HomeMy WebLinkAboutECAT11-008 Shaw Constructrion First Amendment FIRST AMENDMENT TO AGREEMENT BETWEEN EAGLE COUNTY AIR
TERMINAL CORPORATION AND SHAW CONSTRUCTION APPROVING THE
GUARANTEED MAXIMUM PRICE, BUDGET, AND CONSTRUCTION SCHEDULE
FOR IMPROVEMENTS AT THE EAGLE COUNTY REGIONAL AIRPORT
THIS FIRST AMENDMENT is made and entered into this day of October, 2011 between
the Eagle County Air Terminal Corporation, acting by and through its Board of Directors
( "ECAT ") and Shaw Construction (hereinafter referred to as "Contractor "). Together all shall be
referred to as "Parties."
WHEREAS, ECAT and Contractor entered into a Preconstruction and Construction Agreement
for Improvements at the Eagle County Regional Airport dated September 20, 2011 ( "Original
Agreement ") and the Parties desire to amend the Original Agreement as follows; and
WHEREAS, the Original Agreement called for the provision by Contractor of a proposed
Guaranteed Maximum Price (hereinafter referred to as "GMP "), detailed budget and construction
schedule to the County; and
WHEREAS, the GMP, budget and construction schedule must be approved by the Eagle County
Project Manager and ECAT before Contractor may be authorized to commence construction
services; and
WHEREAS, the 100% Design Documents and Specifications, attached hereto as Exhibit D,
have been completed and presented to the Contractor; and
WHEREAS, Contractor has presented to the County Project Manager the GMP, detailed budget
and construction schedule, attached hereto as Exhibit E; and
WHERAS, the Eagle County Project Manager and ECAT wish to approve the GMP, detailed
budget and construction schedule as conditioned herein and authorize the issuance of a Notice to
Proceed with Construction Services.
In consideration of the terms and conditions of the Original Agreement, the sufficiency of which
is hereby acknowledged, ECAT and Contractor hereby agree to the following:
THAT, the 100% Design Documents and Specifications, the GMP, detailed budget and
construction schedules attached hereto are hereby accepted by the undersigned and
incorporated into the Contract Documents as defined in Article 12 of the Original
Agreement.
THAT, Article 12 of the Original Agreement shall be modified with the addition and
incorporation of the following Contract Documents:
"Article 12.6. Exhibit "D ": 100% Design Documents and Specifications, "New Checked
Baggage Inspection System" dated September 1, 2011 as issued by BNP Associates on
September 2, 2011.
"Article 12.7. Exhibit "E ": Guaranteed Maximum Price, (GMP), Budget and
Construction Schedule, including attached exhibits, for the Eagle County Regional Airport
dated September 27, 2011."
THAT, Contractor is hereby designated as the Construction Manager /General Contractor for
• the construction of the Eagle County Regional Airport Improvements, New Checked
Baggage Inspection System.
THAT, the Eagle County Project Manager is authorized to issue a Notice to Proceed to
Contractor to perform those Construction Services set forth in the Original Agreement.
ECAT and Contractor agree that, except as expressly altered, modified and changed in this First
Amendment, all terms and provisions of the Original Agreement shall remain in full force and
effect, and are hereby ratified and confirmed in all respects as of the date hereof.
This First Amendment shall be binding on the Parties hereto, their heirs, executors, successors,
and assigns.
IN WITNESS WHEREOF, the parties have executed this First Amendment on the day and year
first above written.
// SIGNATURE PAGE TO FOLLOW //
G: \Capital Projects - Active\Airport In -Line Baggage System \ Shaw \Contract\Pinal Amendment #1.DOC 2
EAGLE COUNTYAIR TERMINAL CORPORATION,
ATTEST: By and Through Its : CARD'"? 'l ' CTORS
By: _ o f 4 .d -- V -wow
Teak Simonto P * 'r * . • ey, President - - 'I1'- e
Clerk to the Board of c ocoeAO ° YU U" VA J/ w '
County Commissioners
EA E C UNTY PROJECT MANAGER:
By:
Rick Ullom
e0 001001110/ %
`\�� G�„L M,q � / . � 'i ' � CONTRACTOR:
By: / _ L --._
s .,0,u1 Pity), •
.
