HomeMy WebLinkAboutConsent 2022-02 3rd Partial Release of Collateral - File No. PDF-9092_Tree Farm Phase 2BOARD OF COUNTY COMMISSIONERS COUNTY OF EAGLE, STATE OF COLORADO CONSENT NO.2022 - 02 AUTHORIZING THIRD PARTIAL RELEASE OF COLLATERAL FOR PHASE 2 OF TREE FARM PLANNED UNIT DEVELOPMENT FILE NO. No. PDF-9092 WHEREAS, pursuant to C.R.S. § 30-28-137, the Board of County Commissioners of the County of Eagle, State of Colorado (the "County") entered into a Subdivision and Off -Site Improvement Agreement dated July 21, 2020 (the "SIA") with Woody Ventures, LLC, a Colorado limited liability company ("Subdivider") for Phase 2 of the Tree Farm Planned Unit Development ("Tree Farm PUD"); and WHEREAS, Subdivider provided collateral in the form of an irrevocable letter of credit in the amount of $6,984,095.88, which represented 100% of the estimated cost of the Subdivision Improvements ($6,271,446.26) and 1250r0' of the estimated cost of the Landscape Improvements associated with Phase 2 of the Tree Farm PUD ($712,649.62); and WHEREAS, pursuant to Eagle County Consent No. 2020-06, the County authorized a first partial release of collateral in the amount of $2,412,254,41, thereby reducing the collateral held by the County to $4,571,841.47; and WHEREAS, pursuant to Eagle County Consent No. 2021-01, the County authorized a second partial release of collateral in the amount of $2,760,620.45, thereby reducing the collateral held by the County to $1,811,221.02; and WHEREAS, on or about November 13, 2019, Subdivider conveyed the Subdivision property to Tree Farm RFV, LLC, a Colorado limited liability company, such property being more specifically described on the Tree Farm Final Plat recorded June 25, 2019, at Reception No. 201909565, and Tree Farm RFV, LLC assumed all obligations of the Subdivider under the SIA (Tree Farm RFV, LLC hereinafter referred to as Subdivider); and WHEREAS, on or about June 21, 2022, the County and Subdivider entered into a Second Amendment to the SIA to amend the completion date of certain Subdivision Improvements associated with a plaza to be constructed in Phase 2 ("Plaza Subdivision Improvements") and related Landscape Improvements ("Plaza Landscape Improvements"). The total estimated cost of the Plaza Subdivision Improvements is $248,949.60 and the total estimated cost of the Plaza Landscape Improvements is $91,417.30, for a total of $349,233.73. The total estimated cost of the Subdivision Improvements without the Plaza Subdivision Improvements is $6,022,496.66, and the total estimated cost of the Landscape Improvements without the Plaza Landscape Improvements is $507,406.02, for a total of $6,620,874.65; and Eagle County, CO Regina O'Brien Pgs: 11 REC: $0.00 DOC: $0.00 202214445 09/01/2022 09:27:06 AM WHEREAS, Subdivider has represented to the County that certain Subdivision Improvements and Landscape Improvements required under the SIA have been completed and the Subdivider has applied for a third partial release of collateral; and WHEREAS, based upon the written recommendations