Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutC02-256 M.A. Mortenson1
AGREEMENT
THIS AGREEMENT is dated as of the,�day of � the year 2002 by and between
Board of County Commissioners
Eagle County, Colorado
(hereinafter called OWNER)
and
M.A. Mortenson
OWNER and CONTRACTOR, in consideration of the mutual covenants set forth, agree as
follows:
ARTICLE 1 - WORK
CONTRACTOR shall complete all work as specified or indicated in the Contract Documents.
The work is generally described as follows:
Construction of the bus wash modification as identified in the design drawings.
ARTICLE 2 - ENGINEER
The Project has been designed by Alpine Engineering, Inc., and will assume all duties and
responsibilities, and will have the rights and authority assigned to ENGINEER in the Contract
Documents in connection with completion of the work in accordance with the Contract
Documents.
ARTICLE 3 - CONTRACT TIME
3.1 The work will commence on the date set forth in the Notice to Proceed no later than
September 15 and will be substantially completed by November 1, 2002 and .ready for
final payment in accordance with paragraph 14.13 of the General Conditions on or
before November 15, 2002
3.2 LIQUIDATED DAMAGES: OWNER and CONTRACTOR recognize that time is of
the essence of this Agreement and that OWNER will suffer financial loss if the work is
not substantially complete within the time specified in paragraph 3.1 above, plus any
extensions thereof allowed in accordance with Article 12 of the General Conditions.
They also recognize the delays, expense, and difficulties involved in proving a legal or
arbitration proceeding the actual loss suffered by OWNER if the work is not
substantially complete on time. Accordingly, instead of requiring such proof, OWNER
and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty)
CONTRACTOR shall pay OWNER N/A dollars ($ N/A ) for
each day that expires after the time specified in paragraph 3.1 for substantial completion
until the work is substantially complete.
ARTICLE 4 - CONTRACT PRICE
4.1 The funds appropriated for this project are equal to or in excess of the contract amount.
OWNER shall pay CONTRACTOR for performance of the work in accordance with the
Contract Documents in current funds as follows:
Design $ 4,600.00
Construction cost $47,844.00
Total $52)444.00
ARTICLE 5 - PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions.
5.1 PROGRESS PAYMENTS: OWNER shall make monthly progress payments on
account of the Contract Price on the basis of CONTRACTOR's Applications for
Payments All progress payments will be on the basis of the progress of the work
measured by the schedule of values provided for in paragraph 14.1 of the General
Conditions.
5.1.1 Prior to Substantial Completion, progress payments will be in an amount equal to:
90% of the work completed until fifty percent (50%) of the work is
performed, after which no additional retainage shall be withheld, and
90% of materials and equipment not incorporated in the work but delivered
and suitably stored, less in each case the aggregate of payments previously
made.
5.1.2 Upon Substantial Completion, OWNER shall pay an amount sufficient to increase
total payments to CONTRACTOR to 95% of the Contract Price, in accordance
5.2 FINAL PAYMENT: Upon final completion and acceptance in accordance with
paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the
Contract Price as provided in said paragraph 14.13. The final payment shall not be
made until after final settlement of this contract has been duly advertised at least ten
days prior to such final payment by publication of notice thereof at least twice in a
public newspaper of general circulation published in Eagle County, and the Board of
County Commissioners has held a public hearing, thereupon and complied with the
Revised Statutes 1973, Section 38-26-107 as amended. Final payment shall be made in
accordance with the requirements of aforesaid statute.
ARTICLE 6 - CONTRACTOR'S REPRESENTATIONS
In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following
representations:
6.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract
Documents, work, locality, and with all local conditions, and federal, state, and local
laws, ordinances, rules and regulations that in any manner may affect cost, progress, or
performance of the work.
6.2 CONTRACTOR has studied carefully all reports of investigations and tests of
subsurface and latent physical conditions at the site or otherwise affecting cost,
progress, or performance of the work which were relied upon by ENGINEER in the
preparation of the Drawings and Specifications, and which have been identified in the
Supplementary Conditions.
6.3 CONTRACTOR has made, or caused to be made, examinations, investigations, and
tests and studies of such reports and related data in addition to those referred to in
paragraph 6.2 as he deems necessary for the performance of the work at the Contract
Price, within the Contract Time, and in accordance with other terms and conditions of
the Contract Documents; and no additional examinations, investigations, tests, reports,
or similar data are, or will be required by CONTRACTOR for such purposes.
6.4 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, tests, reports, and data with the terms and conditions of the Contract
Documents.
6.5 CONTRACTOR has given Owner written notice of all conflicts, errors, or discrepancies
that he has discovered in the Contract Documents and the written resolution thereof by
Owner is acceptable to CONTRACTOR.
ARTICLE 7 - CONTRACT DOCUMENTS
The Contract Documents which comprise the entire Agreement, made a part hereof, and consist
of the following:
7.1 This Agreement (Pages 1 to 6, inclusive).
7.2 Amendment Number One dated July 26, 2002 from M.A. Mortenson.
7.3 Notice to Proceed.
7.4 General Conditions (Pages 1 to 49, inclusive).
7.5 Drawings, as prepared by Alpine Engineering, Inc, and dated July 25, 2002.
7.6 Any modification, including Change Orders, duly delivered after execution of
Agreement.
There are no Contract Documents other than those listed above in this Article 7. The Contract
Documents may only be altered, amended, or repealed by a Modification (as defined in Section 1
of the General Conditions).
ARTICLE 8 - MISCELLANEOUS
8.1 The terms used in this Agreement which are defined in Article 1 of the General
Conditions shall have the meanings indicated in the General Conditions.
8.2 No assignment by a party hereto of any rights under, or interests in the Contract
Documents will be binding on another party hereto without the written consent of the
party.sought to be bound; and specifically, but without limitation, moneys that may
become due and moneys that are due may not be assigned without such consent (except
to the extent that the effect of this restriction may be limited by law), and unless
specifically stated to the contrary in any written consent to an assignment, no
assignment will release or discharge the assignor from any duty or responsibility under
the Contract Documents.
8.3 OWNER and CONTRACTOR each binds himself, his partners, successors, assigns and
legal representatives to the other party hereto, in respect to all covenants, agreements,
and obligations contained in the Contract Documents.
8.4 ATTORNEY'S FEES: In the event of litigation between the parties hereto regarding the
interpretation of this Agreement, or the obligations, duties or rights of the parties
hereunder, or if suit otherwise is brought to recover damages for breach of this
Agreement, or an action be brought for injunction or specific performance, then and in
such events, the prevailing party shall recover all reasonable costs incurred with regard
to such litigation, including reasonable attorney's fees.
8.5 APPLICABLE LAW: This Agreement shall be governed by the laws of the State of
Colorado. Jurisdiction and venue of any suit, right, or cause of action arising under, or
in connection with this Agreement shall be exclusive in Eagle County, Colorado.
IN WITNESS WHEREOF, the parties hereto have signed this Agreement in triplicate. One
counterpart each has been delivered to OWNER, CONTRACTOR. All portions of the Contract
Documents have been signed or identified by OWNER and CONTRACTOR on their behalf.
This Agreement will be effective oalzo6 2002.
OWNER: Eagle County Board of
County Commissioners
BY:
Chairman
Address for giving notices:
Eagle County Board of
County Commissioners
P.O. Box 850
Eagle, Colorado 81631
CONTRAC • M. A. Mortenson Company
BY:
Senior Vice President
®� (CORPORATE SEAL)
O0 RP9�
ST
Address for giving notices:
11. A. Mortenson Company
700 Meadow Lane North
Minneapolis. MN 55422
GENERAL CONDITIONS
ARTICLE 1 - DEFINITIONS
Wherever used in these general conditions or in the other Contract Documents, the following
terms have the meanings indicated which are applicable to both the singular and plural thereof:
ADDENDA: Written or graphic instruments issued prior to the opening of bids which
clarify, correct, or change the bidding documents or the contract documents.
AGREEMENT: The written agreement between OWNER and CONTRACTOR
covering the work to be performed; other contract documents are attached to the
agreement and made a part thereof as provided therein.
APPLICATION FOR PAYMENT: The form accepted by Owner which is to be used
by CONTRACTOR in requesting progress or final payment, and which is to include
such supporting documentation as is required by the contract documents.
BID: The offer or proposal of the bidder submitted on the prescribed form setting forth
the prices for the work to be performed.
BONDS: Bid, performance, and payment bonds, and other instruments of security.
CHANGE ORDER: A written order to CONTRACTOR signed by OWNER
authorizing an addition, deletion, or revision in the work, or an adjustment in the
contract price or the contract time issued after the effective date of the agreement.
CONTRACT DOCUMENTS: The Agreement, Addenda (which pertain to the
contract documents), CONTRACTOR'S Bid (including documentation accompanying
the bid and any post -bid documentation submitted prior to the Notice of Award) when
attached as an exhibit to the Agreement, the Bonds, these General Conditions, the
Supplementary Conditions, the Specifications, the Drawings, as the same are more
specifically identified in the Agreement, together with all Modifications issued after the
execution of the Agreement.
CONTRACT PRICE: The monies payable by OWNER to CONTRACTOR under the
contract documents as stated in the agreement.
CONTRACT TIME: The number of days (computed as provided in paragraph 16.2),
or the date stated in the agreement for the completion of the work.
General Conditions Page 1
CONTRACTOR: The person, firm, or corporation with whom OWNER has entered
into the agreement.
DAY: A calendar day of twenty-four hours measured from midnight to the next
midnight.
DEFECTIVE: An adjective which, when modifying the word "work", refers to work
that is unsatisfactory, faulty or deficient, or does not meet the requirements of any
inspection, test, or approval referred to in the contract documents, or has been damaged
prior to OWNERS recommendation of final payment or prior to guarantee period under
paragraph 13.12.
DRAWINGS: The drawings which show the character and scope of the work to be
performed, and which have been prepared or approved by Alpine Engineering, and are
referred to in the contract documents.
EFFECTIVE DATE OF THE AGREEMENT: The date indicated in the agreement
on which it becomes effective, but, if no such date is indicated, it means the date on
which the agreement is signed and delivered by the last of the two parties to sign and
deliver.
ENGINEER: The person, firm, or corporation named as such in the Agreement. The
Engineer in such case shall exercise his duties in conformance with the standards
applicable to independent professional engineers.
FIELD ORDER: A written order issued by Owner which orders minor changes in the
work in accordance with paragraph 10.2, but which does not involve a change in the
contract price or the contract time.
GENERAL REQUIREMENTS: Sections of Division 1 of the Specifications.
MODIFICATION: (a) A written amendment of the contract documents signed by both
parties, (b) a change order, or (c) a field order. A modification may only be issued after
the effective date of the agreement.
NOTICE OF AWARD: The written notice by OWNER to the apparent successful
bidder stating that upon compliance by the apparent successful bidder with the
conditions precedent enumerated therein, within the time specified, OWNER will sign
and deliver the agreement.
NOTICE TO PROCEED: A written notice given by OWNER to CONTRACTOR R)
fixing the date on which the contract time will commence to run, and on which
CONTRACTOR shall start to perform his obligation under the contract documents.
General Conditions Page 2
8 1 16
J
OWNER: The public body or authority, corporation, association, partnership, or
individual with whom CONTRACTOR has entered into the agreement, and for whom
the work is to be provided.
PROJECT: The total construction of which the work to be provided under the contract
documents may be the whole or a part, as indicated elsewhere in the contract
documents.
RESIDENT PROJECT REPRESENTATIVE: The authorized representative of
Richard Cunningham Director, Facilities Management Department, who is assigned to
the site or any part thereof.
SHOP DRAWINGS: All drawings, diagrams, illustrations, schedules, and other data
which are specifically prepared by CONTRACTOR, a subcontractor, manufacturer,
fabricator, supplier, or distributor to illustrate some portion of the work, and all
illustrations, brochures, standard schedules, performance charts, instructions, diagrams,
and other information prepared by a manufacturer, fabricator, supplier, or distributor
and submitted by CONTRACTOR to illustrate material or equipment for some portion
of the work.
SPECIFICATIONS: Those portions of the contract documents consisting of written
technical descriptions of materials, equipment, construction systems, standards, and
workmanship as applied to the work, and certain administrative details applicable
thereto.