••• +0® • • — Name: C I -Atzi ATlk.wv3oy
• .
( PA �B.. s Q •::
- . i9 Title: Gxzc. �/.P.
• E li e , OF i `
GO oe %
STATE OF COLORADO )
) SS.
COUNTY OF /fir' )
The foregoing instrument was acknowledged before me by eL //< /9T /<' /iUSO42.) ,
this 4 day of 0G-7 , 2011.
My commission expires: Vc= - ,30/..2_ ij .,��
G: \Capital Projects - Active \Airport In -Line Baggage System \Shaw\Contract\Pinal Amendment #1.DOC 3
Exhibit D
100% design Documents and Specifications
New Checked Baggage Inspection System
September 1, 2011
Issued by BNP Associates, Inc. on September 2, 2011
For purposes of this back-up material this
Exhibit has been omitted due to file size
and paper requirements, and is available
upon request.
Exhibit E
Guaranteed Maximum Price (GMP), Budget, and Construction Schedule
Including Attached Exhibits,
for the Eagle County Regional Airport
Dated September 27, 2011
SHAW EAGLE COUNTY AIRPORT TERMINAL Page 1
Checked Baggage Inspection System 10/3/2011 4:39 PM
GMP Estimate - Revised September 28, 2011 ECAT CB /S GMP 11- 09- 27r2.pee
Project name ECAT CB IS
Eagle County Airport
Gypsum
CO
Estimator rk
Labor rate table 1
Job size 31726 sf
Bid date 9/27/2011
Report format Sorted by 'Group phase /Phase'
'Detail' summ ary
Allocate addons
Print sort level notes
•
. •
• SHAW EAGLE COUNTY AIRPORT TERMINAL Paget
Checked Baggage Inspection System 10/3/2011 4:39 PM
GMP Estimate - Revised September 28, 2011 ECAT CBIS GMP 11- 09 -27r2. pee
Group Phase Description Takeoff Quantity Total Cost/Unit Total Amount Previous Budget/Notes
002000 SITEWORK
002220 SITE DEMOLITION
Site Electric to new Generator 1.00 Is 25,660.00 /Is 25660 Schofield
Demo Paving at Elect Conduit 324.00 sf /sf
Demo Paving of Generator 173.00 sf /sf
Saw Cut Paving at Elect Conduit 432.00 If /If
' Clean -up
8.00 hr 24.32 /hr 198
Clean -up -8.00 hr 24,32 /hr
Haul Trash (195) Included with RFP
incl /incl
SITE DEMOLITION /sf 25,660
002225 SELECTIVE DEMOLITION
Protect Existing Finishes during Demo 1.00 Is 1,966.49 /Is 1,966
Visquene Dust Partition 860.00 sf 1.11 /sf 955 .
