HomeMy WebLinkAboutC02-120 Granite Construction Company_change order 3EGE-2198
STATE OF: Colorado AIP PROJECT NO.: 3-08-0020-26 & 27
NAME OF AIRPORT: Eagle County Regional Airport LOCATION: Eagle, Colorado
CONTRACTOR: Granite Construction Company SCHEDULE NO.: One 1 & Two 2
CHANGE ORDER NO. THREE (3)
TO Granite Construction Company, CONTRACTOR: YOU ARE HEREBY ORDERED TO MAKE THE FOLLOWING
CHANGE IN THE PLANS AND/OR SPECIFICATIONS FOR THE ABOVE DESIGNATED PROJECT.
1. DESCRIPTION OF CHANGE TO BE MADE:
Final quantity adjustments to match final pay quantities and settlement.
2. REASON FOR ORDERING CHANGE:
To adjust quantities to match cost estimate and settlement.
3. SETTLEMENT FOR THE COST OF THE MENTIONED CHANGE IS TO BE MADE AS FOLLOWS:
See attachments for the descriptions of adjusted quantities.
THIS CHANGE ORDER INCREASES DECREASES THE CONTRACT TIME BY 0 CALENDAR DAYS.
4. SUMMARY OF COSTS:
NET (INCREASE) (DEGR€AS€) OF THIS CHANGE ORDER $ 299,338.47
TOTAL (INCREASE) (DECREASE) OF ALL PREVIOUS CHANGE ORDERS 1,424,088.00 (Revised)
TOTAL (INCREASE) (PEGR€AS€) OF ALL CHANGE ORDERS TO DATE 1,723,426.47
TOTAL ESTIMATED CONTRACT COSTS $6,426,128.47
NOTE: THIS ORDER IS NOT EFFfFCTIVE UNTIL SIGNED BY THE ENGINEERING SECTION AIRPORTS DIVISION FEDERAL
AVIATION ADMINISTRAT N.
eid"AGREED TO BY: D
SPONSOR'S AUTHORIZED R TITLE A
AGREED TO BY:
CONTRACTOR'S 77 REP. TITLE "IA T
AGREED TO BY: _
ENGINEERING SECTION, AIRPORTS DIVISION, FAA TITLE DATE
Page 1
m:lfonnsURcldEnginc«inglPcrodiccostEs Lxls
Page 2 ;
INVOICE NO.7 EAGLE COUNTY REGIONAL AIRPORT
EAGLE COUNTY, COLORADO
SPONSOR NAME: EAGLE COUNTY REGIONAL AIP Project No. 3-08-002A-26, 27
PAS JOB # 12234.902
CONTRACTOR: Granite Construction Company ESTIMATE NUMBER: 7 FINAL
1000 North Warm, S rin s Road PERIOD ENDING. December 1 2001
L _ A- \ ,
:{`•:�:.::}ti :'.{�':{':{{1\}{iy .:•{:L{\L{{::L�:�}}ti{},j} ••{S,S'::r{N{{/.{{�• tii:f i {�} WIN
Y• '•}{'ti:•�.: t ti/}�.• •L:: f:•.•}.:•:'•.ti{"u:{•1..{•Lti}ti :J �}1�{L}.•.'�•.ti• 1ti}xYA\•.}1 ••1� .��.1}y K'i '.�•.,• N } � N N LY Y •.• NN\ K' • •Y • , \ N "`K
ttt•.t •t :L:Y.Y.. h h::: X • •i lJfJJJ.Y.'.\1V.•.L 11 Lt,t,tL LL .�.�[.^��L��; • • )Jy}yy,�
.•:51,�{� ... ...TM1T:{,•�1.�{NL�'.N}},}\{41\\N{NY.\t{tiff{{ ..1\}x'�•• . f'• ,,�} }• • Yn•
.LLY.A•• ..... .. .. • •. .. . ...... ' . ... •. .. . .... . T�^.` J••�lt •IiR•••x•Y}
-107a Remove/Reistall Existing Supplemental Wind Cone, 8 1 Ea. $1,600.00 $1,600.00 0.00 $0.00 1.00 $1,600.00 1.00 $1,600.00 100.00
Foot
-107b
Remtove/Reistall Existing Supplemental Wind Cone
Power Frame
1
Ea.
$1,200.00
$1,200.00
0.00
$0.00
1.00
$1,200.00
1.00
$1,200.00
100.00
-107c
Install Windeono Power Frame (C.O. #1)
1
Ea.