SUBSTANTIAL COMPLETION: The work (or a specified part thereof] has
progressed to the point where, as evidenced by his definitive certificate of substantial
completion, it is sufficiently complete, in accordance with the contract documents, so
that the work (or specified part) can be utilized for the purposes for which it was
intended; or if there be no such certificate issued, when final payment is due in
accordance with paragraph 14.13. The terms "substantially complete" and
"substantially completed" as applied to any work refer to substantial completion thereof.
WORK: The entire completed construction or the various separately identifiable parts
thereof required to be furnished under the contract documents. Work is the result of
performing services, furnishing and incorporating materials and equipment into all
construction, all as required by the contract documents.
General Conditions Page 3
a 1 J6
d
ARTICLE 2 - PRELIMINARY MATTERS
DELIVERY OF BONDS:
2.1 When CONTRACTOR delivers the executed agreements to OWNER, CONTRACTOR
shall also deliver to OWNER such bonds as CONTRACTOR may be required to furnish
in accordance with paragraph 5.1.
COPIES OF DOCUMENTS:
2.2 OWNER shall furnish to CONTRACTOR up to ten copies (unless otherwise specified
in the general requirements) of the contract documents as are reasonably necessary for
the execution of the work. Additional copies will be furnished, upon request, at the cost
of reproduction.
COMMENCEMENT OF CONTRACT TIME; NOTICE TO PROCEED:
2.3 The Contract Time will commence to run on the thirtieth day after the effective date of
the Agreement, or if a Notice to Proceed is given, on the day indicated in the Notice to
Proceed; but in no event shall the Contract Time commence to run later than the sixtieth
day after the day of bid opening, or the thirtieth day after the effective date of the
Agreement. A Notice to Proceed may be given at any time within thirty days after the
effective date of the Agreement.
STARTING THE PROJECT:
2.4 CONTRACTOR shall start to perform the work on the date when the Contract Time
commences to run, but no work shall be done at the site prior to the date on which the
Contract Time commences to run.
BEFORE STARTING CONSTRUCTION:
2.5 Before undertaking each part of the work, CONTRACTOR shall carefully study and
compare the Contract Documents and check and verify pertinent figures shown thereon
and all applicable field measurements. CONTRACTOR shall promptly report in
writing to Owner any conflict, error, or discrepancy which CONTRACTOR may
discover; however, CONTRACTOR shall not be liable to OWNER for failure to report
any conflict, error, or discrepancy in the Drawings or Specifications, unless
CONTRACTOR had actual knowledge thereof, or should reasonably have known
thereof.
General Conditions Page 4
2.6 Within ten days after the effective date of the Agreement (unless otherwise specified in
the general requirements) CONTRACTOR shall submit to Owner for review and
acceptance an estimated progress schedule indicating the starting and completion dates
of the various stages of the work, a preliminary schedule of shop drawings submissions,
and a preliminary schedule of values of the Work.
2.7 Before any work at the site is started, CONTRACTOR shall deliver to OWNER,
certificates of insurance (and other evidence of insurance requested by OWNER) which
CONTRACTOR is required to purchase and maintain in accordance with paragraphs
5.3, 5.4, 5.5, 5.6, and 5.7.
PRE -CONSTRUCTION CONFERENCE:
2.8 Within twenty days after the effective date of the Agreement, but before
CONTRACTOR starts the work at the site, a conference will be held for review and
acceptance of the schedules referred to in paragraph 2.6, to establish procedures for
handling shop drawings and other submittals, and for processing applications for
payment, and to establish a working understanding among the parties as to the Work.
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT AND REUSE
INTENT:
3.1 The Contract Documents comprise the entire agreement between OWNER and
CONTRACTOR concerning the work. They may be altered only by a Modification.
3.2 The Contract Documents are complementary; what is called for by one is as binding as
if called for by all. If, during the performance of the Work, CONTRACTOR finds a
conflict, error, or discrepancy in the Contract Documents, he shall report it to OWNER
in writing at once and before proceeding with the Work affected thereby; however,
CONTRACTOR shall not be liable to OWNER for failure to report any conflicts, error,
or discrepancy in the Specifications or Drawings unless CONTRACTOR had actual
knowledge thereof, or should reasonably have known thereof.
3.3 It is the intent of the specifications and drawings to describe a complete project (or part
thereof) to be constructed in accordance with the contract documents. Any work that
may reasonably be inferred from the specifications or drawings as being required to
produce the intended result shall be supplied whether or not it is specifically called for.
When words which have a well known technical or trade meaning are used to describe
work, materials, or equipment, such words shall be interpreted in accordance with such
meaning. References to codes of any technical society, organization, or association, or
to the code of any governmental authority, whether such reference be specific or by
General Conditions
Page 5
implication, shall mean the latest standard specification, manual, or code in effect at the
time of opening of bids (or on the effective date of the agreement if there were no bids),
except as may be otherwise specifically stated. However, no provision of any
referenced standard specification, manual, or code (whether or not specifically
incorporated by reference in the contract documents) shall change the duties and
responsibilities of OWNER, CONTRACTOR, or any of their agents or employees from
those set forth in the contract documents. Clarifications and interpretations of the
contract documents shall be issued by OWNER as provided for in paragraph 9.3.
3.4 The contract documents will be governed by the law of the place of the project.
REUSE OF DOCUMENTS:
3.5 Neither CONTRACTOR nor any subcontractor, manufacturer, fabricator, supplier, or
distributor shall have or acquire any title to or ownership rights in any of the drawings,
specifications, or other documents (or copies of any thereof) prepared by or bearing the
seal of ENGINEER; and they shall not reuse any of them on extensions of the project,
or any other project, without written consent of OWNER and specific written
verification or adaptation by ENGINEER.
ARTICLE 4 - AVAILABILITY OF LANDS: PHYSICAL CONDITIONS:
REFERENCE POINTS
AVAILABILITY OF LANDS:
4.1 OWNER shall furnish, as indicated in the contract documents, the lands upon which the
work is to be performed, rights -of -way for access thereto, and such other lands which
are designated for the use of CONTRACTOR. Easements for permanent structures, or
permanent changes in existing facilities, will be obtained and paid for by OWNER,
unless otherwise provided in the contract documents. If CONTRACTOR believes that
any delay in OWNER'S furnishing these lands or easements entitles him to an extension
of the contract time, CONTRACTOR may make a claim therefore as provided in Article
12. CONTRACTOR shall provide for all additional lands and access thereto that may
be required for temporary construction facilities or storage of materials and equipment.
PHYSICAL CONDITIONS - INVESTIGATIONS AND REPORTS:
4.2 Reference is made to the supplementary conditions for identification of those reports of
investigations and tests of subsurface and latent physical conditions at the site or
otherwise affecting cost, progress, or performance of the work which have been relied
upon by ENGINEER in preparation of the drawings and specifications. Such reports
are not part of the contract documents.
General Conditions
Page 6
�4�
UNFORESEEN PHYSICAL CONDITIONS:
4.3 CONTRACTOR shall promptly notify OWNER in writing of any subsurface or latent
physical conditions at the site or in an existing structure differing materially from those
indicated or referred to in the contract documents. ENGINEER will promptly review
those conditions and advise OWNER in writing if further investigation or tests are
necessary. Promptly thereafter, OWNER shall obtain the necessary additional
investigations and tests, and furnish copies to ENGINEER and CONTRACTOR. If
ENGINEER finds that the results of such investigations or tests indicate that there are
subsurface or latent physical conditions which differ materially from those intended in
the contract documents, and which could not reasonably have been anticipated by
CONTRACTOR, a change order shall be issued incorporating the necessary revisions.
REFERENCE POINTS:
4.4 OWNER shall provide engineering surveys for construction to establish reference points
which in his judgement are necessary to enable CONTRACTOR to proceed with the
work. CONTRACTOR shall be responsible for laying out the work (unless otherwise
specified in the general requirements), shall protect and preserve the established
reference points, and shall make no changes nor relocations without the prior written
approval of OWNER. CONTRACTOR shall report to ENGINEER whenever any
reference point is lost or destroyed or requires relocation because of necessary changes
in grades or locations, and shall be responsible for replacement or relocation of such
reference points by professionally qualified personnel.
ARTICLE 5 - BONDS AND INSURANCE
PERFORMANCE AND OTHER BONDS:
5.1 N/A.
5.2 N/A
INSURANCE:
5.3 CONTRACTOR'S Liability Insurance: The CONTRACTOR shall purchase and
maintain such insurance as will protect him from claims set forth below which may
arise out of or result from the CONTRACTOR'S operations under the contract, whether
such operations be by himself, or by any subcontractor, or by anyone directly or
indirectly employed by any of them, or by anyone for whose acts any of them may be
liable.
General Conditions Page 7
All such insurance shall remain in effect until final payment, and at all times thereafter
when CONTRACTOR may be correcting, removing, or replacing defective work in
accordance with paragraph 13.12. In addition, CONTRACTOR shall maintain such
completed operations insurance for at least two years after final payment, and furnish
OWNER with evidence of continuation of such insurance at final payment and one year
thereafter.
5.3.1 Claims under Workmen's Compensation, disability benefits, and other similar
employee benefit acts;
5.3.2 Claims for damage because of bodily injury, occupational sickness or disease, or
death of his employees, and claims insured by usual personal injury liability
coverage;
5.3.3 Claims for damage because of bodily injury, sickness or disease, or death of any
person other than his employees, and claims insured by usual personal injury
liability coverage; and
5.3.4 Claims for damages because of injury to or destruction of tangible property,
including loss of use resulting therefrom.
Workmen's Compensation insurance shall provide coverage as required by the laws of
the State of Colorado.
Insurance covering claims for damages to persons or property required by the preceding
paragraph (except subparagraph 5.3.1) shall be in the following minimum amounts:
Bodily Injury Liability:
Each Person: $ 5003,000
Each Accident or Occurrence: $ I,000,000
Property Damage Liability:
Each Accident or Occurrence: $ 500,000
Aggregate: $1MUM
and shall be furnished in types specified as follows:
5.3.5 CONTRACTOR'S Liability Insurance issued to and covering the liability for
damage imposed by law upon the CONTRACTOR and each subcontractor with
respect to all work performed by them under the agreement (construction contract).
5.3.6 CONTRACTOR'S Protective Liability Insurance issued to and covering the
liability for damages imposed by law upon the CONTRACTOR and each
General Conditions Page 8
lw�
subcontractor with respect to all work under the agreement (construction contract)
performed for the CONTRACTOR by subcontractors.
5.3.7 Completed Operations Liability Insurance issued to and covering the liability for
damage imposed by law upon the CONTRACTOR and each subcontractor arising
between the date of final cessation of the work, and the date of final acceptance
thereof out of that part of the work performed by each.
5.3.8 Comprehensive Automobile Insurance shall be carried in the amount of
$5001,00051,000,000 for bodily injury and $500,000 for property damage, each
occurrence. All liability and property damage insurance required hereunder shall
be Comprehensive General and Automobile Bodily Injury and Property Damage
form of policy.
5.3.9 The CONTRACTOR shall in addition, and in the amounts required under the
above, obtain protective Liability Insurance issued to and covering the liability for
damages imposed by law upon the OWNER with respect to all operations under the
construction contract by the CONTRACTOR or his subcontractors, including
omissions and supervisory acts by the OWNER.
5.4 Comprehensive Risk Policy Option: In lieu of the several policies specified for
CONTRACTOR's Liability Insurance, a comprehensive liability and property damage
insurance policy inclusive of all the insurance and requirements hereinafter set forth,
with an umbrella covering of $1,000,000, subject to the approval of the OWNER, will
be permissible.
5.5 Subcontractor's Insurance: Before permitting any of his subcontractors to perform any
work under this contract, CONTRACTOR shall either (a) require each of his
subcontractors to procure and maintain during the life of his subcontracts,
Subcontractor's Public Liability and Property Damage Insurance of the types and in the
amounts as may be applicable to his work, which type and amounts shall be subject to
the approval of the OWNER (Eagle County), or (b) insure the activities of his
subcontractors in his own policy.
