GRANT AGREEMENT
Part I - Offer
Date of Offer: APR - 8 196
Airport: Eagle County Regional Airport
Project Number: 3-08-0020-22
Contract Number: DOT-FA96NM-1017
County of Eagle, Colorado
(herein called the "Sponsor")
The United States of America (acting through the Federal Aviation Administration, herein called the "FAA")
Whereas, the Sponsor has submitted to the FAA a Project Application dated January 23, 1995 for a grant of Federal funds
for a project at or associated with the Eagle County Regional Airport which Project Application, as approved by the FAA,
is hereby incorporated herein and made a part hereof, and
Whereas, the FAA has approved a project for the Airport (herein called the "Project") consisting of the following:
Expand Air Carrier Apron (approx. 12,175 s.y.),
all as more particularly described in the Project Application.
FAA Form 5100-37 (10/89) 1
Now therefore, pursuant to and for the purpose of carrying out the provisions of Title 49, U.S.C., Subtitle VII, Part B, and
in consideration of (a) the Sponsor's adoption and ratification of the representations and assurances contained in said Project
Application and its acceptance of this offer as hereinafter provided, and (b) the benefits to accrue to the United States and
the public from the accomplishment of the Project and compliance with the assurances and conditions as herein provided,
The Federal Aviation Administration, for and on behalf of the United States, hereby offers and agrees to pay, as the
United States share of the allowable costs incurred in accomplishing the Project, 90.00 percent.
This Offer is made on and subject to the following terms and conditions:
Conditions
The maximum obligation of the United States payable under this offer shall be $1,086,810. For the purposes of any
future grant amendments which may increase the foregoing maximum obligation of the United States under Title
49, U.S.C., section 47108(b), the following amounts are being specified for this purpose:
$-0-for planning
$1,086,810 for airport development and noise program implementation
2. The allowable costs of the project shall not include any costs determined by the FAA to be ineligible for
consideration as to allowability under the provisions of Title 49, U.S.C., subtitle VII, Part B..
Payment of the United States share of the allowable project costs will be made pursuant to and in accordance with
the provisions of such regulations and procedures as the Secretary shall prescribe. Final determination of the
United States share will be based upon the final audit of the total amount of allowable project costs and settlement
will be made for any upward or downward adjustments to the Federal share of costs.
4. The Sponsor shall carry out and complete the Project without undue delay and in accordance with the terms hereof,
and such regulations and procedures as the Secretary shall prescribe, and agrees to comply with the assurances
which were made part of the project application.
5. The FAA reserves the right to amend or withdraw this offer at any time prior to its acceptance by the Sponsor.
This offer shall expire and the United States shall not be obligated to pay any part of the costs of the project unless
this offer has been accepted by the Sponsor on or before May 31, 1996, or such subsequent date as may be
prescribed in writing by the FAA.
7. The Sponsor shall take all steps, including litigation if necessary, to recover Federal funds spent fraudulently,
wastefully, or in violation of Federal antitrust statutes, or misused in any other manner in any project upon which
Federal funds have been expended. For the purposes of this grant agreement, the term "Federal funds" means funds
however used or disbursed by the Sponsor that were originally paid pursuant to this or any other Federal grant
agreement. It shall obtain the approval of the Secretary as to any determination of the amount of the Federal share
of such funds. It shall return the recovered Federal share, including funds recovered by settlement, order or
judgment, to the Secretary. It shall furnish to the Secretary, upon request, all documents and records pertaining to
the determination of the amount of the Federal share or to any settlement, litigation, negotiation, or other efforts
FAA Form 5100-37 (10/89)
taken to recover such funds. All settlements or other final positions of the sponsor, in court or otherwise, involving
the recovery of such Federal share shall be approved in advance by the Secretary.
The United States shall not be responsible or liable for damage to property or injury to persons which may arise
from, or be incident to, compliance with this grant agreement.
Special Conditions
9. The Sponsor will carry out the project in accordance with policies, standards, and specifications approved by the
Secretary including but not limited to the advisory circulars listed in the "Current FAA Advisory Circulars for AN
Projects," dated May 1, 1995, and included in this grant, and in accordance with applicable state policies,
standards, and specifications approved by the Secretary.
10. Unless otherwise approved by the FAA, it will not acquire or permit any contractor or subcontractor to acquire any
steel or manufactured products produced outside the United States to be used for any project for airport
development or noise compatibility for which funds are provided under this grant. The Sponsor will include in
every contract a provision implementing this special condition.