Demo Ceiling at Ticketing 641.00 sf 2.90 /sf 1,859
Demo Partition for Conveyor - W / 7.75 18.00 sf 2.90 /sf 52
Demo Partition for Conveyor- V.5 / 5.75 38.50 sf 2.90 /sf 112
Demo Partitions- Col Llne4 720.00 sf 227 /sf 1,634
Demo Partition for Conveyor- Z / 4.75 16.63 sf 2.90 /sf 48
Demo Exterior Wall at new Coiling Door 96.00 sf 2.90 /sf 278
Demo Partition for Conveyor - V.5 / 6.75 36.00 sf 290 /sf 104
Demo Drywall Partitions at Ticketing 850.00 sf 227 /sf 1,930
Remove Floor Tile 322.00 sf 0.41 /sf 132
Sawcut Floor at new Equip 116.00 If /If Included w/002320
Foundations
•
Sawcut Floor at Mezzanine 2324 If 15.00 /If 349
Remove Concrete Pad at Door 36.00 sf /sf included w/002320
Remove Concrete Floor 211.00 sf /sf included w/002320
Remove Door and Frame 7.00 ea 46.06 /ea 322
Remove 01-1 Door and Frame 2.00 ea 88.62 /ea 177
Remove Window 2.00 ea 60.06 /ea 120
Remove Chain Link Fence 22.00 0 806 /If 133
Remove Bolt -Down Railing 66.00 0 5.05 /If 333
Remove Guardrail at existing Ramp 14.00 If 505 /If 71
Remove Existing Bollards 3.00 ea 132.96 /ea 399 at Generator
Remove Guardrail at Mezzanine 280.00 If 8.85 /If 2,478
Remove Catwalk & Stairs 260.00 sf 8.85 /sf 2,301
Demo Mezzanine Floor 67.07 sf 8.85 /sf 594
Remove Existing Heaters 8.00 ea 53.64 /ea 429
'Roof Penetrations for Mech /Plumbing 4.00 ea 153.64 /ea 615
Mlsc Demo 1.00 Is 3,596.72 its 3,597
Labor Foreman 80.00 hr 36.48 /hr 2,918
Clean -up 40.00 hr
24.32 /hr 973
Clean -up -40.00 hr 24.32 /hr (973)
Haul Trash 4.00 ea 1,125.00 /ea 4,500
SELECTIVE DEMOLITION part of Demolition Scope
/sf 28,407
002315 EXCAVATION & FILL
Excavate for Generator Feeds 39.60 cy /cy Included w/002220
Excavate for Generator Pad 7.37 cy /cy • Included w/002220
Haul & Dispose excess at 39.60 cy /cy • Included
Generator Feeds
Haul & Dispose excess at 7.37 cy /cy Included
Generator Pad
Flowfill at Generator Feed 39.60 cy . /cy Included w/002220
002320 BUILDING EXCAVATION
Excavation at Building 1.00 Is 2,915.00 /Is 2,915 Schofield.
Excavate Footings at BHS 14.07 cy /
- Haul & Dispose 14.07 cy /cy
Backfill & Compact 10.00 cy /
Hand Excavate 8.00 hr 24.32 /hr 195
Hand Compaction 16.00 hr 24.32 /hr 389
BUILDING EXCAVATION /sf 3,499
002740 ASPHALT PAVING
4 "Asphalt Base Course 36.00 sy /sy included w/002220
002750 CONCRETE PAVING
Misc Conc Paving 1.00 Is /Is included
New Concrete Pad at Door 36.00 sf • /sf included
SHAW EAGLE COUNTY AIRPORT TERMINAL Page
IFEWEICEIBEEM
Checked Baggage Inspection System 10/3/2011 4 :39 PM
GMP Estimate - Revised September 28, 2011 SCAT CBIS GMP 11- 09- 27r2.pee
Group Phase Description Takeoff Quantity Total Cost/Unit Total Amount Previous Budget/Notes
SITEWORK /sf 57,565
003000 CONCRETE .
003310 CAST -IN -PLACE CONCRETE
CIP Concrete - Subcontract 1.00 Is 20,325.00 /Is 20,325 RMS Concrete
Pump Concrete 141.90 cy /cy included
Rect. Spread Footings - cy 4.84 cy /cy included
Round Columns - cy 2.09 cy /cy included
Slab On Grade - sf 211.00 sf /sf included
6" Gravel Base @ S.O.G. 7.81 fn /tn included w/002320
6" Gravel Base @ Generator 3.84 to /tn included w/002320
Slab on Metal Deck - sf 1,474.00 sf /sf included
12" Generator Equipment Pad - 7.37 cy /cy included
173 sf
Equipment Pads at BHS - 1,608 sf 98.27 cy 383.94 /cy 37,730 RMS Concrete
Concrete Sealer 3,373.40 sf /sf included
Clean -up 16.00 hr 24.32 /hr 389
Clean -up -16.00 hr 24.32 /hr (389)
Haul Trash 0.50 ea 1,125.00 /ea 563
Haul Trash -0.50 ea 1,125.00 /ea (562)
CAST -IN -PLACE CONCRETE (sf 58,055
003610 GROUTING
Grout Base Plates 5.00 ea 37.73 /ea 189
GROUTING isf 189
CONCRETE /sf 58,244
005000 METALS
005120 STRUCTURAL STEEL
Structural Steel - Subcontract - 1.00 Is 120,941.00 /Is 120,941 Timberwolf Welding
Demolition of Existing Steel 1.00 Is 6,700.00 4s 6,700
Misc Welding at Joist Tails 12.00 hrs s 115.