5.6 Certificates of Insurance: Certificates of Insurance acceptable to the OWNER shall be
filed with the OWNER prior to commencement of the work. These Certificates shall
contain provisions naming the OWNER as an additional insured under
CONTRACTOR'S insurance, as more fully required by the General Conditions herein,
and that coverage afforded under the policies will not be cancelled until at least thirty
days prior written notice has been given the OWNER. CONTRACTOR and his
subcontractors shall not permit any of his subcontractors to start work until all required
insurance have been obtained and certificates with the proper endorsements have been
filed with the OWNER. Failure of the CONTRACTOR to comply with the foregoing
General Conditions Page 9
insurance requirements shall in no way waive the OWNER'S rights hereunder.
5.7 Owner's Liability Insurance: The OWNER, at his option, may purchase and maintain
such liability insurance as will protect him against claims which may arise from
operations under this contract. Purchasing and maintaining such insurance, however,
will not relieve the CONTRACTOR from purchasing and maintaining the insurance
hereinbefore specified.
5.8 Loss of Use Insurance: The OWNER, at his option, may purchase and maintain such
insurance as will insure him against loss of use of his property due to fire or other
hazards, however caused.
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES
SUPERVISION AND SUPERINTENDENCE:
6.1 CONTRACTOR shall supervise and direct the work competently and efficiently,
devoting such attention thereto and applying such skills and expertise as may be
necessary to perform the work in accordance with the contract documents.
CONTRACTOR shall be solely responsible for the means, methods, techniques,
sequences, and procedures of construction, but CONTRACTOR shall not be solely
responsible for the negligence of others in the design or selection of a specific means,
method, technique, sequence, or procedure of construction which is indicated in and
required by the contract documents. CONTRACTOR shall be responsible to see that
the finished work complies accurately with the contract documents.
6.2 CONTRACTOR shall keep on the work at all times during its progress a competent
resident superintendent, who shall not be replaced without written notice to OWNER
except under extraordinary circumstances. The superintendent will be
CONTRACTOR'S representative at the site and shall have authority to act on behalf of
CONTRACTOR. All communications given to the superintendent shall be as binding
as if given to CONTRACTOR.
LABOR, MATERIALS AND EQUIPMENT:
6.3 CONTRACTOR shall provide competent, suitably qualified personnel to survey and lay
out the work, and perform construction as required by the contract documents.
CONTRACTOR shall at all times maintain good discipline and order at the site. Except
in connection with the safety or protection of persons, or the work, or property at the
site or adjacent thereto, and except as otherwise indicated in the supplementary
conditions, all work at the site shall be performed during regular working hours and
General Conditions
Page 10
CONTRACTOR will not permit overtime work or the performance of work on
Saturday, Sunday, or any legal holiday without OWNER'S written consent.
6.4 Colorado labor shall be employed to perform the work to the extent of not less than
eighty percent of each type or class of labor in the several classifications of skilled and
common labor employed on the project. "Colorado labor" means any person who is a
resident of the state of Colorado, at the time of employment, without discrimination as
to race, color, creed, sex, age, or religion except when sex or age is a bona fide
occupational qualification.
6.5 CONTRACTOR shall furnish all materials, equipment, labor, transportation,
construction equipment and machinery, tools, appliances, fuel, power, light, heat,
telephone, water, and sanitary facilities, and all other facilities and incidentals necessary
for the execution, testing, initial operation, and completion of work.
6.6 All materials and equipment shall be of good quality and new, except as otherwise
provided in the contract documents. If required by CONTRACTOR shall furnish
satisfactory evidence (including reports of required test) as to the kind and quality of
materials and equipment.
6.7 All materials and equipment shall be applied, installed, connected, erected, used,
cleaned, and conditioned in accordance with the instructions of the applicable
manufacturer, fabricator, supplier, or distributor, except as otherwise provided in the
contract documents.
EQUIVALENT MATERIALS AND EQUIPMENT:
6.8 Whenever materials or equipment are specified or described in the drawings or
specifications by using the name of a proprietary item, or the name of a particular
manufacturer, fabricator, supplier, or distributor, the naming of the item is intended to
establish the type, function, and quality required. Unless the name is followed by words
indicating that no substitution is permitted, materials or equipment of other
manufacturers, fabricators, suppliers, or distributors may be accepted by ENGINEER if
sufficient information is submitted by CONTRACTOR to allow OWNER to determine
that the material or equipment proposed is equivalent to that named. The procedure for
review by OWNER will be as set forth in paragraphs 6.7.1 and 6.7.2 below as
supplemented in the general requirements.
6.8.1 Requests for review of substitute items of material and equipment will not be
accepted by OWNER from anyone other than CONTRACTOR. If
CONTRACTOR wishes to furnish or use a substitute item of material or
equipment, CONTRACTOR shall make written application to OWNER for
acceptance thereof, certifying that the proposed substitute will perform adequately
General Conditions
Page 11
the functions called for by the general design, be similar and of equal substance to
that specified and be suited to the same use and capable of performing the same
function as that specified. The application will state whether or not acceptance of
the substitute for use in the work will require a change in the drawings or
specifications to adapt the design to the substitute and whether or not incorporation
or use of the substitute in connection with the work is subject to payment of any
license fee or royalty. All variations of the proposed substitute from that specified
shall be identified in the application and available maintenance, repair and
replacement service will be indicated. The application will also contain an
itemized estimate of all costs or savings that will result directly or indirectly from
acceptance of such substitute, including costs of redesign and claims of other
contractors affected by the resulting change, all of which shall be considered by
OWNER in evaluating the proposed substitute. OWNER may require
CONTRACTOR to furnish, at CONTRACTOR'S expense, additional data about
the proposed substitute. OWNER will be the sole judge of acceptability, and no
substitute will be ordered or installed without OWNERS prior written acceptance.
OWNER may require CONTRACTOR to furnish, at CONTRACTOR'S expense, a
special performance guarantee or other surety with respect to any substitute.
6.8.2 ENGINEER will record time required by ENGINEER and ENGINEER'S
consultants in evaluating substitutions proposed by CONTRACTOR and in making
changes in the drawings or specifications occasioned thereby, whether or not
ENGINEER accepts a proposed substitute. CONTRACTOR shall reimburse
OWNER for the charges of ENGINEER and ENGINEER'S consultants for
evaluating any proposed substitute.
CONCERNING SUBCONTRACTORS:
6.9 CONTRACTOR shall not employ any subcontractor or other person or organization
(including those who are to furnish the principal items of materials or equipment),
whether initially or as a substitute, against whom OWNER may have reasonable
objection. A subcontractor or other person or organization identified in writing to
OWNER by CONTRACTOR prior to the Notice of Award, and not objected to in
writing by OWNER prior to the Notice of Award, will be deemed acceptable to
OWNER. Acceptance of any subcontractor, other person or organization by OWNER
shall not constitute a waiver of any right of OWNER to reject defective work. If
OWNER, after due investigation, has reasonable objection to any subcontractor, other
person or organization proposed by CONTRACTOR after the Notice of Award,
CONTRACTOR shall submit an acceptable substitute, and the contract price shall be
increased or decreased by the difference in cost occasioned by such substitution, and an
appropriate change order shall be issued. CONTRACTOR shall not be required to
employ any subcontractor, other person or organization against whom CONTRACTOR
has reasonable objection.
General Conditions
Page 12
6.10 CONTRACTOR shall be fully responsible for all acts and omissions of his
subcontractors, and of persons and organizations directly or indirectly employed by
them, and of persons and organizations for whose acts any of them may be liable to the
same extent that CONTRACTOR is responsible for the acts and omissions of persons
directly employed by CONTRACTOR. Nothing in the contract documents shall create
a contractual relationship between OWNER and any subcontractor or other person or
organization having a direct contract with CONTRACTOR, nor shall it create any
obligation on the part of OWNER to pay or to see to the payment of any monies due any
subcontractor, or other person or organization, except as may otherwise be required by
law. OWNER may furnish to any subcontractor or other person or organization, to the
extent practicable, evidence of amounts paid to CONTRACTOR on account of specific
work done.
6.11 The divisions and sections of the specifications and the identifications of any drawings
shall not control CONTRACTOR in dividing the work among subcontractors, or
delineating the work to be performed by any specific trade.
6.12 All work performed for CONTRACTOR by a subcontractor will be pursuant to an
appropriate agreement between CONTRACTOR and the subcontractor which
specifically binds the subcontractor to the applicable terms and conditions of the
contract documents for the benefit of the OWNER. CONTRACTOR shall pay each
subcontractor a just share of any insurance monies received by CONTRACTOR on
account of losses under policies issued pursuant to paragraph 5.6.
PATENT FEES AND ROYALTIES:
6.13 CONTRACTOR shall pay all license fees and royalties, and assume all costs incident to
the use in the performance of the work, or the incorporation in the work of any
invention, design, process, product, or device which is the subject of patent rights or
copyrights held by others. If a particular invention, design, process, product, or device
is specified in the contract documents for use in the performance of the work, and if to
the actual knowledge of OWNER its use is subject to patent rights or copyrights calling
for the payment of any license fee or royalty to others, the existence of such rights shall
be disclosed by OWNER in the contract documents. CONTRACTOR shall indemnify
and hold harmless OWNER and anyone directly or indirectly employed by either of
them from and against all claims, damages, losses, and expenses (including attorney's
fees) arising out of any infringement of patent rights or copyrights incident to the use in
the performance of the work, or resulting from the incorporation in the work of any
invention, design, process, product, or device not specified in the contract documents,
and shall defend all such claims in connection with any alleged infringement of such
rights.
General Conditions
Page 13
PERMITS:
6.14 Unless otherwise provided in the supplementary conditions, CONTRACTOR shall
obtain and pay for all construction permits and licenses. OWNER shall assist
CONTRACTOR, when necessary, in obtaining such permits and licenses.
CONTRACTOR shall pay all governmental charges and inspection fees necessary for
the prosecution of the work, which are applicable at the time of opening of bids.
CONTRACTOR shall pay all charges of utility service companies for connections to the
work, and OWNER shall pay all charges of such companies for capital costs related
thereto.
LAWS AND REGULATIONS:
6.15 CONTRACTOR shall give all notices and comply with all laws, ordinances, rules, and
regulations applicable to the work. If CONTRACTOR observes that the specifications
or drawings are at variance therewith, CONTRACTOR shall give prompt written notice
thereof, and any necessary changes shall be adjusted by an appropriate modification. If
CONTRACTOR performs any work knowing, or having reason to know, that it is
contrary to such laws, ordinances, rules, and regulations, and without such notice to
OWNER, CONTRACTOR shall bear all costs arising therefrom; however, it shall not
be CONTRACTOR'S primary responsibility to make certain that the specifications and
drawings are in accordance with such laws, ordinances, rules, and regulations.
TAXES:
6.16 Eagle County is tax exempt.
USE OF PREMISES:
6.17 CONTRACTOR shall confine construction equipment, the storage of materials and
equipment, and the operations of workmen to areas permitted by law, ordinances,
permits, or the requirements of the contract documents, and shall not unreasonably
encumber the premises with construction equipment or other materials or equipment.
6.18 During the progress of the work, CONTRACTOR shall keep the premises free from
accumulations of waste materials, rubbish, and other debris resulting from the work. At
the completion of the work, CONTRACTOR shall remove all waste materials, rubbish,
and debris from and about the premises as well as all tools, appliances, construction
equipment, and machinery, and surplus materials, and shall leave the site clean and
ready for occupancy by OWNER. CONTRACTOR shall restore to their original
condition those portions of the site not designated for alteration by the contract
documents.
General Conditions
Page 14
M
6.19 CONTRACTOR shall not load, nor permit any part of any structure to be loaded, in any
manner that will endanger the structure, nor shall CONTRACTOR subject any part of
the work or adjacent property to stresses or pressures that will endanger it.
RECORD DOCUMENTS:
6.20 CONTRACTOR shall keep one record copy of all specifications, drawings, addenda,
modifications, shop drawings, and samples at the site in good order and annotated to
show all changes made during the construction process. These shall be available to
OWNER for examination and shall be delivered to OWNER upon completion of the
work.
