABILITY
AUTO ONLY - EA ACCIDENT
$
OTHER THAN AUTO ONLY:
ANY AUTO
EACH ACCIDENT
$
AGGREGATE
$
EXCESS LIABILITY
EACH OCCURRENCE
_
AGGREGATE
$
UMBRELLA FORM
$
OTHER THAN UMBRELLA FORM
WORKERS COMPENSATION AND
EMPLOYERS' LIABILITY
I WC STATU• I OTH.
TORY LIMITS ER
EL EACH ACCIDENT
$
THE PROPRIETOR/ INCL
PARTNERSIEXECUTIVE
EL DISEASE - POLICY LIMIT
$
EL DISEASE - EA EMPLOYEE
$
OFFICERS ARE: EXCL
OTHER
A
Hired, Leased or
CBP1076733347
03/01/99
03/01/00
Item $300,000
Borrowed Equipment
Deduct $500
DESCRIPTION OF OPERATIONSILOCATIONSIVEHICLES!SPECIAL ITEMS
Eagle County 1999 Guardrail Project. Board of Count Commisioners, Eagle
County, CO is named as Additional Insured as respecys Liability coverage for
work performed by the Insured.
CERTIFICATE HOLDER
CANCELLATION
BOAC007 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL AIL
Board of County Commissioners
30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
1*4001' Eagle County, Colorado
P.O. Box 850
Eagle CO 81631
AUTHORIkED REPRESENTATIVE
ACORD 25-S (1/95 1
GC`i� ' V ` `>e�V3�D C PORATION 1988
*M/
'.w
Engineering Department
(970) 328-8760
FAX (970) 328-7185
TDD (970) 328-8797
April 19, 1999
EAGLE COUNTY. COLORADO
NOTICE OF AWARD
Gonzales Construction Company, Inc.
29996 Hwy 184
Dolores, CO 81323
Re: Eagle County 1999 Guardrail Project
NWW
Eagle County Building
P.O. Box 850
500 Broadway
Eagle, Colorado 81631-0850
Please be notified that on April 19, 1999 the Eagle County Board of County
Commissioners awarded the above referenced project to Gonzales Construction Company,
Inc. in the amount of $55,435.00.
Enclosed please find four counterparts of the contract documents including the agreement.
In accordance with Section 18 of the Instructions to Bidders, you are to execute all four
counterparts of the Agreement, attach the Payment Bond, Performance Bond, and Proof
of Insurance required by the documents, and return all four counterparts to Eagle County
within fifteen (15) days.
EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS
Phillips, Chairman
cc: James R. Fritze, County Attorney
George Roussos, County Engineer
Brad Higgins, Road & Bridge Director
\40000
`/
...
Engineering Department
(970)328-8760
FAX (970) 328-7185
TDD (970) 328.8797
EAGLE COUNTY, COLORADO
INVITATION TO BID
1999 GUARDRAIL PROJECT
Eagle County Building
P.O. Box 850
500 Broadway
Eagle, Colorado 81631-0850
Eagle County will receive sealed bids for the 1999 Guardrail Project until 11:30am, April
6, 1999 in the office of the Eagle County Engineering Department, 500 Broadway, Eagle,
Colorado 81631 at which time bids will be opened and read aloud. Bidding documents
may be obtained at the Eagle County Engineering Department. Each bid shall be
accompanied by Bid Security in accordance with the Instructions to Bidders.
GUARDRAIL CAD 16.35 MILE MARKER ON THE FRYING PAN RIVER ROAD # 104
EAGLE COUNTY, COLORADO
NOTES:
1) 150 L.F. TOTAL
SEE C.D.O. I - M & S STANDARDS (M-606-1)
FOR DETAILS.
2) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
3) RE -USE EXISTING 3E END SECTIONS AT ANOTHER LC
4) USE CORE 10 RAIL.
� CL�
(PULL-OUT)
m
FR-y-MG
EXISTING GUARDRAIL
(1:1 SLOPE, 75' DROP)
ar 1w er. WBH D IE. J110199
04rcm er. PTs DRAWNG Na: GUARDRL 96
38 sy fr 1 or 9
{
EXISTING GUARDRAIL
(1:1 SLOPE. 20' DROP)
INSTALL 150 L.F. NEW GUARDRAIL
REMOVE EXISTING END SECTIONS
do JOIN EXISTING GUARDRAIL
(1:1 SLOPE. 100' DROP)
GUARDRAIL 0 16.6 MILE MARKER ON FRYING PAN RIVER ROAD # 104
EAGLE COUNTY COLORADO
1) 550 L.F. TOTAL WITH TWO - 3E END SECTIONS
SEE C.D.O.T. M & S STANDARDS (M-606-1) FOR DETAILS.
2) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
3) USE CORE 10 RAIL.
f
IIVJIALL JJV L.r. IYGn vVrUwllnil me" ITw - ..PL. L-119 LF .,rwIwow
ORAMN ". WSH
DAM JIIO11999
aaEc o er. PTS
aRAIM.- Na. GUARDRL 96
_ F.38
wrrr ?_ nr .9
L
lTy PWAM RY:
Rums CDUNTY
RN(;DOT MC; DEPARTMENT
TARDRAIL LOCATION MAP
D
1999
0
6
5
5 EGEND
P_
21
2z
23 SUTS,, CoMff.. OR f0WJF XAi7i AUM ROADS
O
vm
SPRIS 70 HTERSTATE HOHEAY
RESET
2 UNnw STATES HiHMAYS
Q
® STATE HNMAYS
w
z
22
26 NTERSTATE 70
LL_
i• -
STATE HMMAY
ROAD MMUC DR PRMATE)
Q
a MUNTANS A: PEAKS
f ^
V
33
N
35
AO
2 2Y�, SYLVAPI LAPE
STATE /
2 1 6 Ylv ' RECRD TIO
EA `
ROAD LAKE
9
to
RD
1 LEDE G �T
6 RES., 10 11
12
,
CREEK
6
N
SPI C�
16
15
p 18 15 to 13
PN T ry
��/t
1
23
9
O
2,
22
20 21 22 25 24
19
20
26
27
MTN.
28
'
29 26 22 26 25
J E
30
Ilk
29
L
33
3
35
32 33 34 35
.
3
2 C 31
A
32
U)
IS
5 . 3 2
6
9
10
10 n 12
2
Z
j e
m
R 87
N
R 84 W R
83 IN
.65, 17.86, 19.41 & 20.07
3TIONS, 3,900 L.F. TOTAL)
GUARDRAIL 0 16.8 MILE MARKER ON THE FRYING PAN RIVER ROAD # 104
EAGLE COUNTY, COLORADO
REPLACE 250 L.F. OF EXISTING GUARDRAIL
WITH TWO — 3E END SECTIONS
BEGINNING AT THIS END
REMOVE 275 L.F. OF EXISTING GUARDRAIL
4
O
O
INSTALL 125 L.F. OF NEW GUARDRAIL
WITH ONE — 3E END SECTION
REPLACE 225 L.F. OF EXISTING GUARDRAIL
WITH ONE — 3E END SECTION
NOTES:
1) 600 L.F. TOTAL WITH FOUR — 3E END SECTIONS
SEE C.D.O.T. M & S STANDARDS (M-606-1)
FOR DETAILS.
2) ALL OLD GUARD RAIL TO BE REMOVED AND
TRANSPORTED TO AN AREA DESIGNATED BY
EAGLE COUNTY ENGINEER.
3) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
4) USE CORE 10 RAIL.
DRAW Or. WBH
OAM 311011999
P rs
GUARDRL196
cHrcxw er
aaAWNG Na:
&%Q AOA, E38
sv rr 3 or 9
1 "= 60'
GUARDRAIL 0 17.25 MILE MARKER ON FRYING PAN RIVER ROAD # 104
EAGLE COUNTY, COLORADO
f
1
i
i
/ P o
INSTALL 300 L.F. NEW GUARDRAIL
WITH TWO — 3E END SECTIONS
(1.5 : 1 SLOPE, 60' DROP)
NOTES:
1) 300 L.F. TOTAL WITH TWO - 3E END SECTIONS
SEE C.D.O.T. M & S STANDARDS (M-606-1)
FOR DETAILS.
2) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
I3) USE CORE 10 RAIL
ORAUN B» WBH
DAM J11011999
CHECM er PTS
DRANWO Na: GUARDRL 96
_ .. _ E38
&vrrr 4 or 9
GUARDRAIL 0 17.45 MILE MARKER ON THE FRYING PAN RIVER ROAD # 104
EAGLE COUNTY, COLORADO
INSTALL 25 L.F. NEW GUARDRAIL
WITH ONE — 3E END SECTION f'
a
o
REPLACE 90 L.F. EXISTING GUARDRAIL---"_
INSTALL 10 L.F. NEW GUARDRAIL
WITH ONE — 3E END SECTION
�Ql
*,-�—EXISTING,'GUARDRAIL TO REMAIN +
�A
NOTES:
1) 125 L.F. TOTAL WITH TWO - 3E END SECTIONS
SEE C.D.O.T. M & S STANDARDS (M-606-1)
FOR DETAILS. #`
2) ALL OLD GUARD RAIL TO BE REMOVED AND
TRANSPORTED TO AN AREA DESIGNATED BY
EAGLE COUNTY ENGINEER.
3) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
4) USE CORE 10 RAIL.
WBH
311011999
ORAON er
CA7E-
CHECAIn er. prs
a4AWNc Ha: GUARORL 96
Alw on E38
s wrr 5 a- 9
1"=60'
3 rA
GUARDRAIL ® 17.653 MILE MARKER ON THE FRYING PAN RIVER ROAD # 104
��LOR EAGLE COUNTY, COLORADO
\ A„
INSTALL 650 L.F. NEW GUARDRAIL
\ \ WITH TWO - 3E END SEC11ONS
1 =60
NOTES: \
1) .650 L.F. TOTAL WITH TWO - 3E END SECTIONS \ \
SEE C.D.O.T. M & S STANDARDS (M-606-1) \
FOR DETAILS. \
2) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL \
30" ABOVE FINISH GRADE OF EXISTING ASPHALT. \
3) USE CORE 10 RAIL. \
Fhr
DRAW Br. WBH \
\
\
\
DAYr' .3/10/1999
PTS
GUARDRL/96
df£CKO or
MAWNG NQ:
E38
smErr 6 or 9
GUARDRAIL 0 17.861 MILE MARKER ON THE FRYING PAN RIVER ROAD # 104
EAGLE COUNTY, COLORADO
EMBANKMENT
�R
1"=60'
NOTES:
1) 150 L.F. TOTAL WITH TWO -
SEE C.D.O.T. M & S STANDA
FOR DETAILS.
2) INSTALL THE GUARDRAIL WI1
30" ABOVE FINISH GRADE 0
3) USE CORE 10 RAIL.
skin,
DRAW Or. RDH
DAB 311011999
cmrc*w or PTS
aRAwmc Na. GUARDRL 96
— .1 , E38
mirr 7 a- 9
L.F. NEW GUARDRAIL
3E END SECTIONS
'GUARDRAIL 0 19.4 MILE MARKER ON THE FRYING PAN RIVER ROAD # 104
EAGLE COUNTY, COLORADO
1 "=60'
I
a
z
a
0
REPLACE 400 L.F. OF GUARDRAIL
WITH TWO — 3E END SECTIONS
BEGINNING AT THIS END
'/r
REMOVE 400 L.F. OF GUARDRAIL
,z
AbSO
/ G i
REPLACE 400 L.F. OF GUARDRAIL
WITH ONE — 3E END SECTION
INSTALL 75 L.F. OF NEW GUARDRAIL
WITH ONE — 3E END SECTION
NOTES:
1) 875 L.F. TOTAL WITH FOUR - 3E END SECTIONS
SEE C.D.O.T. M & S STANDARDS (M-606-1)
FOR DETAILS.
2) ALL OLD GUARD RAIL TO BE REMOVED AND
TRANSPORTED TO AN AREA DESIGNATED BY
EAGLE COUNTY ENGINEER.
3) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
4) USE CORE 10 RAIL.
DRANN Br. WBH
DAM 311011990
arMCAID BY` PTs
DRAWW „fa; GUARDRL 96
„, ,,,, , E38
-wtrr 8 a,- 9
GUARDRAIL 0 20.072 MILE MARKER ON THE FRYING PAN RIVER ROAD 104
EAGLE COUNTY, COLOR AD 0
EOANKMENT�, `•
1 "=60'
INSTALL 500 L.F. NEW GUARDRAIL
WITH TWO — 3E END SECTIONS
O
NOTES:
1) 500 L.F. TOTAL WITH TWO — 3E END SECTIONS \
i SEE C.D.O.T. M & S STANDARDS (M-606-1)
FOR DETAILS. ` \
2) INSTALL THE GUARDRAIL WITH THE TOP OF RAIL
30" ABOVE FINISH GRADE OF EXISTING ASPHALT.
PULL—OUT
3) USE CORE 10 RAIL. \
EAGLE COUNTY
4) USE 7' POSTS WHEN NECESSARY. /
CRAM Or weH DAM 3/10/1999 PITKIN COUNTY LINE
CHEcav er: PTS ARAWNG NQ: GUARDRL196
E- 38 9 c� 9
M,
Dgjfijj�ON�
Orl
4. contract Boo
3.
!9�es �to.-
L Accounting
2.
3.
4.,