00 Mrs
1,380
Touch -up Paint at existing Steel 1.00 Is 400.00 /Is 400
Steel Stairs 1.00 ea /ea included
STRUCTURAL STEEL /sf 129,421
005310 METAL DECK
Metal Floor Deck 1,419.00 sf /sf included
005510 MISC. METALS
1 1 /2 " dia. Guardrail at Stairs 43.00 If /If included
Pipe Bollard (Bolt Down) 4.00 ea /ea included
Steel Grating - Stair Tread 81.00 sf /sf included
Grout Bollards and Column Base Plates 11.00 ea 42.51 /ea 468
HSS Frame at OH Coiling Door 1.00 ea /ea included
MISC. METALS (sf 468
METALS /sf 129,889 .
006000 WOOD & PLASTICS
006105 ROUGH CARPENTRY
P.T. In -Wall Blocking 1,878.00 If 3.68 /If 6,911
2x4 Blocking @ Drs/Wndws 113.00 If 3.68 /If 416
Rough Hardware 1.00 Is 125.00 /Is 125
Temp. Handrails & Toeboards 352.00 If 7.30 /If 2,570
Hoisting - Rough Carpentry . 1.00 mo 4,666.67 /mo 4,667
Clean -up 16.00 hr 24.32 /hr 389
Clean -up -16.00 hr 24.32 /hr (389)
Haul Trash 0.50 ea 1,125.00 /ea 563
Haul Trash -0.50 ea 1,125.00 /ea (562)
ROUGH CARPENTRY /sf 14,688
WOOD & PLASTICS /sf 14,688
007000 THERMAUMOISTURE
PROTEC'N
007210 BUILDING INSULATION
•
. .
S EAGLE COUNTY AIRPORT TERMINAL Page
NEENIMMEia
Checked Baggage Inspection System 10/3/2011 4:39 PM
GMP Estimate - Revised September 28, 2011 ECAT CBIS GMP 11- 09- 27r2.pee
Group Phase Description Takeoff Quantity Total Cost/Unit Total Amount Previous Budget/Notes
007210 BUILDING INSULATION
3.5 "RI1 Batt Insulation 6,514.00 sf /sf included w/009250
Patch & Repair Vinyl Insulation at Deck 352.00 0 0.75 /If 264
BUILDING INSULATION /sf 264
007240 EIFS
2" EIFS 40.00 sf 15.00 /sf 600
EIFS /sf 600
007610 SHEET METAL ROOFING
RoofJacks 2.00 ea 150.00 /ea 300
Roof Hoods 2.00 ea 1,500.00 /ea 3,000
SHEET METAL ROOFING /sf 3,300
007620 FLASHING & SHEET METAL •
Wall Flashing 12.00 If • 4.91 /0 59 at OH Coiling Door
FLASHING & SHEET METAL /sf 59
007840 FIRESTOPPING
•
Fire Safing @ Slab Edge n/a /n /a
007920 JOINT SEALANTS
Exterior Sealants 1.00 Is 500.00 Ps 500
Interior Caulking /Sealing 31,726.00 sf 0.10 /sf 3,173
JOINT SEALANTS /sf 3,673
THERMAL/MOISTURE /sf 7,895
PROTEC'N
008000 DOORS & WINDOWS
008005 DOOR BID
Doors, Frames & Hardware 1.00 Is 12,465.00 Ps 12,465 Colorado Doorways
DOOR BID /sf 12,465 Material Only
008110 STEEL DOORS /FRAMES
Re- Install Salvaged Door at Ticketing 1.00 ea 157.06 /ea 157 •
Hollow Mtl Doors - Rated 5.00 Iv 76.03 M 380
Sgl HM Door Frame 5.00 ea 43.02 /ea 215
Dbl HM Door 4.00 Iv 76.03 /Iv 304
Dbl HM Door Frame 2.00 ea 81.03 /ea 162
Unload & Distribute 16.00 ea 22.80 /ea 365
STEEL DOORS /FRAMES /sf 1,583 Installation Only
008330 COILING DOORS/GRILLS
Coiling Overhead Door 96.00 sf 63.94 /sf 6,138 Overhead Door of GJ