SAFETY AND PROTECTION:
6.21 CONTRACTOR shall be responsible for initiating, maintaining, and supervising all
safety precautions and programs in connection with the work. CONTRACTOR shall
take all necessary precautions for the safety of, and shall provide the necessary
protection to prevent damage, injury, or loss to:
6.21.1 all employees on the work and other persons who may be affected thereby,
6.21.2 all the work and all materials or equipment to be incorporated therein, whether in
storage on or off the site, and
6.21.3 other property at the site, or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, and utilities not designated for removal,
relocation or replacement in the course of construction. CONTRACTOR shall
comply with all applicable laws, ordinances, rules, regulations, and orders of any
public body having jurisdiction for the safety of persons or property, or to protect
them from damage, injury, or loss; and shall erect and maintain all necessary
safeguards for such safety and protection. CONTRACTOR shall notify owners of
adjacent property and utilities when prosecution of the work may affect them. All
damage, injury, or loss to any property referred to in paragraph 6.20.2 or 6.20.3
caused, directly or indirectly, in whole or in part, by CONTRACTOR, any
subcontractor, or anyone directly or indirectly employed by any of them, or anyone
for whose acts any of them may be liable, shall be remedied by CONTRACTOR
(except damage or loss attributable to the fault of drawings or specifications, or to
the acts or omissions of OWNER or anyone employed by either of them, or
anyone for whose acts either of them may be liable, and not attributable, directly or
indirectly, in whole or in part, to the fault or negligence of CONTRACTOR).
CONTRACTOR'S duties and responsibilities for the safety and protection of the
work shall continue until such time as all the work is completed in accordance with
paragraph 14.13, that the work is acceptable.
General Conditions Page 15
6.22 CONTRACTOR shall designate a responsible member of his organization at the site
whose duty shall be the prevention of accidents. This person shall be CONTRACTOR's
superintendent, unless otherwise designated in writing by CONTRACTOR to OWNER.
EMERGENCIES:
6.23 In emergencies affecting the safety or protection of persons, or the work, or property at
the site or adjacent thereto, CONTRACTOR, without special instruction or
authorization from OWNER, is obligated to act to prevent threatened damage, injury, or
loss. CONTRACTOR shall give OWNER prompt written notice of any significant
changes in the work, or deviations from the contract documents caused thereby.
SHOP DRAWINGS AND SAMPLES:
6.24 After checking and verifying all field measurements, CONTRACTOR shall submit to
OWNER for review and approval, in accordance with the accepted schedule of shop
drawing submissions (see paragraph 2.8), five copies (unless otherwise specified in the
general requirements) of all shop drawings, which shall have been checked by, and
stamped with the approval, of CONTRACTOR, and identified as ENGINEER may
require. The data shown on the shop drawings will be complete with respect to
dimensions, design criteria, materials of construction, and like information to enable
ENGINEER to review the information as required.
6.25 CONTRACTOR shall also submit to OWNER for review and approval, with such
promptness as to cause no delay in work, all samples required by the contract
documents. All samples will have been checked by, and stamped with the approval, of
CONTRACTOR, identified clearly as to material, manufacturer, and any pertinent
catalog numbers, and the use for which intended.
6.26 At the time of each submission, CONTRACTOR shall, in writing, call ENGINEER'S
attention to any deviations that the shop drawings or samples may have from the
requirements of the contract documents.
6.27 ENGINEER will review and approve, with reasonable promptness, shop drawings and
samples, but ENGINEER'S review and approval shall be only for conformance with the
design concept of the project, and for compliance with the information given in the
contract documents, and shall not extend to means, methods, sequences, techniques, or
procedures of construction, or to safety precautions or programs incident thereto. The
review and approval of a separate item as such will not indicate approval of the
assembly in which the item functions. CONTRACTOR shall make any corrections
required by ENGINEER, and shall return the required number of corrected copies of
shop drawings, and resubmit new samples for review and approval. CONTRACTOR
shall direct specific attention in writing to revisions other than the corrections called for
General Conditions Page 16
\ftwp� �J
by ENGINEER on previous submittals. CONTRACTOR'S stamp of approval on any
shop drawing or sample shall constitute a representation to OWNER and ENGINEER
that CONTRACTOR has either determined and verified all quantities, dimensions, field
construction criteria, materials catalog numbers, and similar data, or assumes full
responsibility for doing so, and that CONTRACTOR has reviewed or coordinated each
shop drawing or sample with the requirements of the work and the contract documents.
6.28 Where a shop drawing or sample is required by the specifications, no related work shall
be commenced until the submittal has been reviewed and approved by ENGINEER.
6.29 ENGINEER'S review and approval of shop drawings or samples shall not relieve
CONTRACTOR from responsibility for any deviations from the contract documents
unless CONTRACTOR has, in writing, called ENGINEER'S attention to such deviation
at the time of submission, and ENGINEER has given written concurrence and approval
to the specific deviation, nor shall any concurrence or approval by ENGINEER relieve
CONTRACTOR from responsibility for errors or omissions in the shop drawings.
CONTINUING THE WORK:
6.30 CONTRACTOR shall carry on the work and maintain the progress schedule during all
disputes or disagreements with OWNER. No work shall be delayed or postponed
pending resolution of any disputes or disagreements, except as CONTRACTOR and
OWNER may otherwise agree in writing.
INDEMNIFICATION:
6.31 To the fullest extent permitted by law, CONTRACTOR shall indemnify and hold
harmless OWNER, and their agents and employees, from and against all claims
damages, losses, and expenses including, but not limited to, attorney's fees arising out
of, or resulting from, the performance of the work, provided that any such claim,
damage, loss, or expense (a) is attributable to bodily injury, sickness, disease, or death,
or to injury to or destruction of tangible property (other than the work itself) including
the loss of use resulting therefrom, and (b) is caused, in whole or in part, by any
negligent act or omission of CONTRACTOR, any subcontractor, anyone directly or
indirectly employed by any of them, or anyone for whose acts any of them may be
liable, regardless of whether or not it is caused in part by a party indemnified hereunder.
6.32 In any and all claims against OWNER, or any of their agents or employees, by any
employee of CONTRACTOR, any subcontractor, anyone directly or indirectly
employed by any of them, or anyone for whose acts any of them may be liable, the
indemnification obligation under paragraph 6.30 shall not be limited in any way by any
limitation on the amount or type of damages, compensation, or benefits payable by or
for CONTRACTOR or any subcontractor under worker's or workmen's compensation
General Conditions Page 17
acts, disability benefit acts, or other employee benefit acts.
6.33 The obligations of CONTRACTOR under paragraph 6.30 shall not extend to the
liability of ENGINEER, his agents, or employees arising out of the preparation or
approval of maps, drawings, opinions, reports, surveys, change orders, designs, or
specifications.
General Conditions Page 18
ARTICLE 7 - WORK BY OTHERS
7.1 OWNER may perform additional work related to the project by himself, or have
additional work performed by utility service companies, or let other direct contracts
therefor which shall contain general conditions similar to these. CONTRACTOR shall
afford the utility service companies and the other contractors who are parties to such
direct contracts (or OWNER, if OWNER is performing the additional work with
OWNER'S employees) reasonable opportunity for the introduction and storage of
materials and equipment, and the execution of work, and shall properly connect and
coordinate his work with theirs.
7.2 If any part of CONTRACTOR'S work depends, for proper execution or results, upon the
work of any such other contractor or utility service company (or OWNER),
CONTRACTOR shall inspect and promptly report to ENGINEER in writing any patent
or apparent defects or deficiencies in such work that render it unsuitable for such proper
execution and results. CONTRACTOR'S failure to so report shall constitute an
acceptance of the other work as fit and proper for integration with CONTRACTOR'S
work, except for latent or nonapparent defects and deficiencies in the other work.
7.3 CONTRACTOR shall do all cutting, fitting, and patching of his work that may be
required to make its several parts come together properly and integrate with such other
work. CONTRACTOR shall not endanger any work of others by cutting, excavating, or
otherwise altering their work, and will only cut or alter their work with the written
consent of ENGINEER and the others whose work will be affected.
7.4 If the performance of additional work by other contractors or utility service companies
or OWNER was not noted in the contract documents, written notice thereof shall be
given to CONTRACTOR prior to starting any such additional work. If
CONTRACTOR believes that the performance of such additional work by OWNER or
others involves additional expense to CONTRACTOR, or requires an extension of the
contract time, CONTRACTOR may make a claim therefor as provided in Articles I I
and 12.
ARTICLE 8 - OWNER'S RESPONSIBILITIES
8.1 OWNER shall issue all communications to CONTRACTOR.
8.2 In case of termination of the employment of ENGINEER, OWNER shall appoint an
engineer whose status under the contract documents shall be that of the former
ENGINEER.
General Conditions Page 19
ARTICLE 9 - ENGINEER'S STATUS DURING CONSTRUCTION
OWNER'S REPRESENTATIVE:
9.1 Richard Cunningham, Director of Facilities Management, will be OWNER'S
representative during the construction period. The duties and responsibilities and the
limitations of authority as OWNER'S representative during construction are set forth in
the contract documents, and shall not be extended without written consent of OWNER.
CLARIFICATIONS AND INTERPRETATIONS:
9.2 ENGINEER will issue, with reasonable promptness, such written clarifications or
interpretations of the contract documents (in the form of drawings or otherwise) as
ENGINEER may determine necessary, which shall be consistent with, or reasonably
inferable from, the overall intent of the contract documents.
If CONTRACTOR believes that a written clarification or interpretation justifies an
increase in the contract price or contract time, CONTRACTOR may make a claim
therefor, as provided in Article 11 or Article 12.
REJECTING DEFECTIVE WORK:
9.3 OWNER will have authority to disapprove or reject work which is defective, and will
also have authority to require special inspection or testing of the work as fabricated,
installed, or completed.
SHOP DRAWINGS, CHANGE ORDERS, AND PAYMENTS:
9.4 In connection with Engineer's responsibility for shop drawings and samples, see
paragraphs 6.23 through 6.29 inclusive.
9.5 In connection with OWNER'S responsibilities as to change orders, see Articles 10, 11,
and 12.
9.6 In connection with OWNER'S responsibilities in respect to applications for payment,
etc., see Article 14.
General Conditions
Page 20
PROJECT REPRESENTATION:
9.7 OWNER may utilize a Resident Project Representative to assist ENGINEER in
observing the performance of the work. The duties, responsibilities, and limitations of
authority of any such Resident Project Representative and assistants will be as provided
in the supplementary conditions. If OWNER designates another agent to represent him
at the site who is not ENGINEER'S agent, the duties, responsibilities, and limitations of
authority of such other person will be as provided in the supplementary conditions.
DECISIONS ON DISAGREEMENTS:
9.8 OWNER will be the initial interpreter of the requirements of the contract documents
and judge of the acceptability of the work thereunder. Claims, disputes, and other
matters relating to the acceptability of the work, or the interpretation of the requirements
of the contract documents pertaining to the execution and progress of the work, shall be
referred initially to OWNER in writing with a request for a formal decision which
OWNER will render in writing within a reasonable time.
LIMITATIONS ON ENGINEER'S RESPONSIBILITIES:
9.9 Neither OWNER'S authority to act under this Article 9, or elsewhere in the contract
documents, nor any decision made by ENGINEER in good faith either to exercise or not
exercise such authority shall give rise to any duty or responsibility of ENGINEER to
CONTRACTOR, any subcontractor, any manufacturer, fabricator, supplier, or
distributor, or any of their agents or employees, or any other person performing any of
the work.
9.10 Whenever, in the contract documents, the terms "as ordered", "as directed", "as
required", "as allowed", or terms of like effect or import are used, or the adjectives
"reasonable", "suitable", "acceptable", "proper", or "satisfactory", or adjectives of like
effect or import are used to describe requirement, direction, review, or judgement of
OWNER as to the work, it is intended that such requirement, direction, review, or
judgement will be solely to evaluate the work for compliance with the contract
documents (unless there is a specific statement indicating otherwise). The use of any
such term or adjective never indicates that OWNER shall have authority to supervise or
direct performance of the work, or authority to undertake responsibility contrary to the
provisions of paragraphs 9.12 or 9.13.
9.11 OWNER will not be responsible for CONTRACTOR'S means, methods, techniques,
sequences or procedures of construction, or the safety precautions and programs
incident thereto, and OWNER will not be responsible for CONTRACTOR'S failure to
perform the work in accordance with the contract documents.
