HomeMy WebLinkAboutC97-284 Elam ConstructionC'97 28 4 -5 0 CHANGE ORDER NUMBER 3 CONTRACTOR Elam Construction, Inc. Contract for Eagle-Vail/West Vail Paving Contract Date April 28, 1997 --------------------------------------------------- -------------------------------------------------- TO: Elam Construction, Inc. You are directed to make the changes noted below in the Subject Contract. Appropriations to cover the costs of additional work have been made. EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS By- DA.:n ---------------------------------- Nature of Changes: ITEM DESCRIPTION 19. Manhole Adjustments: Change Order Number 2 increased contract for 56 manhole adjustments. Correct quantity should have been 55. Deduct 1 manole adjustment @ $135 ----------------------------- ---------------------------- INCREASE DECREASE $135.00 These changes result in the following adjustment of Contract Price and Contract Time: Contract Price Prior to this Change Order $392,243.00 Net DECREASE Resulting from this Change Order $ 135.00 Current Contract Price Including this Change Order $392,108.00 -------------------------------------------------- Change Order No. 3 Page 2 Contract Time Prior to this Change Order August 1, 1997 Net Resulting from this Change Order No change Current Contract Time Including this Change Order August 1, 1997 The above changes are recommended: Don Fessler Road and Bridge Director Date: The above changes are accepted: Elam Construction, Inc. By: f Title: Ago#, /ij#wON-31— Date: !b — Z3– /'%'