COILING DOORS /GRILLS /sf 6,138
008710 DOOR HARDWARE
Hardware Sets 9.00 ea 266.57 /ea 2,399
Unload & Distribute 9.00 ea 6.46 /ea 58
DOOR HARDWARE /sf 2,457 Installation Only •
DOORS & WINDOWS /sf 22,644
009000 FINISHES
009250 GYPSUM WALL BOARD
Drywall - Subcontract 1.00 Is 47,532.00 /Is 47,532 Superior Drywall
Interior Wall - New Walls 6,514.00 sf /sf included
Interior Wall - Infll 139.00 sf /sf included
Gyp Bd Ceiling System 132.00 sf /sf included
Layout 16.00 hr 41.04 /hr 657
Temp Heat for Finishes 17.00 wk 1,403.06 /wk 23,852 Utility consumption charges by Owner
Temp Heat for Finishes -17.00 wk 1,403.06 /wk (23,852) Utility consumption charges by Owner
Patch at wall connections 1.00 Is 1,500.00 Ps 1,500
Touch -up 1.00 Is 500.00 Is - 500
Clean -up 80.00 hr 24.32 fir 1,946
Clean -up -80.00 hr 24.32 /hr (1,946)
Haul Trash 1.00 ea 1,125.00 /ea 1,125
Haul Trash -1.00 ea 1,125.00 /ea (1,125)
GYPSUM WALL BOARD /sf 50,189
•
. .
SHAW EAGLE COUNTY AIRPORT TERMINAL Page 5
EiTUNECIEMEIM
Checked Baggage Inspection System 10/3/2011 4 :39 PM
GMP Estimate - Revised September 28, 2011 ECAT CBIS GMP 11-09-2 7r2.pee
Group Phase Description Takeoff Quantity Total Cost/Unit Total Amount Previous Budget/Notes
009510 ACOUSTICAL CEILINGS
Acoustic Ceiling .Subcontract 1.00 Is 1,611.00 /Is 1,611 Superior Drywall
New Acoustic Ceiling 279.00 sf /sf included
Remove & Reinstall Existing Acoustic 309.75 sf 1.50 /sf 465
Ceiling
ACOUSTICAL CEILINGS Isf 2,076
•
009650 RESILIENT FLOORING
Resilient Flooring - Subcontract 1.00 Is 1,328.00 /Is 1,328 Abbey Carpet
12x12 VCT Flooring 338.00 sf /sf included
4" Rubber Base 967.00 If 1.25 /If 1,209
Floor Prep 338.00 sf 0.35 /sf 118
Finished Floor Protec'n - Resilient 338.00 sf 022 /sf 75
RESILIENT FLOORING /sf 2,730
009910 PAINTING
Painting - Subcontract 1.00 Is 19,999.00 Is 19,999 Swedish Painting
Paint - Int. & Ext. 13,160.00 sf /sf included
Paint Existing 5,671.00 sf /sf included
Repair Finishes 1.00 Is 750.00 As 750
Paint Doors/Windows 9.00 ea /ea included
Haul Trash 0.50 ea 1,125.00 /ea 563
Haul Trash -0.50 ea 1,125.00 /ea (562)
PAINTING isf 20,749
FINISHES Isf 75,743
010000 SPECIALTIES
010260 WALL & CORNER GUARDS
3.5 "x3.5" Stain.Steel Comer Guards 1,440.00 If 18.44 /If 26,548
•
WALL & CORNER GUARDS Isf 26,548
010520 FIRE PROTECTION
Fire Ext. & Cabinet (Surface Mtd) 6.00 ea 301.03 /ea 1,806
FIRE PROTECTION isf 1,806
SPECIALTIES Isf 28,355
014000 CONVEYING SYSTEMS
014550 CONVEYORS
Baggage Handling System 1.00 Is 3,432,902.00 /Is 3,432,902 The Horsley Company
CONVEYORS
/sf 3,432,902
014610 HOISTS
4000 lb Hoists 1.00 ea 14,187.00 /ea 14,187 American Equipment
