HomeMy WebLinkAboutC97-267 Elam ConstructionC'972675O
CHANGE ORDER NUMBER 1
CONTRACTOR Elam Construction, Inc.
Contract for Bellyache Ridge Paving Project Contract Date June 4, 1997
TO: Elam Construction, Inc.
You are directed to make the changes noted below in the Subject Contract. Appropriations
to cover the costs of additional work have been made.
EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS
By:
v
Johnnette Phillip , hairman
DATE:
Nature of Changes: Final adjusting change order
ITEM DESCRIPTION
1. Hot Bituminous Pavement, from
7,750 Tons @ $32.30/ton to
7,735 Tons @ $32.30/ton
INCREASE
DECREASE
$484.50
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to this Change Order $259,825.00
Net Decrease Resulting from this Change Order $ 484.50
Current Contract Price Including this Change Order $259,340.50
Change Order No. 1
Page 2
Contract Time Prior to this Change Order August 31, 1997
Net Resulting from this Change Order No Change
Current Contract Time Including this Change Order August 31, 1997
The above changes are recommended:
Don Fessler
Road and Bridge Director
Date:
The above changes are accepted: Elam Construction, Inc.
By:
Title: AWW *r f�� Ff-t?--
Date: !a/?/�i'7