of the County Engineer set forth in Exhibit A attached hereto and incorporated herein, and the recommendation of the County Attorney, THE COUNTY FINDS that certain Subdivision Improvements and Landscape Improvements associated with Phase 2 of the Tree Farm PUD appear to be completed as of August 17, 2022, and a third partial reduction in the collateral is warranted; and WHEREAS, pursuant to Resolution 95-35, the Chair of the Board of County Commissioners, or in her absence, the Chairman Pro Tern, has the authority to approve partial releases once the release has been recommended for approval by the County Attorney; and WHEREAS, based upon the recommendation of the County Engineer attached, hereto as Exhibit A, and the recommendation of the County Attorney, THE COUNTY FINDS that a third partial release is warranted. NOW, THEREFORE, BE IT AUTHORIZED BY THE COUNTY OF EAGLE, STATE OF COLORADO: THAT, based on the recommendation of the County Engineer and the County Attorney, the Chair of the Board authorizes this third partial release of collateral in the amount of $732,035.16, thereby reducing the required collateral to $715,964.63, which represents the collateral to be held for the two-year warranty period under the SIA for the Subdivision Improvements and Landscape Improvements for Phase 2 of the Tree Farm PUD. Collateral for the Plaza Subdivision Improvements and the Plaza Landscape Improvements in the amount of $349,233,73 will continue to be held by the County in accordance with the SIA. THAT, this partial release of collateral does not represent the County's acceptance of the work purportedly completed by the Subdivider. THAT, this partial release of collateral does not commence the warranty period under the SIA. THAT, this partial release of collateral shall not in any way abrogate the rights of the County in enforcing the Subdivider's performance of its outstanding obligations under the SIA. THAT, this partial release is contingent upon the Subdivider substituting collateral in a form acceptable to the County Attorney. [Remainder of this page left intentionally blank] APPROVED by the Chair of the Board of County Commissioners of the County of Eagle, State of Colorado, pursuant to Eagle County Resolution 95-35, this day of 8/31/2022 COUNTY OF EAGLE, STATE OF COLORADO, by and Through Its CHAIR TO THE BOARD OF COUNTY COMMISSIONERS Doeu fined by: el*"eeny, Chair EAGLE COUNTY ATTORNEY DocuSigned by: By: =�--- +ILATmu, County Attorney EAGLE COUNTY ENGINEER Docuftned by: By: keA G 3CRCGWdWj4Gounty Engineer EXHIBIT A ENGINEERING DEPARTMENT MEMORANDUM E MEMORANDUM EAGLE COUNTY ENGINEERING TO: Tracy Stowell, Eagle County Attorney's Office FROM: Rickie Davies, Engineering Department DATE: August 22, 2022 RE: Subdivision Improvements Agreement, Tree Farm PUD Phase 11, Eagle County File No. PDF-009092-2020 Authorization of the Third Partial Collateral Release A written request for reduction of the collateral for the construction of portions of the improvements under the agreement was received from Dave Marrs