General Conditions Page 21
\%000" dam�
9.12 OWNER will not be responsible for the acts or omissions of CONTRACTOR, or of any
subcontractor, or of the agents or employees of any CONTRACTOR or subcontractor,
or of any other persons at the site or otherwise performing any of the work.
ARTICLE 10 - CHANGES IN THE WORK
10.1 Without invalidating the agreement, OWNER may, at any time or from time to time,
order additions, deletions, or revisions in the work; these will be authorized by change
orders. Upon receipt of a change order, CONTRACTOR shall proceed with the work
involved. All such work shall be executed under the applicable conditions of the
contract documents. If any change order causes an increase or decrease in the contract
price, or an extension or shortening of the contract time, an equitable adjustment will be
made as provided in Article 11 or Article 12 on the basis of a claim made by either
Ply-
10.2 OWNER may authorize minor changes in the work, not involving an adjustment in the
contract price or the contract time, which are consistent with the overall intent of the
contract documents. These may be accomplished by a field order, and shall be binding
on OWNER, and also on CONTRACTOR who shall perform the change promptly. If
CONTRACTOR believes that a field order justifies an increase in the contract price or
contract time, CONTRACTOR may make a claim therefor as provided in Article 11 or
Article 12.
10.3 Additional work performed without authorization of a change order will not entitle
CONTRACTOR to an increase in the contract price, or an extension of the contract
time, except in the case of an emergency as provided in paragraph 6.22, and except as
provided in paragraphs 10.2 and 13.9.
10.4 OWNER shall execute appropriate change orders prepared by CONTRACTOR
covering changes in the work which are required by OWNER, or required because of
unforeseen physical conditions or emergencies, or because of uncovering work found
not to be defective, or as provided in paragraphs 11.10 or 11.11.
10.5 If notice of any change affecting the general scope of the work or change in the contract
price is required by the provisions of any bond to be given to the surety, it will be
CONTRACTOR'S responsibility to so notify the surety, and the amount of each
applicable bond shall be adjusted accordingly. CONTRACTOR shall furnish proof of
such adjustment to OWNER.
ARTICLE 11 - CHANGE OF CONTRACT PRICE
11.1 The contract price constitutes the total compensation (subject to authorized adjustments)
General Conditions Page 22
11-� \00OP/
payable to CONTRACTOR for performing the work. All duties, responsibilities, and
obligations assigned to or undertaken by CONTRACTOR shall be at his expense
without change in the contract price.
11.2 The contract price may only be changed by a change order. Any claim for an increase
in the contract price shall be based on written notice delivered to OWNER within ten
days of the occurrence of the event giving rise to the claim. Any change in the contract
price resulting from any such claim shall be incorporated in a change order.
11.3 No change orders or other form of order or directive which requires additional
compensable work to be performed may be issued or be effective unless accompanied
by a written assurance to the CONTRACTOR that lawful appropriations to cover the
costs of the additional work have been made.
11.4 The value of any work covered by a change order, or of any claim for an increase or
decrease in the contract price, shall be determined in one of the following ways:
11.4.1 Where the work involved is covered by unit prices contained in the contract
documents, by application of unit prices to the quantities of the items involved
(subject to the provisions of paragraph 11.10).
11.4.2 By mutual acceptance of a lump sum.
11.4.3 On the basis of the cost of the work (determined as provided in paragraphs 11.5 and
11.6), plus a contractor's Fee for overhead and profit (determined as provided in
paragraph 11.7).
COST OF THE WORK:
11.5 The term "Cost of the Work" means the sum of all costs necessarily incurred and paid
by CONTRACTOR in the proper performance of the work. Except as otherwise may be
agreed to in writing by OWNER, such costs shall be in amounts no higher than those
prevailing in the locality of the project, shall include only the following items, and shall
not include any of the costs itemized in paragraph 11.6:
11.5.1 Payroll costs for employees in the direct employ of CONTRACTOR in the
performance of the work under schedules of job classifications agreed upon by
OWNER and CONTRACTOR. Payroll costs for employees not employed full
time on the work shall be apportioned on the basis of their time spent on the work.
Payroll costs shall include, but not be limited to, salaries and wages, plus the cost
of fringe benefits which shall include social security contributions, unemployment,
excise and payroll taxes, worker's or workmen's compensation, health and
retirement benefits, bonuses, sick leave, vacation and holiday pay applicable
General Conditions Page 23
thereto. Such employees shall include superintendents and foremen at the site. The
expenses of performing work after regular working hours, or on Sunday or legal
holidays, shall be included in the above only to the extent authorized by OWNER.
11.5.2 Cost of all materials and equipment furnished and incorporated in the work,
including costs of transportation and storage thereof, and manufacturers' field
services required in connection therewith. All cash discounts shall accrue to
CONTRACTOR unless OWNER deposits funds with CONTRACTOR with which
to make payments, in which case, the cash discounts shall accrue to OWNER. All
trade discounts, rebates and refunds, and all returns from sale of surplus materials
and equipment shall accrue to OWNER, and CONTRACTOR shall make
provisions so that they may be obtained.
11.5.3 Payments made by CONTRACTOR to the subcontractors for work performed by
subcontractors. If required by OWNER, CONTRACTOR shall obtain competitive
bids from subcontractors acceptable to CONTRACTOR, and shall deliver such bids
to OWNER, who will then determine, which bids will be accepted. If a
subcontract provides that the subcontractor is to be paid on the basis of Cost of the
Work Plus a Fee, the subcontractor's Cost of the Work shall be determined in the
same manner as CONTRACTOR'S Cost of the Work. All subcontracts shall be
subject to the other provisions of the contract documents insofar as applicable.
11.5.4 Supplemental costs including the following:
11.5.4.1 The proportion of necessary transportation, travel, and subsistence expenses of
CONTRACTOR'S employees incurred in discharge of duties connected with the
work.
11.5.4.2 Cost, including transportation and maintenance, of all materials, supplies,
equipment, machines, appliances, office and temporary facilities at the site, and
hand tools not owned by the workmen, which are consumed in the performance of
the work, and cost less market value of such items used but not consumed which
remain the property of CONTRACTOR.
11.5.4.3 Rentals of all construction equipment and machinery, and the parts thereof, whether
rented from CONTRACTOR or others in accordance with rental agreements
approved by OWNER, and the costs of transportation, loading, unloading,
installation, dismantling and removal thereof, all in accordance with terms of said
rental agreements. The rental of any such equipment, machinery or parts shall
cease when the use thereof is no longer necessary for the work.
11.5.4.4 Sales, use, or similar taxes related to the work, and for which CONTRACTOR is
liable, imposed by any governmental authority.
General Conditions
Page 24
swmp�
1�0w�
11.5.4.5 Deposits lost for causes other than CONTRACTOR'S negligence, royalty
payments, and fees for permits and licenses.
11.5.4.6 Losses and damages (and related expenses), not compensated by insurance or
otherwise, to the work otherwise sustained by CONTRACTOR in connection with
the execution of the work, provided they have resulted from causes other than the
negligence of CONTRACTOR, any subcontractor, or anyone directly or indirectly
employed by any of them, or for whose acts any of them may be liable. Such
losses shall include settlements made with the written consent and approval of
OWNER. No such losses, damages, and expenses shall be included in the Cost of
the Work for the purpose of determining Contractor's Fee. If, however, any such
loss or damage requires reconstruction, and CONTRACTOR is placed in charge
thereof, CONTRACTOR shall be paid for services a fee proportionate to that stated
in paragraph 11.7.2.
11.5.4.7 The cost of utilities, fuel, and sanitary facilities at the site.
11.5.4.8 Minor expenses such as telegrams, long distance calls, telephone service at the site,
expressage and similar petty cash items in connection with the work.
11.5.4.9 Cost of premiums for additional bonds and insurance required because of changes
in the work.
11.6 The term "Cost of the Work" shall not include any of the following:
11.6.1 Payroll costs and other compensation of CONTRACTOR'S officers, executives,
principals (of partnership and sole proprietorship), general managers, engineers,
architects, estimators, lawyers, auditors, accountants, purchasing and contracting
agents, expediters, timekeepers, clerks, and other personnel employed by
CONTRACTOR whether at the site or in his principal or a branch office for general
administration of the work, and not specifically included in the agreed upon
schedule of job classifications referred to in subparagraph 11.5.1, all of which are
to be considered administrative costs covered by the Contractor's Fee.
11.6.2 Expenses of CONTRACTOR'S principal and branch office, other than
CONTRACTOR'S office at the site.
11.6.3 Any part of CONTRACTOR'S capital expenses including interest on
CONTRACTOR'S capital employed for the work, and charges against
CONTRACTOR for delinquent payments.
11.6.4 Cost of premiums for all bonds and for all insurance whether or not
CONTRACTOR is required by the contract documents to purchase and maintain
General Conditions Page 25
s4wi 1%0�
the same (except for additional bonds and insurance required because of changes in
the work).
11.6.5 Costs due to the negligence of CONTRACTOR, any subcontractor, or anyone
directly or indirectly employed by any of them, or for whose acts any of them may
be liable, including, but not limited to, the correction of defective work, disposal of
materials or equipment wrongly supplied, and making good any damage to
property.
11.6.6 Other overhead or general expense costs of any kind, and the costs of any item not
specifically and expressly included in paragraph 11.5.
CONTRACTOR'S FEE:
11.7 The Contractor's Fee allowed to CONTRACTOR for overhead and profit shall be
determined as follows:
11.7.1 a mutually acceptable fixed fee; or, if none can be agreed upon,
11.7.2 a fee based on the following percentages of the various portions of the Cost of the
Work:
11.7.2.1 for costs incurred under paragraphs 11.5.1 and 11.5.2, the Contractor's Fee shall be
ten percent,
11.7.2.2 for costs incurred under paragraph 11.5.3, the Contractor's Fee shall be five
percent; and if a subcontract is on the basis of Cost of the Work Plus a Fee, the
maximum allowable to the subcontractor as a fee for overhead and profit shall be
ten percent, and
11.7.2.3 no fee shall be payable on the basis of costs itemized under paragraphs 11.5.4,
11.5.5, and 11.6.
11.8 The amount of credit to be allowed by CONTRACTOR to OWNER for any such
change which results in a net decrease in cost, will be the amount of the actual net
decrease. When both additions and credits are involved in any one change, the
combined adjustment to overhead and profit shall be figured on the basis of the net
increase or decrease in allowable costs, if any.
ADJUSTMENT OF UNIT PRICES:
11.9 Whenever the cost of any work is to be determined pursuant to paragraphs 11.5 and
11.6, CONTRACTOR will submit, in form acceptable to OWNER, an itemized cost
General Conditions Page 26
breakdown together with supporting data.
11.10 Where the quantity of work with respect to any item that is covered by a unit price
differs materially and significantly from the quantity of such work indicated in the
contract documents, an appropriate change order shall be issued on recommendation of
OWNER to adjust the unit price.
CASH ALLOWANCES:
11.11 It is understood that CONTRACTOR has included in the contract price all allowances
so named in the contract documents, and shall cause the work so covered to be done by
such subcontractors, manufacturers, fabricators, suppliers, or distributors, and for such
sums within the limit of the allowances as may be acceptable to OWNER. Upon final
payment, the contract price shall be adjusted as required, and an appropriate change
order issued. CONTRACTOR agrees that the original contract price includes such
sums as CONTRACTOR deems proper for costs and profit on account of cash
allowances. No demand for additional cost or profit in connection therewith will be
valid.
ARTICLE 12 - CHANGE OF THE CONTRACT TIME
12.1 The contract time may only be changed by a change order. Any claim for an extension
in the contract time shall be based on written notice delivered to OWNER within ten
days of the occurrence of the event giving rise to the claim. Any change in the contract
time resulting from any such claim shall be incorporated in a change order.
12.2 All time limits stated in the contract documents are of the essence of the agreement.
The provisions of Articles 11 and 12 are Contractor's sole remedies for delay by any
cause whatsoever, including acts of Owner.