$3,000.00
$3.000.00
0.00
$0.00
1.00
$3,000.00
1.00
$3,000.00
100.0 '
-108a
Install Cable,l/C #8, 5000V, L-824 C (C.O. #1)
53,200
L.P.
$0.63
$33,516.00
0.00
$0.00
53,200.00
$33,516.00
53,200.00
$33,516.00
100.00
-108b
Install Counterpoise Wire Including Ciround Rods and
Ground Connectors
440
L.P.
$2.90
$1,276.00
0.00
$0.00
450.00
$1,305.00
450.00
$1,305.00
102.27
-108c
Install Cable, LC #8, Bare Copper (C.O. #1)
16,600
L.F.
$0.75
$12,450.00
0.00
$0.00
16,600.00
$12,450.00
16,600.00
$12,450.00
100.00
-110a
Install 1-2 Inch PVC Duct (DEB) (C.O. #1)
24,795
L.P.
$3.00
$74,385.00
0.00
$0.00
25,439.00
$76,317.00
25,439.00
$76,317.00
102.60
-110b
Install 1-2 Inch PVC Duct (CE)
830
L.F.
$9.50
$7,885.00
0.00
$0.00
891.00
$8,464.50
891.00
$8,464.50
107.35
110e
Install 1-2 Inch PVC Duct (CE) iuExisting Pavement
(C.O. #1)
1,293
L.F.
$30.00
$38,790.00
0.00
$0.00
1,293.00
$38,790.00
1,293.00
$38,790.00
100.00
-110d
Install 2-3 Inch PVC Duct (CE) (C.O. #1)
Install 2-3 Inch PVC Duct (CIE) In Existing Pavement
797
L.F.
$16.00
$12,75100
0.00
$0.00
890.00
$14,240.00
890.00
$14,240.00
111.67
86.76
110e
110f
L-110g
110h
(C.O. #1)
Install 4-3 Inch PVC Duct (CE) (C.O. #1)
Install 4-3 Inch PVC Duct (CE) In Existing Pavement
Install 1 2 Inch PVC Duct (CE) in Existing Pavement For
Future CL Lights C.O. #1
355
220
200
4,875
L.F.
L.P.
L.F.
L.P.
$35.00
$32.00
$50.00
$30.00
$12,425.00
$7,040.00
$10,000.00
$146,250.00
0.00
0.00
0.00
0.00
$0.00
$0.00
$0.00
$0.00
308.00
220.00
210.00
4,875.00
$10,780.00
$7,040.00
$10,500.00
$146,250.00
308.00
22.0.00
210.00
4,875.00
$10,780.00
$7,040.00
100.00
$10,500.00
105.00
$146,250.00
100.00
-110i
125a
-125b
Install 4-4 Inch PVC Duct (CE) (C.O. #1)
Remove Exisitu L-861 Runway Ede Light (C.O. #1)
Reinstall Existing L-861 Runway Edge Light On New
Base (C.O. #1
100
79
71
L.F.
Ea.
Ea.
$36.00
$121.09
$679.00
$3,600.00
$9,559.00
$48,209.00
0.00
0.00
0.00
$0.00
$0.00
$0.00
100.00
79.00
79.00
$3,600.00
$9,559.00
$53,641.00
100.00
79.00
$3.600.00
$9,559.00
100.00
100.00
79.00
$53,641.00
111.27
125e
Remove/Reinstall L-861 Runway Threshold Light On
New Base
8
Ea.
$467.00
$3,736.00
0.00
$0.00
8.00
$3,736.00
8.00
$3.736.00
100.0
-125d
RemovelReinstall L-858 Taxiway Sign, (2P,S1) on New
Base (C.O. #1)
15
Ea.
$824.00
$12,360.00
0.00
$0.00
14.00
$11,536.00
14.00
$11,536.00
93.33
125e
Remove/Reinstall L-858 Taxiway Sign, (3P,S1) on New
Base
5
Ea.
$886.00
$4,430.00
0.00
$0.00
5.00
$4,430.00
5.00
$0430.00
100.00
125f
RemAove/Reinstall MR RDR Sign, (1P,S4) on New Base
5
Ea.
$886.00
$4,430.00
0A0
$0.00
5.00
$4,430.00
5.00
$4,430-00
100.00
L-125g RemoveL-867 Junction Box (C.O. #1)
Install L-867 Junction Box, Size D, 4-Hub, Complete
24
Ea.
$79.00
$1,896.00
0.00
$0.00
22.00
$1.738.00
22.00
$1,738A0
91.6?