with Geronimo Ventures LLC on August 18, 2022. The original amount from the signed Subdivision and Off -Site Improvements Agreement was: Public Improvements — $6,271,446.26 Landscaping — $ 712,649.62 Total Collateral Amount = $6,984,095.88 The first partial collateral release was approved on October 27, 2020 in the amount of $2,412,254.41. Total Collateral Amount $6,984,095.88 First Partial Collateral Release — $2,412,254.41 Remaining Collateral Amount = $4,571,841.46 The second partial collateral release was approved on July 19, 2021 in the amount of $2,760,620.45. Remaining Collateral Amount= $4,571,841.46 SrrQnd Partial Collateral Release = $2,760,620.45 Remaining Collateral Amount = $1,811,221.01 On June 21, 2022, an Amendment was approved amending the completion date for the plaza improvements/landscaping and separated out the estimated costs of construction. The developer is currently in the building construction stage for buildings on Lots E-1, E-2 & E-3. The pedestrian plaza is located with Lots E-1 & E-2 on one side and Lot E-3 on the other side of the pedestrian plaza. The rationale for amending the SIA is that the developer has concerns about the pedestrian plaza being damaged during building construction. The break out of the estimated costs of construction are in the attached "Summary of Tree Farm PUD Phase II Collateral Release". The Eagle County Engineering Department performed an inspection confirming the amount of work completed on August 17, 2022. Construction items were checked for completion as listed on the attached exhibit. The items requested for reduction were found to be constructed and completed in a satisfactory manner. The amount of work completed exceeds the amount of collateral that can be released. Eagle County Land Use Regulations Section 5-280.B.5.e.(3).(b) states, "As portions of the landscape improvements are completed, the Planning Director shall inspect them, and upon: approval and acceptance, shall authorize the release of the agreed estimated cost for that portion of the improvements, except that ten (10) percent shall be withheld until all proposed improvements are completed and approved, and an additional twenty-five (25) percent shall be retained until the improvements have been maintained in a satisfactory condition for two (2) years. " The amount that must be held as collateral for the 2 year warranty period is $715,964.63. The Eagle County Engineering Department recommends a reduction of the collateral in the amount of $732,035.16 from the $1,447,999.79 that remains on the Main SIA. This will leave a balance of $715,964.63 collateral remaining. Remaining Collateral Amount — $1,447,999.79 Third Partial Collateral Release = $ 732,035.16 Remaining Collateral Amount = $ 715,964.63 This reduction does start the warranty period. rii" y' cc: Ben Gerdes, County Engineer Beth Oliver, Deputy County Attorney Danny Stewart, Roaring Fork Engineering Jon Fredricks, Landwest Dave Marrs, Geronimo Ventures, LLC Attachment: Email Request for Reduction, Engineer's Opinion of Probable Construction Cost, Summary of Collateral Release, Photos VuI'u-J.. LI IY-V. - JV- VT J-, - ---, V ,- -.