ARTICLE 13 - WARRANTY AND GUARANTEE, TESTS .AND INSPECTION,
CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK
WARRANTY AND GUARANTEE:
13.1 CONTRACTOR warrants and guarantees to OWNER that all work will be in
accordance with the contract documents and will not be defective. Prompt notice of all
defects shall be given to CONTRACTOR. All defective work, whether or not in place,
may be rejected, corrected, or accepted as provided in this Article 13.
ACCESS TO WORK:
General Conditions Page 27
13.2 OWNER, testing agencies, and governmental agencies with jurisdictional interests will
have access to the work at reasonable times for their observation, inspection and testing.
CONTRACTOR shall provide proper and safe conditions for such access.
TESTS AND INSPECTIONS:
13.3 CONTRACTOR shall give OWNER timely notice of readiness of work for all required
inspections, tests or approvals.
13.4 If any law, ordinance, rule, regulation, code, or order of any public body having
jurisdiction requires any work (or part thereof) to specifically be inspected, tested, or
approved, CONTRACTOR shall assume full responsibility therefor, pay all costs in
connection therewith, and furnish OWNER the required certificates of inspection,
testing, or approval. CONTRACTOR shall also be responsible for and shall pay all
costs in connection with any inspection or testing required in connection with
OWNER'S acceptance of a manufacturer, fabricator, supplier, or distributor of
materials or equipment proposed to be incorporated in the work, or of materials or
equipment submitted for approval prior to CONTRACTOR'S purchase thereof for
incorporation of the work. The cost of all other inspections, tests, and approvals
required by the contract documents shall be paid by OWNER (unless otherwise
specified).
13.5 Any inspections, tests, or approvals, other than those required by law, ordinance, rule,
regulation, code, or order of any public body having jurisdiction, shall be performed by
organizations acceptable to OWNER and CONTRACTOR if so specified).
13.6 If any work that is to be inspected, tested, or approved is covered without written
concurrence of OWNER, it must, if requested by OWNER, be uncovered for
observation. Such uncovering shall be at CONTRACTOR'S expense, unless
CONTRACTOR has given OWNER timely notice of CONTRACTOR'S intention to
cover such work and OWNER has not acted with reasonable promptness in response to
such notice.
13.7 Neither observations by OWNER nor inspections, tests, or approvals by others shall
relieve CONTRACTOR from his obligations to perform the work in accordance with
the contract documents.
UNCOVERING WORK:
13.8 If any work is covered contrary to the written request of OWNER, it must, if requested
by OWNER, be uncovered for ONWER'S observation and replaced at
CONTRACTOR'S expense.
General Conditions Page 28
13.9 If OWNER considers it necessary or advisable that covered work be observed by
OWNER, or inspected or tested by others, CONTRACTOR, at OWNER'S request, shall
uncover, expose, or otherwise make available for observation, inspection, or testing as
OWNERS may require, that portion of the work in question, furnishing all necessary
labor, material, and equipment. If it is found that such work is defective,
CONTRACTOR shall bear all the expenses of such uncovering, exposure, observation,
inspection, and testing of satisfactory reconstruction, including compensation for
additional professional services, and an appropriate deductive change order shall be
issued. If, however, such work is not found to be defective, CONTRACTOR shall be
allowed an increase in the contract price, or an extension of the contract time, or both,
directly attributable to such uncovering, exposure, observation, inspection, testing, and
reconstruction.
OWNER MAY STOP THE WORK:
13.10 If the work is defective, or CONTRACTOR fails to supply sufficient skilled workmen
or suitable materials or equipment, OWNER may order CONTRACTOR to stop the
work, or any portion thereof, until the cause for such order has been eliminated;
however, this right of OWNER to stop the work shall not give rise to any duty on the
part of OWNER to exercise this right for the benefit of CONTRACTOR or any other
party.
CORRECTION OR REMOVAL OF DEFECTIVE WORK:
13.11 If required by OWNER, CONTRACTOR shall promptly, without cost to OWNER and
as specified by OWNER, either correct any defective work, whether or not fabricated,
installed, or completed, or, if the work has been rejected by OWNER, remove it from
the site and replace it with non defective work in a manner acceptable to the OWNER.
ONE YEAR CORRECTION PERIOD:
13.12 If, within one year after the date of substantial completion, or such longer period of time
as may be prescribed by law, or by the terms of any applicable special guarantee
required by the contract documents, or by any other specific provision of the contract
documents, any work is found to be defective, CONTRACTOR shall promptly, without
cost to OWNER, and in accordance with OWNER'S written instructions, either correct
such defective work, or, if it has been rejected by OWNER, remove it from the site, and
replace it with non defective work. If CONTRACTOR does not promptly comply with
the terms of such instructions, or in an emergency where delay would cause serious risk
of loss or damage, OWNER may have the defective work corrected or the rejected work
removed and replaced, and all direct and indirect costs of such removal and
replacement, including compensation for additional professional services, shall be paid
by CONTRACTOR.
General Conditions
Page 29
ACCEPTANCE OF DEFECTIVE WORK:
13.13 If, instead of requiring correction or removal and replacement of defective work,
OWNER may do so. In such case, if acceptance occurs prior to OWNERS
recommendation of final payment, a change order shall be issued incorporating the
necessary revisions in the contract price; or, if the acceptance occurs after such
recommendation, an appropriate amount shall be paid by CONTRACTOR to OWNER.
OWNER MAY CORRECT DEFECTIVE WORK:
13.14 If CONTRACTOR fails, within a reasonable time after written notice of OWNER, to
proceed to correct defective work, or to remove and replace rejected work as required by
OWNER in accordance with paragraph 13.11, or if CONTRACTOR fails to perform the
work in accordance with the contract documents (including any requirements of the
progress schedule), OWNER may, after seven days written notice to CONTRACTOR,
correct and remedy any such deficiency. In exercising his rights under this paragraph
OWNER shall proceed expeditiously. To the extent necessary to complete corrective
and remedial action, OWNER may exclude CONTRACTOR from all or part of the site,
take possession of all or part of the work, and suspend CONTRACTOR'S services
related thereto, take possession of CONTRACTOR'S tools, appliances, construction
equipment, and machinery at the site, and incorporate in the work all materials and
equipment stored at the site, or for which OWNER has paid CONTRACTOR, but which
are stored elsewhere. CONTRACTOR shall allow OWNER, OWNER'S
representatives, agents, and employees such access to the site as may be necessary to
enable OWNER to exercise his rights under this paragraph. All direct and indirect costs
of OWNER in exercising such rights shall be charged against CONTRACTOR in an
amount verified by OWNER, and a change order shall be issued incorporating the
necessary revisions in the contract documents and a reduction in the contract price.
Such direct and indirect costs shall include, in particular but without limitation,
compensation for additional professional services required, and all costs of repair and
replacement of work of others destroyed or damaged by correction, removal, or
replacement of CONTRACTOR'S defective work. CONTRACTOR shall not be
allowed and extension of the contract time because of any delay in performance of the
work attributable to the exercise by OWNER of OWNER'S rights hereunder.
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION
SCHEDULES:
14.1 At least ten days prior to submitting the first application for a progress payment,
CONTRACTOR shall (except as otherwise specified in the general requirements)
submit to OWNER a progress schedule, a final schedule of shop drawing submissions,
General Conditions
Page 30
t%will �U �
and, where applicable, a schedule of values of the work. These schedules shall be
satisfactory in form and substance to OWNER. The schedule of values shall include
quantities and unit prices aggregating the contract price, and shall subdivide the work
into component parts in sufficient detail to serve as the basis for progress payments
during construction. Upon acceptance of the schedule of values by OWNER, it shall be
incorporated into a form of application for payment acceptable to OWNER.
APPLICATION FOR PROGRESS PAYMENT:
14.2 At least ten days before each progress payment falls due (but not more often than once a
month), CONTRACTOR shall submit to OWNER for review an application for
payment filled out and signed by CONTRACTOR covering the work completed as of
the date of the application, and accompanied by such supporting documentation as is
- --required by the contract doumentsand also-_as-0 ER mavx onably require. If
payment is requested on the basis of materials and equipment not incorporated in the
work, but delivered and suitably stored at the site or at another location agreed to in
writing, the application for payment shall also be accompanied by such data,
satisfactory to OWNER, as will establish OWNER'S title to the material and equipment,
and protect OWNER'S interest therein, including applicable insurance. Each
subsequent application for payment shall include an affidavit of CONTRACTOR
stating that all previous progress payments received on account of the work have been
applied to discharge in full all of CONTRACTOR'S obligations reflected in prior
applications for payment. The amount of retainage with respect to progress payments
will be as stipulated in the agreement.
CONTRACTOR'S WARRANTY OF TITLE:
14.3 CONTRACTOR warrants and guarantees that title to all work, materials, and equipment
covered by any application for payment, whether incorporated in the project or not, will
pass to OWNER at the time of payment free and clear of all liens, claims, security
interests, and encumbrances (hereafter in these General Conditions referred to as
"Liens").
REVIEW OF APPLICATIONS FOR PROGRESS PAYMENT:
14.4 OWNER will, within ten days after receipt of each application for payment, either
indicate in writing a recommendation of payment and present the application to
OWNER, or return the application to CONTRACTOR indicating in writing OWNER'S
reasons for refusing to recommend payment. In the latter case, CONTRACTOR may
make the necessary corrections and resubmit the application. OWNER shall, within
twenty days of presentation to him of the application for payment with OWNER'S
recommendation, pay CONTRACTOR the amount recommended.
General Conditions Page 31
rn
NNW/
14.5 OWNER may refuse to recommend the whole, or any part of any payment if, in his
opinion, it would be incorrect to make such representations to OWNER. He may also
refuse to recommend any such payment, or, because of subsequently discovered
evidence, or the results of subsequent inspections or tests, nullify any such payment
previously recommended to such extent as may be necessary in OWNER'S opinion to
protect OWNER from loss because:
14.5.1 the work is defective, or completed work has been damaged requiring correction or
replacement,
14.5.2 written claims have been made against OWNER, or Liens have been filed in connection
with the work,
14.5.3 the contract price has been reduced because of modifications,
14.5.4 OWNER has been required to correct defective work, or complete the work in
accordance with paragraph 13.14,
14.5.5 of CONTRACTOR'S unsatisfactory prosecution of the work in accordance with the
contract documents, or
14.5.6 CONTRACTOR'S failure to make payment to subcontractors, or for labor, materials, or
equipment.
SUBSTANTIAL COMPLETION:
14.6 When CONTRACTOR considers the entire work ready for its intended use,
CONTRACTOR shall, in writing to OWNER certify that the entire work is substantially
complete, and issue a certificate of substantial completion. Within a reasonable time
thereafter, OWNER, CONTRACTOR shall make an inspection of the work to
determine the status of completion. If OWNER does not consider the work
substantially complete, OWNER will notify CONTRACTOR in writing giving his
reasons therefor. If OWNER considers the work substantially complete, tentative
certificate of substantial completion which shall fix the date of substantial completion.
There shall be attached to the certificate a tentative list of items to be completed or
corrected before final payment. OWNER shall have seven days after receipt of the
tentative certificate during which he may make written objection to CONTRACTOR as
to any provisions of the certificate or attached list. If, after considering such objections,
OWNER concludes that the work is not substantially complete, OWNER will, within
fourteen days after submission of the tentative certificate to OWNER, notify
CONTRACTOR in writing stating his reasons therefor. If, after consideration of
OWNER'S objections, OWNER considers the work substantially complete, OWNER
General Conditions Page 32
will, within said fourteen days, execute and deliver to OWNER and CONTRACTOR a
definitive certificate of substantial completion (with a revised tentative list of items to
be completed or corrected) reflecting such changes from the tentative certificate as he
believes justified after consideration of any objections from OWNER. At the time of
delivery of tentative certificate of substantial completion, OWNER will deliver to
OWNER and CONTRACTOR a written recommendation as to division of
responsibilities pending final payment between OWNER and CONTRACTOR with
respect to security, operation, safety, maintenance, heat, utilities, and insurance. Unless
OWNER and CONTRACTOR agree otherwise in writing and so inform ENGINEER
prior to his issuing the definitive certificate of substantial completion, ENGINEER'S
aforesaid recommendation will be binding on OWNER and CONTRACTOR until final
payment.
14.7 OWNER shall have the right to exclude CONTRACTOR from the work after the date
of substantial completion, but OWNER shall allow CONTRACTOR reasonable access
to complete or correct items on the tentative list.