14.00
$4,858.00
82.35
125h (C.O. #1)
Install L-850C Semi Plush Runway Edge Light, Complete
17
Ea.
$347.00
$5,899.00
0.00
$0.00
14.00
$4,858.00
$4,620.00
$3,736.00
$4,200.00
$1,580.00
$1,240.00
2.00
8.00
8.00
79.00
62A0
$4,620.00
$3,736.00
$4,200.00
$1,580.00
$1.240.00
100.00
100.00
140.00
100.00
100A0
-125i (C.O. #1)
-125' Adjust L-861SE Runway Threshold Light
-125k InstallL-868 Junction Box, Size C. Complete
-126a RemoveL-853 RetroretlectiveMarker in Soil (C.O. #1)
-126b Reinstall L-853 Retroreflective Marker in Soil C.O. #I
2
8
5
79
62
Ea.
Ea.
Ea.
Ea.
Ea.
$2,310.00
$467.00
$600.00
$20.00
$20.00
.620.001
3,736.001
$3,000.00
$1,580.00
$1.?j10.0Q
0.00
0.00
0.00
0,00
0.00
$0.00
$0.00
$0.00
$0.00
$0.001
2.00
8.00
7.00
79.00
62.00
ru %fm=UR eldFngine«ing%Pcro&cCostFstxts
Page 3
$105,0.0
$60,060.00
$90,150.00
$78,960.00
$135,300.00
$9.79
$1,300.00
$4,560.00
$836,689.79
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.Q0
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
1.32
$138,60000
F-630a
110d-
Mobilization
Unclassified Excavation (C.O. #1
Sub de Pr aration (C.O. #1)
Place and Co act 909 ' ' Tani C.O. #1
BituminousPav' Course, (1-1/4InchMix)
Bituminous Paving Course, (1 Inch Mtx) C.O. #1)
Modified Bituminous Material C.O. #1)
Tack Coat
Insta112-3 Inch PVC Duct CE
SCE[EDULE II TOTAL
1
23,100
60,100
15,040
4,100
10,950
979
2,000
285
L.S.
C.Y.
S.Y.
C.Y.
Ton
Ton
Ton
Ohl,
L.F.
$105,000.00
$2.60
$1.50
$5.25
$33.00
$33.00$361,350.00
$0.01
$0.65
$16.00
1.32
$138,6-
132.00
23,100.00
60,100.00
15040.00
4,100.00
$60,060.00
$90,150.00
$78,960.00
$135,300,00
23,100.00
60,100.00
15,040.00
4,100,OQ
$60.060.00
$90,ISO.QO
$78,960.00
$135,300.Q0
100.00
100.00
100,00
100.00
1Q950.00
900,00
2,000.00
285.00
$361,350.0010,950.00
$9,00
$1,3$9.00
70289.00
$870,289.00
900.00Bituminous
2,000.00
285.00
$361,350.00
$9.00
$1,300.00
$4,560.00
$870289.00
100.00
91.93
100A0
100.00
104,02%
LI
CERTIFiCi it aVl \ W4 L = R .. n r L;L"KLIL4 Y Mat t$e work pedorined and the materials supplied to date, as shown on this periodic cost
accomplishment under the terms of this contract in conformitywith approved plans and P � went the actual value of
PPr P specifications; that the quantities shown were properly dettcm =
been full compliance with 111abor provisi included in the contract identified above, and in all subcontracts made under this contract,
BY: �Z 0/
shill Divisi ytheo Infrastructure Fme. Da a BY:
&ON
m:lfo=%SReldEngineminglperodiceDstEsLxls
10-29-01; 4:21PM;EAGLE COUNTY AIRPORT Isblll ;9705248247 # 1/
'r2RR111TE
�•►' formerly Gibbons & Reed Company
C(InsirRucirion s
compou SINCE
1922
October 24, 2001
Eddie Storer
Airport Manager
Eagle County Regional Airport
PO Box 850
Eagle, CO 81631
Re: Eagle County Airport
AIP No- 3-08-0020-27
Mr. Storer,
of
We are in receipt of your letter of October 16 and accept your settlement terms. Please
include the additional $96,168.48 on the final estimate along with our retention and we
will sign and return the estimate to you.
Sin ly,
Carter Ro u
Project M ge
Utah Operations
Warm Springs Office mailing Ogden Office Mailing
1000 North Warm Springs Road RO Box 30429 1555 South 1900 West P.O. Box 1477
Salt Lake City, Utah 84116 Salt Lake City, Utah 84130 West Haven, Utah 84401 Ogden, Utah 84402
(801) 526-6000 (801) 731-3181