- EAGLE COUNTY Richard Davies <richard.davies@eaglecounty.us •ee Farm PUD - Collateral Releases nessage ive Marrs <dave@geronimoventures.biz> : Richard Davies <richard.davies@eaglecounty.us> Rickie, Thu, Aug 18, 2022 at 10:16 At 3reat seeing you again yesterday. Appreciate your diligence in working with us all these years... See attached related to our requests •elease of warranty collateral for phase 1 and final release of collateral (3rd LOC release) for phase 2. My notes you asked for and a :opy of what Danny Stewart prepared for the 2nd LOC release as a reference for item numbers. Let me know if you need anything 'urther on my end in order to get the BOCC to release the warranty collateral for phase 1 and hopefully final for phase 2 (excl. the Plaza 31A). David Marrs ZWef Financial Officer 3eronimo Ventures, LLC 101 Tree Farm Drive Carbondale, CO 81623 3rdReleaseRequest.TreeFarm.Aug.18.2022.pdf 3129K ITEM DESCRIPTION 9j RCM4YyrkOF STAUCFt2Z', ORL k j4 10 PE.NOVA'-rlF 1IA4yOL=.;SiORk; R414f14A'. 111 I„ Pi IVL[I'4'.I(: 1-I.WNII Tq RIMOYM OF LMALL IuNr� VMS' ... QUANTITY UNIT UNIT PRICE I TOTAL AMOUNT -- '. I LST COLLATERAL RELEASE ZND COLLATERAL RELEASE 3RD COlWERAI REIEASE I _ J 2; 177 561 ;0 (A E{_ LI 11- I k.046 +F ..SL47i4 i1 ., pq fi. 09.7: ' 5Y W $fi 11 564.59 1 5,39188 OO PrMQW.. OF aS ALTMAI IFl kWN,:71 INLA. LD) REMOs'R'-OF LIC4T ETiN�UD J EA _ SrJ.4.14 �1iY7744 528E -�.S_ Sl - a AE4du4k' 01 tr•J4.xd 54.!q ti 8_rMoym Or r'N'.i - 305f, or& rONCRE'E,S'NEV. .--- .. # L0 3+LF ri L1 LF LF Sl' 3 f@6C 17 _ 55j!:? .L]Dfil SI:.11 Sd2 $7dS' SI 157 54h N� W li;- 1/1T4R1AF T2 lyf, M -L,i.''s5':.SNIs ASf"'11r rEi7FRULL �d Ya NI RP a41F .63 Uti.:ASi :EO FXrbYAT :'Al1COk'PLM rN fir.' - _ 3a,r 7.7 f+:IN �1CrvA[;nr_ _147 0 !M_BAAWEYE MA-EFO&L IrLM'LF'i i T,.1<rr; 42 I•zrACY {r IF 535.643 _ rii7LOM S 1k 5 #S{1 CRUSHL}SAND =CP.!E#t'4G ABC '•,4iSf Nit L- 4V101 . w T{i , L5 rly SY S358} � 1 } ii S17 77-7 77 $lii a* Sib � $53�75 Sl: 2S _5151f12 CC _ S1 f 205,058.88 255 41C CL�53! 6 uiROHA=f -#P 1x7 CLASi f xMLIULD+4 _ _ _ _ ;d3 k�:TTMIN S^N4LT.;] NG2Q-p5iiPG. i%YLIY _ 70HGrPAIiLAhMI.T( NG5M!7)}IPG!8Bit, " - 4E r. }7 1 Up 1.'TOr:?% $ +�o2com 5138 701 7} REENNER 4i:Cl1.25 _ ;:fi NAM xl+.'300t: $ic493Fa i}[Y"Qc � � �' S7 a;6 t $ 113,195.04 211,411.00 193.656.56 s 31,281.25 + 113 "-tL IT VA4I Ir!Nl ia',N"f CQNCgF!r PAY-k+=NT[41Nf,N, COhYRE1 :lI=NT 417N'.N?;SPFCli I I v.G1CR rRC155144.k .-- Sin T45w _- . j4D €r 5M., `4 14c 1kNCxLI{PA'11N'�N rr jG 1 I 19651 $17750 7YJcolUM'FkA':FM"HTff,IW! kf'NFORCE.3 k+}i7 lim?5 '3lZ CONC rE RO",rER SEL Oh 19A S4 il'+SP -�- �'$4 -4 30 G{CITE MLI ISrlAkAT,.)1�riAt% r 7m yr - n::rkhlNfr AL. IeEDI RUCK V.A1'.I _ 311Eq rA'�WN: 'N+'I._ISr!rI/{7, MAW84OrKl -- -. 5*)6 _-Jli i}505F ii_ ^-?.LT�R] SikL,1 ST 3Eil R�->•lilN4 Wnl. Il:.{i i Sl i.-II ':PWI:"yIN4MI ]d0 4ANORAA ...- $6-42. SI ,Yd-9.3k -$-,11 SiU 11 $lef �l r• ~3Ljr.f, Ti0d "C40a}06wATkR Y550_F ri0 a• flrlt .i5 s*G:it1 _ _ _ T �O 4' SiI, 40 SLf;tii52-1 PER TkE-W" i:w "A $35 4r $+= 41 "_ S+:_26 .