PARTIAL UTILIZATION:
14.8 Use by OWNER of completed portions of the work may be accomplished prior to
substantial completion of all of the work subject to the following:
14.9.1 OWNER, at any time, may request CONTRACTOR in writing to permit OWNER to
use any part of the work which OWNER believes to be substantially complete and
which may be so used without significant interference with construction of the other
parts of the work. If CONTRACTOR agrees, CONTRACTOR will certify to OWNER
that said part of the work is substantially complete, and request ENGINEER to issue a
certificate of substantial completion for that part of the work. Within a reasonable time
thereafter, OWNER, CONTRACTOR, and ENGINEER shall make an inspection of that
part of the work to determine its status of completion. If ENGINEER considers that
part of the work to be substantially complete, ENGINEER will execute, and deliver to
OWNER and CONTRACTOR, a certificate to that effect, fixing the date of substantial
completion as to that part of the work, attaching thereto a tentative list of items to be
completed or corrected before final payment. Prior to issuing a certificate of substantial
completion as to part of the work, ENGINEER will deliver to OWNER and
CONTRACTOR a written recommendation as to the division of responsibilities
pending final payment between OWNER and CONTRACTOR with respect to security,
operation, safety, maintenance, utilities, and insurance for that part of the work which
shall become binding upon OWNER and CONTRACTOR at the time of issuing the
definitive certificate of substantial completion as to that part of the work, unless
OWNER and CONTRACTOR shall have otherwise agreed in writing. OWNER shall
have the right to exclude CONTRACTOR from any part of the work which ENGINEER
has so certified to be substantially complete, but OWNER shall allow CONTRACTOR
General Conditions Page 33
reasonable access to complete or correct items on the tentative list.
14.9.2 In lieu of the issuance of a certificate of substantial completion as to part of the
work, OWNER may take over operation of a facility constituting part of the work,
whether or not it is substantially complete, if such facility is functionally and
separately usable; provided that prior to any such takeover, OWNER and
CONTRACTOR have agreed as to the division of responsibilities between
OWNER and CONTRACTOR for security, operation, safety, maintenance,
correction period, heat, utilities, and insurance with respect to such facility.
14.9.3 No occupancy of part of the work, or taking over of operations of a facility will be
accomplished before the insurers providing the property insurance have
acknowledged notice thereof and in writing effected any changes in coverage
necessitated thereby. The insurers providing the property insurance shall consent
by endorsement on the policy or policies, but the property insurance shall not be
cancelled or permitted to lapse on account of any such partial use or occupancy.
FINAL INSPECTION:
14.10 Upon written notice from CONTRACTOR that the work is complete, ENGINEER will
make a final inspection with OWNER and CONTRACTOR, and will notify
CONTRACTOR in writing of all particulars in which this inspection reveals that the
work is incomplete or defective. CONTRACTOR shall immediately take such
measures as are necessary to remedy such deficiencies.
FINAL APPLICATION FOR PAYMENT:
14.11 After CONTRACTOR has completed all such corrections to the satisfaction of
OWNER, and delivered all maintenance and operating instructions, schedules,
guarantees, bonds, certificates of inspection, marked -up record documents, and other
documents, all as required by the contract documents, and after OWNER has indicated
that the work is acceptable (subject to the provisions of paragraph 14.14),
CONTRACTOR may make application for final payment following the procedure for
progress payments. The final application for payment shall be accompanied by all
documentation called for in the contract documents, and such other data and schedules
as OWNER may reasonably require, together with complete and legally effective
releases or waivers (satisfactory to OWNER) of all liens arising out of, or filed in
connection with the work. In lieu thereof, and as approved by OWNER,
CONTRACTOR may furnish receipts or releases in full; an affidavit of
CONTRACTOR that the releases and receipts include all labor, services, material, and
equipment for which lien could be filed, and that all payrolls, material, and equipment
bills, and other indebtedness connected with the work, for which OWNER or his
property might in any way be responsible, have been paid or otherwise satisfied; and
General Conditions Page 34
consent of the surety, if any, to final payment. If any subcontractor, manufacturer,
fabricator, supplier, or distributor fails to furnish a release or receipt in full,
CONTRACTOR may furnish a bond or other collateral satisfactory to OWNER to
indemnify OWNER against any lien.
FINAL PAYMENT AND ACCEPTANCE:
14.12 If, on the basis of ENGINEER'S observation of the work during construction and final
inspection, and ENGINEER'S review of the final application for payment and
accompanying documentation, all as required by contract documents, ENGINEER is
satisfied that the work has been completed and CONTRACTOR has fulfilled all of his
obligations under the contract documents, ENGINEER will, within ten days after
receipt of the final application for payment, indicate in writing his recommendation of
payment, and present the application to OWNER for payment. Thereupon, ENGINEER
will give written notice to OWNER and CONTRACTOR that the work is acceptable
subject to the provisions of paragraph 14.15. Otherwise, ENGINEER will return the
application to CONTRACTOR, indicating in writing the reasons for refusing to
recommend final payment, in which case CONTRACTOR shall make the necessary
corrections, and resubmit the application. If the application and accompanying
documentation are appropriate as to form and substance, OWNER shall, process final
payment pursuant to the terms and conditions of this Agreement.
CONTRACTOR'S CONTINUING OBLIGATION:
14.13 CONTRACTOR'S obligation to perform and complete the work in accordance with the
contract documents shall be absolute. Neither recommendation of any progress or final
payment by OWNER, nor the issuance of a certificate of substantial completion, nor
any payment by OWNER to CONTRACTOR under the contract documents, nor any
use or occupancy of the work or any part thereof by OWNER, nor any act of acceptance
by OWNER, nor any failure to do so, nor the issuance of a notice of acceptability by
OWNER pursuant to paragraph 14.13, nor any correction of defective work by OWNER
shall constitute an acceptance of work not in accordance with the contract documents or
a release of CONTRACTOR'S obligation to perform the work in accordance with the
contract documents.
WAIVER OF CLAIMS:
14.14 The making and acceptance of final payment shall constitute:
14.14.1 a waiver of all claims by OWNER against CONTRACTOR, except claims arising
from unsettled liens, from defective work appearing after final inspection pursuant
to paragraph 14.11, or from failure to comply with the contract documents or the
terms of any special guarantees specified therein; however, it shall not constitute a
General Conditions
Page 35
waiver by OWNER of any rights in respect of CONTRACTOR'S continuing
obligations under the contract documents; and
14.14.2 a waiver of all claims by CONTRACTOR against OWNER other than those
previously made in writing and still unsettled.
ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION
OWNER MAY SUSPEND WORK:
15.1 OWNER may, at any time and without cause, suspend the work, or any portion thereof,
for a period of not more than ninety days, by notice in writing to CONTRACTOR
which shall fix the date on which work shall be resumed. CONTRACTOR shall resume
the work on the date so fixed. CONTRACTOR may, at the OWNER'S sole discretion,
be allowed an increase in the contract price, or an extension of the contract time, or
both, directly attributable to any suspension, if he makes a claim therefor as provided in
Articles 11 and 12.
15.2 Upon the occurrence of any one or more of the following events:
15.2.1 if CONTRACTOR is adjudged bankrupt or insolvent,
15.2.2 if CONTRACTOR makes a general assignment for the benefit of creditors,
15.2.3 if a trustee or receiver is appointed for CONTRACTOR or for any of
CONTRACTOR'S property,
15.2.4 if CONTRACTOR files a petition to take advantage of any debtor's act, or to
reorganize under the bankruptcy or similar laws,
15.2.5 if CONTRACTOR repeatedly fails to supply sufficient skilled workmen, or
suitable materials or equipment,
15.2.6 if CONTRACTOR repeatedly fails to make prompt payments to subcontractors, or
for labor, materials, or equipment,
15.2.7 if CONTRACTOR disregards laws, ordinances, rules, regulations, or orders of any
public body having jurisdiction,
15.2.8 if CONTRACTOR disregards the authority of OWNER, or
15.2.9 if CONTRACTOR otherwise violates, in any substantial way, any provisions of the
----ntract documents,
General Conditions Page 36
`4wo *4�
OWNER may, after giving CONTRACTOR and his surety seven days written notice,
terminate the services of CONTRACTOR, exclude CONTRACTOR from the site, and
take possession of the work and of all CONTRACTOR'S tools, appliances, construction
equipment, and machinery at the site, and use the same to the full extent they could be
used by CONTRACTOR (without liability to CONTRACTOR for trespass or
conversion), incorporate in the work all materials and equipment stored at the site, or for
which OWNER has paid CONTRACTOR but which are stored elsewhere, and finish
the work as OWNER may deem expedient. In such case, CONTRACTOR shall not be
entitled to receive any further payment until the work is finished. If the unpaid balance
of the contract price exceeds the direct and indirect costs of completing the work,
including compensation for additional professional services, such excess shall be paid to
CONTRACTOR. If such costs exceed such unpaid balance, CONTRACTOR shall pay
the difference to OWNER. Such costs incurred by OWNER shall be verified by
ENGINEER and incorporated in a change order, but in finishing the work, OWNER
shall not be required to obtain the lowest figure for the work performed.
15.3 Where CONTRACTOR's services have been so terminated by OWNER, the termination
shall not affect any rights of OWNER against CONTRACTOR then existing, or which
may thereafter accrue. Any retention or payment of monies due CONTRACTOR by
OWNER will not release CONTRACTOR from liability.
15.4 Upon seven days written notice to CONTRACTOR, OWNER may, without cause and
without prejudice to any other right or remedy, elect to abandon the work and terminate
the agreement. In such case, CONTRACTOR shall be paid for all work executed and
expenses sustained plus reasonable termination expenses.
CONTRACTOR MAY STOP WORK OR TERMINATE:
15.5 If, through no act or fault of CONTRACTOR, the work is suspended for a period of
more than ninety days by OWNER, or under an order of court or other public authority,
fails to act on any application for payment within thirty days after it is submitted, or
OWNER fails for thirty days to pay CONTRACTOR any sum finally determined to be
due, then CONTRACTOR may, upon seven days written notice to OWNER, terminate
the agreement and recover from OWNER payment for all work executed, and any
expense sustained plus reasonable termination expenses. In addition, and in lieu of,
terminating the agreement, if ENGINEER has failed to act on an application for
payment, or OWNER has failed to make any payment as aforesaid, CONTRACTOR
may, upon seven days notice to OWNER, stop the work until payment of all amounts
then due. The provisions of this paragraph shall not relieve CONTRACTOR of his
obligations under paragraph 6.29 to carry on the work in accordance with the progress
schedule and without delay during disputes and disagreements with OWNER.
General Conditions Page 37
ARTICLE 16 - MISCELLANEOUS
GIVING NOTICE:
16.1 Whenever any provision of the contract documents requires the giving of written notice,
it shall be deemed to have been validly given if delivered in person to the individual, or
to a member of the firm, or to an officer of the corporation for whom it is intended, or if
delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
COMPUTATION OF TIME:
16.2 When any period of time is referred to in the contract documents by days, it shall be
calendar days and be computed to exclude the first and include the last day of such
period. If the last day of any such period falls on a Saturday or Sunday, or on a day
made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted
from the computation.
GENERAL:
16.3 Should OWNER or CONTRACTOR suffer injury or damage to his person or property
because of any error, omission or act of the other party or of any of the other party's
employees or agents, or others for whose acts the other party is legally liable, claim
shall be made in writing to the other party within a reasonable time of the first
observances of such injury or damage.
16.4 The duties and obligations imposed by these general conditions and the rights and
remedies available hereunder to the parties hereto, and, in particular, but without
limitation, the warranties, guarantees, and obligations imposed upon CONTRACTOR
by paragraphs 6.30, 13.1, 13.11, 13.14, 14.3, and 15.2, and all of the rights and remedies
available to OWNER thereunder, shall be in addition to, and shall not be construed in
any way as a limitation of, any rights and remedies available to any or all of them which
are otherwise imposed or available by law or contract, by special warranty or guarantee,
or by other provisions of this paragraph shall be as effective as if repeated specifically in
the contract documents in connection with each particular duty, obligations, right and
remedy to which they apply. All representations, warranties, and guarantees made in
the contract documents shall survive final payment and termination or completion of
this agreement.