HOISTS Isf 14,187
CONVEYING SYSTEMS Isf 3,447,089
015000 MECHANICAL
015100 PLUMBING
Plumbing - Subcontract Intl /incl w/015510 HVAC
015300 FIRE PROTECTION
Interior Sprinkler System 31,726.00 sf 0.24 /sf 7,645 Assurance Fire Systems
FIRE PROTECTION isf 7,645
015510 HVAC
HVAC - Subcontractcontract 1.00 Is 162,077.00 /ls 162,077 Design Mechanical
HVAC Isf 162,077
MECHANICAL Isf 169,722
016000 ELECTRICAL
016010 ELECTRICAL
Electrical - Subcontract 1.00 Is 441,525.00 /Is 441,525 New Electric
SHAW EAGLE COUNTY AIRPORT TERMINAL Page 6
agEMEMILIM
Checked Baggage Inspection System 10/3/2011 4:39 PM
GMP Estimate - Revised September 28, 2011 SCAT CBIS GMP 11- 09- 27r2.pee
Group Phase Description Takeoff Quantity Total Cost/Unit Total Amount Previous Budget/Notes
016010 ELECTRICAL
Temp Generator for Change 1.00 wk /wk Included
Over
- Secondary Feeds from MDC to BHS 1.00 Is 30,000.00 /Is 30,000
ELECTRICAL Isf 471,525
016740 COMMUNICATIONS & SECURITY
Phone /Data Systems - Prew/re nic /nic
only
Fire Alarm 31,726.00 sf 0.73 /sf 23,160 New Electric
Telecomm 1,00 Is 33,058.00 /Is 33,058 New Electric
COMMUNICATIONS & SECURITY /sf 56,218
ELECTRICAL /sf 527,743
019000 INSURANCE /PERMITS /MISC
019100 INSURANCE
General Liability Insurance Is /Is See back page
Builders Risk Insurance Is /Is By Owner
019400 SERVICES
Preconstruction Services Is /Is Included with Executive
Summary
•
•
•
6 e
sHAw EAGLE COUNTY AIRPORT TERMINAL Page 7
EMEIGURIEMEE
Checked Baggage Inspection System 10/3/2011 4:39 PM
GMP Estimate - Revised September 28, 2011 ECAT CB/S GMP 11- 09- 27r2.pee
•
Estimate Totals
Description Amount Totals Rate
Labor 39,657
Material 41,052
Subcontract 4,458 868
4,539,577 4,539,577
Material Sales Tax - Exempt
4,539,577
GC's by % of COW per RFP 171,596 1780
CM /GC Fee by % of COW per RFP 233,674 4.960
405,270 4,944,847
Contingency 98,897 2.000
P &P Bond 49,287 0.960
General Liability Insurance 41,073 0.800
Total 5,134,104
b •
sHAw EXHIBIT E - CONSTRUCTION SCHEDULE
C O N S T R U C T I O N
ID 1 Task Name Duration Start ' Finish Prede I % !Resource
t
i Comple Names ,
..
1
EGE - CBIS - Construction Schedule 1 day? Tue 8/16/11 Tue 8/16/11 p%
2
3 I V ADMINISTRATIVE MILESTONES 21 days Thu 8/11/11 Thu 9/8/11 100%
" Contractor Pre - Construction Agreement 10 days Thu 8/11/11 Wed 8/24/11 100%
5 I v" Submit for permit 5 days Fri 9/2/11 Thu 9/8/11 100%
6 I
7 ! .," UTILITY SERVICE AGREEMENTS 1 day Thu 9/1/11 Thu 9/1/11 100%
8 I /' Electrical Service Agreement 1 day Thu 9/1/11 Thu 9/1/11 100% OWNER
9
10 i v /• DESIGN /PRECONSTRUCTION MILESTONES 16 days Wed 8/3/11 Wed 8/24/11 100%
...........