� 1 $ly ar id.1 L S I23.-! +'9f+ 1 S FA**l4 T iB�i i'Si01.OR;LMA4ti 5{Wil 140,L•1,1l,", if �150"!C'RC6 i'OPN41,i�ail21 ^i �!~ 3!il i LB.22040 Lw', 11-70'.{,.• T,'+T'�.°4275 1A.0 L - ',2,4--'$Ti75J8 2 h "I•p- }E' • 567 ZS .,${ly1:6 1 Slcsi' LA $16VbLm; J� SB:}t8'i rf, 5s,dnk 1 '-si9179ili ' 5A25? 525.1f8.5} __il;p.n,l;t 52i,lil.l5 ¢ sEB!'S{YrfR=,RL{SDR35; p6;1:IVQF!;.A1{$ IU'}od 1N1 I1 N-L+WiA.7'ry1p' auFNLF.T!PzC'AL DRAT4j4444CH WMT-4 � iTRENCH ;SC -J :Li'STNCTU91{SPO[1AO jWtsS' $10.di2.24 S74.Y+S.M 53F,Ti3.ii Sld, ".7Y y}d, 11.FA siq,554,6+ 54,ZZE.lY yC.sTCR+4OWN nRSM¢U}w1k1tLY/R+ryu}¢ S;O iSO/Sl ORWN �iRNHMES 520 S+NIZ . EEW RMAMDLES 50CF'S':LxiASFltlo(i5A00EAiH SSC FE NC£4486-6- ~,�Y.• 4 SicnU RAIL;s-0E.LBLIlPE5;14h1LN1; Ll:i 9µa. I ,�'.r,n e.. $1=r.00 i S2}g4g.0D $iYY. 00 _ 13. D6 w 9.3:2 k }1C'[+pM[RLT�E1n11114-P S1{ B.76TAPV WARNIw5$ si, tjRaoqbGUvrrZ 13KCWJ iSKrIE'AA 3 S 61 ley 51 Sr5 `C s9.312.50 l+r: L1r Idc+IE 516 %, )99.441',n W 47.145 -' ' B ND U. il'fi Lfr1 V-8> FODY 53 ELECTRIC LIGHT N UI F' iii.82.'0a III lie P T41.4s''Hi vu. aol, # i2 N -.l..- 700 ELECTRICAL LIGHTING- POLE LIGHTS, BOLLARDS, ETC. 232- t - L - iTdd�LE iLUJ LF lVLA ILS -314. -_.'14.01 n1, SL4S 40 523,31i S6 1 ..a S11"A11-00 5613 111?L ei -- -- $344,411.00 740 LICHT$TANDARD FOUNDATION 790 SIGN PANELS WITH 2- POSTS (CLASS 1) 15 14 EA EA $1,875.00 $439.59 528,125.06 $6,854.12 BOO STEELSIGN SUPPORT 2'ROUND 11 EA $62500 56,875.00 C01EY:LT T'J E ST1ii W„ sRUNE 23'J 0' YfAITh SLR'ff{Sn +S'f:.irE ti•'Al I!d0ll D1�W14ArfYP1LE.s "- #67F¢i'S1G.inNT$6.D?F4C...-_----_ O LDNsfh-ri4N54'.ikY1ti 940 EPOKY PAVEMENT MARKING _ }is EA LF _.. S1'12418 -•$*7 7G $L!910 58756 )b _ 25i5LF µ{, 1 15 1'A LS GAL 5d.2ek 7# 5114. 15j04 5208.33 $3,724.95 95p STEELGRATES AT PLAZA aS8 ,r.0. M[a1n wti-V.0 102 lA WING DECK PLATFORM ILs �7 1 $44,312.50 ,LjR6 LS 5102,370.38 548,312,50 $102 370.38 $350,000.00 5 6,271,446.26 S 2,1112A.11141 104 SEWER LIFT STATON SL$ 1 $31SkOW00 EOPC TPUlj 6 7-?WA-- IaZZ,D80.77 a) IA m a oc L O u m r a G a E m U. N GJ H O E E 7 tA O M en 00 e-r e-0 VI [- O n 6.4 V M V 01 ltl 00 M N O rl Ul Ul 00 CY O rn in M v o + N N N N tao N N N O 00 0i1 00 01 Ql �O 00 1- ri 01 1, V 111 00 C 00 rl 1% 1� M M O -tr e0 M O w m vi m rl &A rl M V lA r1 N N N N N N N t 10 D (U W 0 0. v >- O L/I Y 10 N O c 16 6) � V N R wm U.0 LL1 c y v a d E E N }O w N 00 Y a n a u, c--— w w E ad a yC P �p M- T 3 E 0 (U G `a E E E o ie E Q mom`-' w 06 w C 'CL 3Ln 0 m �o Am N M ate+ m t1 m o 0 G c cJ F 1e C U J 7 N 0 N J �D 6L :: W �_ 9i5lH m 16 Ln O N V H N N N a N 0 C 3 O E CC rn f` N M LA f N rq N rn W M M N N N N N N ti to m UD � IN � n -1-1 tp V V O O Ol ll1 ll1 V elkN in in Q1 C' O 0e O N 00 O 1- N N' 1l7 ID nt N r n 1` n N N N N N N V1 N ui cl N Q Qp c N 7 c Q a � Q y m 76 %O O 10 — N N .. m — N 0 r1 = O V } a V 00 _O.. 7 Q -4-4 t_L N ei cc M N 7cr O7 � O7 3 C O0 y i m a u Q �p : D: m G a m G c 0 O O0 = al E 'c i6 o 2 cu m 1O = lu V O w 0 ly p E CC 'x a ,. a cmo H �yi F N H M C H