HomeMy WebLinkAboutC22-158 Holy Cross Energy3799 HIGHWAY 82∙P.O. DRAWER 3350
GLENWOOD SPRINGS, COLORADO 81602
(970) 945-5491∙FAX (970) 945-4081
A Touchstone Energy Cooperative
March 10, 2022
Tanya Dahlseid
P.O. Box 850
794 Fairgrounds Rd.
Eagle, CO 81631
RE: WO# 24439 Eagle County Fair Carnival Transformer
Dear Eagle County Government,
Holy Cross Energy has completed a design and cost estimate for providing electric service to the above
referenced project, hereinafter the “Project”. Our facilities will be installed as shown on the attached
sketch. The owner or developer of the subject Project is hereinafter referred to as the “Owner”.
The estimated cost of construction is as follows:
Total estimated cost of underground
construction $28,300.00
Standard Construction Allowance $(1,000.00)
Construction deposit consisting of
equivalent overhead credits (refundable) $22,700.00
Contribution in aid of construction (non refundable) $4,600.00
Total payment required before
starting work on the project $27,300.00
Less prepayment received $(2,000.00)
Additional payment required $25,300.00
Electronic payments are now being accepted with a 2.5% Convenience Fee. Please contact us if you’d like
to know more.
The above figures are only estimates. After the job has been completed, the actual cost of construction
will be determined. The Owner’s contribution and deposit will be adjusted to reflect the actual cost by
making a refund or further assessment. Execution of this document constitutes the Owner’s agreement to
pay any further assessment in a timely manner. This payment is being made by (and any refunds at final
accounting will be sent to):
Payee:
Phone:
Address:
Adjusted construction deposits are available for refunds over a ten year period as specified by Holy Cross
Energy's Line Extension Policy. These refunds will be paid to (unless otherwise directed in writing):
Name:
Address:
Eagle County
P.O. Box 850, Eagle, CO 81631
Eagle County
P.O. Box 850, Eagle CO 81631
970-328-8600
DocuSign Envelope ID: 51F2A976-345B-4B70-9D60-9B73F2176590
Dahlseid
March 10, 2021
Page Two
Address:
Our power facilities must be installed on an easement. If facilities have to be relocated a new easement
may be required.
The following conditions are hereby noted:
1.A Load Form must be submitted for this project. These forms are available on-line and can be
found by visiting www.holycross.com.
2.Holy Cross Energy has separate Policies and Procedures for Generation Interconnections. Please
visit www.holycross.com or send an e-mail to renewables@holycross.com for more information.
3.Holy Cross Energy has implemented a policy which requires that the Owner provide all excavation,
backfill, compaction and cleanup needed for installation of the underground power system
extension to serve the Project. The Owner must also set all vaults and install all conduits as
specified by Holy Cross Energy’s design for the Project and the enclosed construction
specifications. Holy Cross Energy will supply all material which can be picked up by the Owner at
the appropriate storage yard. The cost of this material is included in the job cost estimate. The
attached Trench, Conduit, and Vault Agreement must be properly executed by the Owner and
returned prior to the start of excavation.
4.No excavation will be undertaken within five (5) feet of existing underground power lines except
under the on site supervision of a Holy Cross Energy employee.
5.It shall be the Owner’s responsibility to ensure that splice vaults, switchgear vaults and
transformer vaults installed hereunder for the Project are accessible by Holy Cross boom trucks
and other necessary equipment and personnel at all times. The use of such access by Holy Cross
shall not require removal or alteration of any improvements, landscaping, or other obstructions.
The ground surface grade shall not be altered within ten (10) feet of said splice, switchgear and
transformer vaults, nor along the power line route between the vaults. The ground surface grade
at said transformer and switchgear vaults shall be six (6) inches below the top of the pad. The
ground surface grade at said splice vaults shall be even with the top of the pad. The manhole
opening of said splice vaults shall be uncovered (excluding snow) and accessible at all times.
Improvements, landscaping or any other objects placed in the vicinity of said transformers and
switchgear shall be located so as not to hinder complete opening of the equipment doors. The
ground surface within ten (10) feet of said transformer and switchgear doors shall be flat, level
and free of improvements, landscaping, and other obstructions. Improvements, landscaping and
other objects will be kept a minimum of four (4) feet from non-opening sides and backs of said
transformers and switchgear. Owner hereby agrees to maintain the requirements of this
paragraph and further agrees to correct any violations which may occur as soon as notified by
Holy Cross Energy. Said corrections will be made at the sole cost and expense of Owner.
6.Secondary voltage available will be 208Y/120, three-phase.
7.Secondary facilities shall be installed in accordance with National Electrical Code and Holy Cross
Energy specifications. All meter locations must be approved. Any service over 200 amps or 240
volts must have prior written approval from Holy Cross Energy.
8.It will be the Owner’s responsibility to extend underground secondary entrance conductors from
the pad-mounted transformer, or junction box, to points of power usage.
9.All underground services shall be installed in conduit ahead of the meter. All underground
services must be in conduit beneath roads, driveways, and other areas of difficult excavation.
DocuSign Envelope ID: 51F2A976-345B-4B70-9D60-9B73F2176590
Dahlseid
March 10, 2021
Page Three
10.Low voltage starting will be required on all three-phase motors larger than 25 HP and all single-
phase motors larger than 10 HP.
11.Motor protection from phase loss and other voltage problems should be provided. This
equipment shall be installed and maintained at the expense of the Owner.
12.The above mentioned cost estimate does not include connect fees or meter deposits, if required.
Arrangements for payment of these items and for scheduling the actual meter installation should
be made through the local Holy Cross Energy office.
13.We attempt to complete all projects in a timely manner. However, highest priority is given to
maintaining service to our existing consumers. This fact, along with inevitable construction
delays, will not allow us to guarantee a project completion date.
14.All Holy Cross Energy rules and regulations will be followed.
15.When Holy Cross Energy is in receipt of the Owner’s check in the amount of $25,300.00, all
necessary executed easements, other permits, if required, a completed “Residential Load Form” or
“General Services Load Form”, the executed trench agreement, and the signed original of this
letter agreement (below), the job can be scheduled for construction. Holy Cross Energy does not
accept checks with lien waivers.
Sincerely,
HOLY CROSS ENERGY
Ezra Velez,
Engineering Department
evelez@holycross.com
970-987-0158
EV:MM
Enclosure
The above terms and conditions are hereby
agreed to and accepted
COUNTY OF EAGLE, STATE OF COLORADO, By and
Through Its COUNTY MANAGER
By:
Jeff Shroll, County Manager
W/O#22-24439:43-44:Eagle County Fair Carnival Transformer
22-24439 Contract Letter
DocuSign Envelope ID: 51F2A976-345B-4B70-9D60-9B73F2176590