11 i . 70% Design Documents 16 days Wed 8/3/11 Wed 8/24/11 100%
12 ; ./' 70% DD plans complete 0 days Wed 8/3/11 Wed 8/3/11 100% BNP
.._..........
13 i , 70% DD Estimate Due 1 day Wed 8/17/11 Wed 8/17/11 12 100% SHAW
14 1.v" 70% DD Constructability Comments Due 1 day Wed 8/17/11 Wed 8/17/11 100% SHAW
15 I Systems analysis Complete 1 day Wed 8/24/11 Wed 8/24/11 100% SHAW
16
I .7 Identify Long Lead Procurement 1 day Wed 8/17/11 Wed 8/17/11 100% SHAW
17
18 I 100% DESIGN DRAWINGS 30 days Thu 9/1/11 Wed 10/12/11 94%
19 ; + 100% Plans complete 1 day Thu 9/1/11 Thu 9/1/11 12 100% BNP
, 20 I ,r' Prepare Bid Package 1 day Tue 9/6/11 Tue 9/6/11 19 100% SHAW
21 1.,,." Sub Bids Due 10 days Wed 9/7/11 Tue 9/20/11 20 100% SHAW
22 I I V ' Shaw review and assemble GMP 3 days Fri 9/23/11 Tue 9/27/11 21 100% SHAW
23 ' Present GMP to Owner °
1 day Wed 9/28/11 Wed 9/28/11 22 100% SHAW
24 1 rig Notice to Proceed 1 day. Wed 10/12/11 Wed 10/12/11 0% OWNER
25
26 I CONSTRUCTION 263 days Tue 9/6/11 Thu 9/6/12 0%
..................
27 c'' Obtain Building permit °
8
I � 5 days Tue 9/6/11 Mon 9/12/11 0 /o OWNER
8
2
29 Site work 7 days Mon 10/17/11 Tue 10/25/11 0%
30 � Underground electrical 7 days Mon 10/17/11 Tue 10/25/11 0%
31 .
IA
1 Sawcut & Removal 2 days Mon 10/17/11 Tue 10/18/11 0% SHAW
32 � Install conduit 2 days Wed 10/19/11 Thu 10/20/11 31 0% SHAW
i
33 Backfill 2 days Fri 10/21/11 Mon 10/24/11 - 32 0% SHAW
34 Patch 1 day Tue 10/25/11 Tue 10/25/11 33 0% SHAW
35
36 Mezzanine Construction 135 days Mon 10/17/11 Fri 4/20/12 0%
37 Demolition 8 days Mon 10/17/11 Wed 10/26/11 0%
33 emove Steel
I � Remove 2 days Mon 10/17/11 Tue 10/18/11 24 0% SHAW
'8 9 Concrete Removal 2 days Wed 10/19/11 Thu 10/20/11 38 0% SHAW
40 I Seletive wall demolition 2 days Fri 10/21/11 Mon 10/24/11 39 0% SHAW
41 I Wall opening demolition 2 days Tue 10/25/11 Wed. 10/26/11 40 0% SHAW
42
43 Concrete 10 days Fri 10/21/11 Thu 11/3/11 0%
44 Place concrete for ftgs 2 days Fri 10/21/11 Mon 10/24/11 39 0% SHAW
Page 1
i
a s
sHAw EXHIBIT E - CONSTRUCTION SCHEDULE
C0 NS T R U C T 1 0 N
ID I Task Name Duration ' Start Finish Predf ; % Resource
■
Complete !Names
45 I Place concrete at mezzanine 2 days Wed 11/2/11 Thu 11/3/11 50 0% SHAW
46
I
4 7 Steel 129 days Tue 10/25/11 Fri 4/20/12 0%
48 Install columns 2 days Tue 10/25/11 Wed 10/26/11 44 0% SHAW
,
49 � Install beams 3 days Thu 10/27/11 Mon 10/31/11 48 0% SHAW
....................