General Conditions
Page 38
� 1 .
INDEX TO GENERAL CONDITIONS
PARAGRAPH
ARTICLE OR
Access to the work ......................................................... 13.2
Addenda - definition of (see Specifications) ....................................... 1
Agreement - definition of ...................................................... 1
Application for Payment - definition of ........................................... 1
Application for Payment - Final ............................................. 14.12
Application for Progress Payment ............................................. 14.2
Application for Progress Payment - review of ............................... 14.4 - 14.7
Availability of Lands ........................................................ 4.1
Award, Notice of - defined .................................................... 1
Before Starting Construction .............................................. 2.5 - 2.7
Bid - definition of............................................................ 1
Bonds and Insurance, in General ................................................ 5
Bonds - definition of ......................................................... 1
Bonds, delivery of ..................................................... 2.5 & 5.1
Bonds, Performance and Other ........................................... 5.1 & 5.2
Cash Allowances......................................................... 11.11
Change Order - definition of ...................................................
1
Changes in the Work ........................................................
10
Claims, Waiver of - on Final Payment .........................................
14.16
Clarifications and Interpretations...............................................
9.3
Cleaning.................................................................
6.17
Completion................................................................
14
Completion, Substantial ...............................................
14.8 & 14.9
Conference, Pre -Construction .................................................
2.8
Construction Machinery, Equipment, Etc .........................................
6.4
Continuing Work..........................................................
6.29
Contract Documents - definition of ..............................................
1
Contract Documents, Intent and Reuse ...........................................
3
Contract Documents, Reuse of ................................................
3.5
Contract Price, Change of ....................................................
11
Contract Price - definition of ...................................................
1
Contract Time, Change of ....................................................
12
Contract Time, Commencement of .............................................
2.3
Contract Time - definition of ...................................................
1
Contractor - definition of ......................................................
1
General Conditions Page 39
N
Contractor May Stop Work or Terminate ....................................... 15.5
Contractor's Continuing Obligation ...........................................
14.15
Contractor's Duty to Report Discrepancy in
Documents ........................ 2.5 & 3.2
Contractor's Fee, Costs Plus ..................................................
11.7
Contractor's Liability Insurance ................................................
5.3
Contractors Responsibilities, in General ..........................................
6
Contractor's Warranty of Title ................................................
14.3
Copies of Documents........................................................
2.2
Correction or Removal of Defective Work
..................................... 13.11
Correction Period, Two Year ................................................
13.12
Correction, Removal or Acceptance of
Defective Work, in General ........................................
13.11 - 13.14
Cost of Work .......................................................
11.5 & 11.6
Costs, Supplemental......................................................
11.5.5
Day- definition of ........................................................... 1
Defective Work, Acceptance of ..............................................
13.13
Defective Work, Correction or Removal of .....................................
13.11
Defective - definition of ....................................................... 1
Defective Work, in General ................................................... 13
Defective Work, Rejection .................................................... 9.4
Definitions................................................................. 1
Delivery of Bonds.......................................................... 2.1
Disagreements, Decisions by Engineer .......................................... 9.9
Documents, Copies of ....................................................... 2.2
Documents, Record........................................................ 6.19
Documents, Reuse.......................................................... 3.5
Drawings - definition of ....................................................... 1
Effective Date of Agreement - definition of ....................................... 1
Emergencies.............................................................. 6.22
Engineer - definition of ....................................................... 1
Engineer's Notice Work is Acceptable .......................................... 14.3
Engineer's Responsibilities, Limitations on ................................. 9.10 - 9.13
Engineer's Status During Construction, in General .................................. 9
Engineer's Recommendation of Payment ................................ 14.4 & 14.13
Equipment, Labor, and Materials ........................................... 6.3 - 6.6
Equivalent Materials and Equipment ............................................ 6.7
Fee, Contractor's, Costs Plus ................................................. 11.7
Field Order - definition of ..................................................... 1
Field Order, Issued by Engineer .............................................. 10.2
Final Application for Payment ............................................... 14.12
General Conditions Page 40
f \4000
Final Inspection.......................................................... 14.11
Final Payment, Recommendation of ................................... 14.13 & 14.14
Final Payment, Acceptance ................................................. 14.13
General Requirements - definition of ............................................. 1
General Provisions ................................................... 16.3 & 16.4
Giving Notice............................................................. 16.1
Guarantee of Work, by Contractor ............................................. 13.1
Indemnification...................................................... 6.30 - 6.32
Inspection, Final-.......................................................... 14.11
Inspection, Tests and .................................................. 13.3 - 13.7
Insurance, Bonds and, in General ............................................... 5
Insurance, Builders Risk ..................................................... 5.6
Insurance, Certificates of ................................................ 2.7 & 5.7
Insurance, Contractor's Liability ............................................... 5.3
Insurance, Owner's Liability .................................................. 5.8
Intent of Contract Documents ....................................... 3.1 - 3.4 & 9.12
Interpretations and Clarifications ............................................... 9.3
Investigations of Physical Conditions ........................................... 4.2
Labor, Materials and Equipment ........................................... 6.3 - 6.6
Laws and Regulations...................................................... 6.14
Liability Insurance, Contractor's ............................................... 5.3
Liability Insurance, Owners ................................................... 5.5
Limitations on Engineer's Responsibilities ...................................... 9.10
Materials and Equipment, Furnished by Contractor ................................ 6.3
Materials or Equipment, Equivalent ............................................ 6.7
Miscellaneous Provisions..................................................... 16
Modifications - definition of ................................................... 1
Notice, Giving of .......................................................... 16.1
Notice of Award - definition of ................................................. 1
Notice of Acceptability of Project ............................................ 14.13
Notice to Proceed - definition of ................................................ 1
Notice to Proceed, Giving of .................................................. 2.3
"Or -Equal" Items ........................................................... 6.7
Other Contractors............................................................ 7
Overtime Work, Prohibition of ................................................ 6.3
Owner - definition of ......................................................... 1
Owner May Correct Defective Work .......................................... 13.14
General Conditions Page 41
Owner May Stop Work .................................................... 13.10
Owner May Suspend Work, Terminate .................................... 15.1 - 15.4
Owner's Duty to Execute Change Orders ....................................... 11.9
Owner's Liability Insurance ................................................... 5.8
Owner's Representative, Engineer to Serve as ..................................... 9.1
Owner's Responsibilities, in General ............................................. 8
Owner's Separate Representatives at Site ........................................ 9.8
Partial Utilization......................................................... 14.10
Partial Utilization, Property Insurance ..........................................
5.14
Patent Fees and Royalties ...................................................
6.12
Payments to Contractor, in General .............................................
14
Payment, Recommendation of .........................................
14.4 - 14.7.5
Performance and Other Bonds .............................................
5.1 - 5.2
Permits..................................................................
6.13
Physical Conditions, Investigations and Reports
................................... 4.2
Physical Conditions, Unforeseen ...............................................
4.3
Pre -Construction Conference ..................................................
2.8
Preliminary Matters..........................................................
2
Premises, Use of ......................................................
6.16 - 6.18
Price, Change of Contract ....................................................
11
Price, Contract - definition of ..................................................
1
Progress Payment, Applications for ............................................
14.2
Progress Schedule ....................................................
2.6 & 14.1
Project - definition of .........................................................
1
Project Representative, Resident - definition of
.................................... 1
Project Representation, Provision for ...........................................
9.8
Project, Starting............................................................
2.4
Protection, Safety and .................................................
6.20 - 6.21
Recommendation of Payment ......................................... 14.4 &
14.13
Record Documents.........................................................
6.19
Reference Points...........................................................
4.4
Regulations, Laws and ......................................................
6.14
Rejecting Defective Work ....................................................
9.4
Remedies Not Exclusive ....................................................
16.5
Removal or Correction of Defective Work .....................................
13.11
Resident Project Representative - definition of .....................................
1
Resident Project Representative, Provision for ....................................
9.8
Responsibilities, Contractor's...................................................
6
Responsibilities, Owner's ......................................................
8
Reuse of Documents........................................................
3.5
Royalties, Patent Fees and ...................................................
6.13
General Conditions Page 42
Safety and Protection ..................................................
6.20 - 6.21
Samples.................................................................
6.23
Schedules of Shop Drawing Submissions ..................................
2.6 & 14.1
Schedule of Values ...................................................
2.6 & 14.1
Shop Drawings and Samples ............................................
6.23 - 6.29
Shop Drawings - definition of ..................................................
1
Site, Visits to by Engineer ....................................................
9.2
Specifications - definition of ...................................................
1
Starting Construction, Before .............................................
2.5 - 2.9
Starting the Project..........................................................
2.4
Stopping Work, by Contractor ................................................
15.5
Stopping Work, by Owner ..................................................
13.10
Subcontractor - definition of ...................................................
1
Subcontractors, in General ...............................................
6.8 - 6.11
Substantial Completion, Certification of ........................................
14.8
Substantial Completion - definition of ............................................
1
Subsurface Conditions ..................................................
4.2 & 4.3
Supplemental Costs ......................................................
11.5.5
Surety, Consent to Payment .......................................... 14.12
& 14.14
Surety, Notice of Changes ...................................................
10.5
Surety, Qualification of .................................................
5.1 & 5.2
Suspending Work, by Owner .................................................
15.1
Suspension of Work and Termination, in General ..................................
15
Superintendent, Contractor's..................................................
6.2
Supervision and Superintendence .........................................
6.1 & 6.2
Taxes, Payment by Contractor ................................................ 6.15
Termination, by Contractor .................................................. 15.5
Termination, by Owner ................................................ 15.2 - 15.4
Termination, Suspension of Work and, in General ................................. 15
Tests and Inspections .................................................. 13.3 - 13.7
Time, Change of Contract .................................................... 12
Time, Computation of ...................................................... 16.2
Time, Contract - definition of .................................................. 1
Uncovering Work .................................................... 13.8 & 13.9
UnitPrices............................................................. 11.4.1
Unit Prices, Adjustment of .................................................. 11.10
Use of Premises...................................................... 6.17 - 6.18
Values, Schedule of ........................................................ 14.1
Visits to Site, by Engineer .................................................... 9.2
General Conditions Page 43
Warranty and Guarantee, by Contractor ........................................ 13.1
Warranty of Title, Contractor's ............................................... 14.3
Work, Access to ........................................................... 13.2
Work by Others, in General .................................................... 7
Work, Cost of ....................................................... 11.5 & 11.6
Work Continuing During Disputes ............................................ 6.29
Work - definition of .......................................................... 1
Work, Neglected by Contractor .............................................. 13.14
Work, Stopping by Contractor ................................................ 15.5
Work, Stopping by Owner .............................................. 15.1 - 15.4
General Conditions
Page 44
GENERAL CONDITIONS
TABLE OF CONTENTS OF GENERAL CONDITIONS
ARTICLE
TITLE PAGE
1.
DEFINITIONS .................................................
1
2.
PRELIMINARY MATTERS ......................................
4
3.
CONTRACT DOCUMENTS .....................................
5
4.
AVAILABILITY OF LANDS; PHYSICAL CONDITIONS;
REFERENCE POINTS ..........................................
6
5.
BONDS AND INSURANCE .....................................
8
6.
CONTRACTOR'S RESPONSIBILITIES ............................
12
7.
WORK BY OTHERS ..........................................
21
8.
OWNER'S RESPONSIBILITIES ..................................
21
9.
ENGINEER'S STATUS DURING CONSTRUCTION .................
22
10.
CHANGES IN THE WORK ......................................
24
11.
CHANGE OF CONTRACT PRICE ................................
25
12.
CHANGE OF CONTRACT TIME .................................
30
13.
WARRANTY AND GUARANTEE; TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE
OF DEFECTIVE WORK ........................................
31
14.
PAYMENTS TO CONTRACTOR AND COMPLETION ...............
34
15.
SUSPENSION OF WORK AND TERMINATION ....................
41
16.
MISCELLANEOUS .............................................
43
INDEX.......................................................
45
FADOCSImamortensonbuswash.wpd
General Conditions Page 46
4r ` /
��.
DISTRIBUTION
Originals to:
1.
Contract Book
Ce�ssas to•
M
Accounting
4