HomeMy WebLinkAboutC22-202 HR Green Fiber and Broadband
Version2.0 12172018
FIRST AMENDMENT
HR GREEN FIBER AND BROADBAND, LLC
PROFESSIONAL SERVICES AGREEMENT
THIS AMENDMENT, made this _________________ by and between, Eagle County, Colorado,
(hereafter “CLIENT”), and HR GREEN FIBER AND BROADBAND, LLC (hereafter "COMPANY"), for
professional services concerning:
Dotsero High-Level Design and Next Steps / COMPANY Project Number: 200040
hereby amends the original Professional Services Agreement dated September 30, 2020 (C20-371) as
follows:
The term of the Original Agreement is hereby extended to the December 31, 2022.
The CLIENT and COMPANY agree to amend the Scope of Services of the original Professional
Services Agreement for additional compensation as follows:
TASK 0 – Kickoff Meeting
COMPANY will coordinate with CLIENT to arrange a Kickoff Meeting to define the information to
be transferred, milestones and timeline of the project.
TASK 1 – Develop a Base Map
In the original project (200040), CLIENT provided some GIS information and COMPANY developed a
base map germane to that project. The same process will need to be completed for this project.
Because of steps in the original project, the base map might be partially complete, but analysis will
need to be completed and information gathered for the Dotsero area.
DELIVERABLE: GIS Base Map
Task 2 – Evaluate Transport Options
Any infrastructure to be deployed in Dotsero will require connection to transport technology (fiber or
relay signals). COMPANY will evaluate a Project THOR meet me center, CDOT fiber, connection to
other fiber and connection through other technologies.
DELIVERABLE: Report of findings of transport options and costs
Task 3 – Evaluate Technology Options
The two most common options for broadband improvement in the Dotsero area are Fiber to the
Premise (FTTP) and Point-to-Point. COMPANY will evaluate these options to see how available they
are, how effective they would be in the Dotsero circumstances.
DELIVERABLE: Report of findings of applicable technology options in the Dotsero area
Task 4 – High-Level Design of the Two Dotsero Areas
COMPANY will create a high-level design of the two areas of Dotsero (the mobile home park north of
the Interstate and the homes south of the Interstate. The high-level design will consist of a desktop
drawing of the two areas (not field verified) and a high-level listing of the costs for construction.
Utilizing the high-level costs, COMPANY will develop a cost/revenue benefit analysis regarding the two
scenarios of building out only the Dotsero mobile home park and building out the two areas in Dotsero.
DocuSign Envelope ID: E9EB9539-6872-4743-BAEC-710AEBB0A1BE
5/17/2022
Amendment 1 to Professional Services Agreement
Holy Cross Energy Fiber Design
200291
Page 2 of 3
Version1.0 07012017
DELIVERABLES:
• Two high-level designs and associated costs of construction
• Two high-level cost/benefit analysis of the two options (mobile home park only and entire
Dotsero area)
Task 5 – Provider Outreach
From tasks 0 – 4, CLIENT will have information to either decide to further explore building the needed
infrastructure as a County project or to partner with a telecommunications provider to negotiate building
the infrastructure in a form of partnership. In this Task, COMPANY will collaborate with CLIENT to
arrange a meeting with area providers to ascertain interest from providers in negotiating an
arrangement to deploy infrastructure.
DELIVERABLES: Two group provider meetings (conducted remotely) or five individual provider
meetings (conducted remotely). Also, COMPANY will provide summaries of the provider meetings.
The final deliverable will be a final report that includes a summary of findings of Tasks 1 – 4. Also, in
the final report will be: 1) the two technical designs in Task 2 with recommendations on viable ways to
move forward 2) each recommendation will include a high level suggested approach on how to
realistically move forward 3) estimated costs of each 4) and insight into how to fund those costs.
In consideration for these services, the CLIENT AGREES to authorize the payment for services
performed by COMPANY on the following basis:
A lump sum amount for the tasks above of $38,260
Costs are broken out per phase as:
Project Management $3,960
Task 0 Kickoff $2,000
Task 1 GIS Base Map $4,450
Task 2 Transport Options $5,750
Task 3 Technology Options $5,250
Task 4 High-level Design $8,785
Task 5 Provider Outreach $8,065
Task 5 is at the option of Client. If Client does not choose to pursue this task, the total will be $30,195.
The total authorized compensation after this Amendment, including the original Professional Services
Agreement increases the total compensation amount from the original Agreement of Sixteen Thousand
Four Hundred Seventy dollars ($16,470) to the new amount (including this First Amendment) not to
exceed Fifty four thousand seven hundred thirty dollars ($54,730).
THIS AMENDMENT is subject to all provisions of the original Professional Services Agreement.
THIS AMENDMENT, together with the original Professional Services Agreement and all previous
amendments represents the entire and integrated AGREEMENT between the CLIENT and COMPANY.
DocuSign Envelope ID: E9EB9539-6872-4743-BAEC-710AEBB0A1BE
Amendment 1 to Professional Services Agreement
Holy Cross Energy Fiber Design
200291
Page 3 of 3
Version1.0 07012017
THIS AMENDMENT executed the day and year written above.
COUNTY OF EAGLE, STATE OF COLORADO,
By and Through Its COUNTY MANAGER
HR GREEN FIBER AND BROADBAND, LLC
By: Jeff Shroll, County Manager By
Edward K. Barrett
Practice Leader
DocuSign Envelope ID: E9EB9539-6872-4743-BAEC-710AEBB0A1BE