50 Install decking 1 day Tue 11/1/11 Tue 11/1/11 49 0% SHAW
51 Install stairs
5 days Mon 4/16/12 Fri 4/20/12 0% SHAW
52 __
53 J Roof work 4 days Fri 11/4/11 Wed 11/9/11 0%
54 Cut in roof openings 2 days Fri 11/4/11 Mon 11/7/11 45 0% SHAW
.. .......
55 I Flash in roof (temp cover hole) 2 days Tue 11/8/11 Wed 11/9/11 54 0% SHAW
56 .
57 Framing 4 days Fri 11/4/11 Wed 11/9/11 0%
58 Steel framing at perimeter of Mezzanin( 3 days Fri 11/4/11 Tue 11/8/11 45 0% SHAW
.....................
59 i Frame openings 1 day Wed 11/9/11 Wed 11/9/11 58 0% SHAW
60
61 Drywall (exterior mezz) 14 days Wed 11/9/11 Mon 11/28/11 0%
6 2 Hang drywall 4 days Wed 11/9/11 Mon 11/14/11 58 0% SHAW
63 Tape and finish 5 days Tue 11/15/11 Mon 11/21/11 62 0% SHAW
64 Prime 1 day Tue 11/22/11 Tue 11/22/11 63 •0% SHAW
65 Texture 2 days Wed 11/23/11 Thu 11/24/11 64 0% SHAW
66 Paint 2 days Fri 11/25/11 Mon 11/28/11 65 0% SHAW
67
68 i.�x.. Mezzanine Enclosed (off lower floor) 1 day Thu 12/15/11 Thu 12/15/11 0%
69
70 Install OH Door 2 days Tue 11/29/11 Wed 11/30/11 66 0% SHAW
........_.._
71 . Install Crane 1 day Thu 12/1/11 Thu 12/1/11 70 0% SHAW
72
.........................
73 Rough In Work 25 days Thu 12/1/11 Wed 1/4/12 0%
74. Rough In Electrical 15 days Thu 12/1/11 Wed 12/21/11 70 0% SHAW
75 Rough In Mechanical 10 days Thu 12/22/11 Wed 1/4/12 74 0% SHAW
76 Insulate 2 days Thu 1/5/12 Fri 1/6/12 75 ' 0% SHAW
77 Drywall Interior 7 days Mon 1/9/12 Tue 1/17/12 76 0% SHAW
...............
78
79 CBIS Equipment Install 152 days Wed 1/18/12 Thu 8/16/12 0%
80 n Phase 1 25 days Wed 1/18/12 Tue 2/21/12 77 0% SHAW
81 n Phase 2
14 days Mon 4/16/12 Thu 5/3/12 80 0% SHAW
.......................
82 1 Phase 3 15 days Fri 5/4/12 Thu 5/24/12 81 0% SHAW
83 Phase 4 7 days Fri 5/25/12 Mon 6/4/12 82 0% SHAW
84 Phase 5 20 days Tue 6/5/12 Mon 7/2/12 83 0% SHAW
85 1 Phase 6 16 days Tue 7/3/12 Tue 7/24/12 84 0% SHAW
........86 I Phase 7
11 days Wed 7/25/12 Wed 8/8/12 85 0% SHAW
87 I Delivery of EDS 0 days Wed 8/8/12 Wed 8/8/12 86 0% SHAW
88 I SAT of EDS 6 days Thu 8/9/12 Thu 8/16/12 87 0% SHAW
Page 2
v e
sHAw EXHIBIT E - CONSTRUCTION SCHEDULE
CONSTRUCTION
ID j Task Name Duration Start Finish Prede i % Resource
{
.. .. Complete Names
89
-�-�
90 n Testing and Commissioning Phase 108 days Tue 4/10/12 Thu 9/6/12 0% SHAW
91
92 1 Project Complete 1 day Thu 9/6/12 Thu 9/6/12 0% SHAW
• I
i
Page 3