11. It is understood and agreed by the parties hereto that the maximum obligation of the United States for this grant
agreement may, if requested by the Sponsor and approved by the FAA, be increased as provided in Title 49,
U.S.C., Section 47108(b) to cover increased eligible and allowable development project costs. Upon approval of
the Sponsor's request for such an increase, FAA will advise the Sponsor by letter of the new grant amount.
Issuance of such letter will constitute an amendment to this agreement and the maximum grant obligation of the
United States will be adjusted to the amount specified.
12. The Sponsor agrees to perform the following:
a. Furnish a construction management program to FAA prior to the start of construction which shall detail the
measures and procedures to be used to comply with the quality control provisions of the construction
contract, including, but not limited to, all quality control provisions and tests required by the Federal
specifications. The program shall include as a minimum:
(1) The name of the person representing the sponsor who has overall responsibility for contract
administration for the project and the authority to take necessary actions to comply with the
contract.
(2) Names of testing laboratories and consulting engineer firms with quality control responsibilities on
the project, together with a description of the services to be provided.
(3) Procedures for determining that testing laboratories meet the requirements of the American Society
of Testing and Materials standards on laboratory evaluation, referenced in the contract
specifications (D 3666, C 1077).
(4) Qualifications of engineering supervision and construction inspection personnel.
FAA Form 5100-37 (10/89)
(5) A listing of all tests required by the contract specifications, including the type and frequency of
tests to be taken, the method of sampling, the applicable test standard, and the acceptance criteria
or tolerances permitted for each type of test.
t
(6) Procedures for ensuring that the tests are taken in accordance with the program, that they are
documented daily, that the proper corrective actions, where necessary, are undertaken.
b. Submit at completion of the project, a final test and quality control report documenting the results of all
tests performed, highlighting those tests that failed or did not meet the applicable test standard. The report
shall include the pay reductions applied and reasons for accepting any out -of -tolerance material.
C. Failure to provide a complete report as described in paragraph (c), or failure to perform such tests, shall,
absent any compelling justification, result in a reduction in Federal participation for costs incurred in
connection with construction of the applicable pavement. Such reduction shall be at the discretion of the
FAA and will be based on the type or types of required tests not performed or not documented and will be
commensurate with the proportion of applicable pavement with respect to the total pavement constructed
under the grant agreement.
d. The FAA, at its discretion, reserves the right to conduct independent tests and to reduce grant payments
accordingly if such independent tests determine that Sponsor test results are inaccurate.
FAA Form 5100-37 (10/89) 4
The Sponsor's acceptance of this Offer and ratification and adoption of the Project Application incorporated herein shall be
evidenced by execution of this instrument by the Sponsor, as hereinafter provided, and this Offer and Acceptance shall comprise a
Grant Agreement, as provided by Title 49, U.S.C., Subtitle VII, Part B, constituting the contractual obligations and rights of the
United States and the Sponsor with respect to the accomplishment of the Project and compliance with the assurances and conditions
as provided herein. Such Grant Agreement shall become effective upon the Sponsor's acceptance of this Offer.
United States of America
.Federal Aviation Administration
Manager, Denver Airports District Office
Part II - Acceptance
The Sponsor does hereby ratify and adopt all assurances, statements, representations, warranties, covenants, and agreements
contained in the Project Application and incorporated materials referred to in the foregoing Offer and does hereby accept this Offer
and by such acceptance agrees to comply with all of the terms and conditions in this Offer and in the Project Application.
Executed this day of 19 .
is COUNTY OF EAGLE, COLORADO
G
By: _zy
(SEAL) / `� Sppo+nsor's Desi ed Offici Representative
Attest: a itn +b `OQ Title: rI _
Title: r
Certificate of Sponsor's Attorney
I, a, M2S I ' I� 1 �Z4 acting as Attorney for the Sponsor do hereby certify:
That in my opinion the Sponsor is empowered to enter into the foregoing Grant Agreement under the laws of the State of Colorado.
Further, I have examined the foregoing Grant Agreement and the actions taken by said Sponsor relating thereto, and find that the
acceptance thereof by said Sponsor and Sponsor's official representative has been duly authorized and that the execution thereof is in
all respects due and proper and in accordance with the laws of the said State and Title 49, U.S.C., Subtitle VII, Part B. In addition,
for grants involving projects to be carried out on property not owned by the Sponsor, there are no legal impediments that will prevent
full performance by the Sponsor. Further, it is my opinion that the said Grant Agreement constitutes a legal and binding obligation
of the Sponsor in accordance with the terms thereof.
Dated at this day of
Signature of Sponsor's Attorney