HomeMy WebLinkAboutC14-306 FCI Constructors First Addendum FIRST ADDENDUM APPROVING THE GUARANTEED MAXIMUM PRICE,
BUDGET,AND CONSTRUCTION SCHEDULE FOR THE EAGLE COUNTY
REGIONAL AIRPORT SNOW REMOVAL EQUIPMENT FACILITY(SRE)
THIS First Addendum is made and entered into this Of). day of August, 2014 between the
Board of County Commissioners, County of Eagle, State of Colorado, (hereinafter referred to as
"County") and FCI Constructors, Inc. (hereinafter referred to as "FCI"). Together all shall be
referred to as"Parties."
WHEREAS, County and FCI entered into an Agreement dated December 17, 2013 ("Original
Agreement") for Preconstruction and Construction of the Eagle County Regional Airport Snow
Removal Equipment Facility;and
WHEREAS, the Original Agreement called for the provision by FCI of a proposed Guaranteed
Maximum Price (hereinafter referred to as "GMP"),detailed budget and construction schedule to
the County; and
WHEREAS,the GMP,budget and construction schedule must be approved by the Eagle County
Project Manager and the County before FCI may be authorized to commence construction
services;and
WHEREAS,FCI has presented to the County a GMP,detailed budget and construction schedule
attached hereto;and
WHERAS, the Eagle County Project Manager and the County wish to approve the GMP,
detailed budget and construction schedule as conditioned herein and authorize the issuance of a
Notice to Proceed with Construction Services.
In consideration of the terms and conditions of the Original Agreement, the sufficiency of which
is hereby acknowledged, County and FCI hereby agree to the following:
THAT, the GMP, detailed budget and construction schedules attached hereto are hereby
accepted by the undersigned and incorporated into the Contract Documents as defined in
Article 2.2(A) of the Original Agreement.
THAT,Article 12 of the Original Agreement shall be modified with the addition of the
following Contract Documents:
12.6 Construction Set drawings dated July 14, 2014;Project Manual specifications
dated July 14,2014;Bid Clarifications provided by Menendez Architects on July 21,2014
and July 22,2014.
12.7 First Addendum Approving the Guaranteed Maximum Price, Budget,and
Construction Schedule, including attached exhibits or the Eagle County Regional Airport
Snow Removal Equipment Facility dated August ,2014.
THAT,the Original Agreement, General Conditions, and the Drawings and Specifications
shall control if there exists any conflicts with those documents and this First Addendum,
including any attachments attached hereto, unless otherwise notified in writing by the Eagle
County Project Manager.
THAT,FCI is hereby designated as the Construction Manager/General Contractor for the
construction of the Eagle County Regional Airport Snow Removal Equipment Facility.
THAT,the Eagle County Project Manager is authorized to issue a Notice to Proceed to FCI
to perform those Construction Services set forth in the Original Agreement.
County and FCI agree that, except as expressly altered, modified and changed in this First
Addendum, all terms and provisions of the Original Agreement shall remain in full force and
effect,and are hereby ratified and confirmed in all respects as of the date hereof.
This First Addendum shall be binding on the parties hereto,their heirs,executors, successors,
and assigns.
IN WITNESS WHEREOF, the parties have executed this First Addendum on the day and year
first above written.
_ E COUNTY:
c"
ATTEST: or,01�►, • •F EAGLE, STATE OF COLORADO
a 0 `' I'ugh its BOARD OF COUNTY
•. *NERS
te
Teak Simonton — — I� , -Ryan hairman- I -dTtL„
Clerk to the Board of 514- 1---1S14-100—
County Commissioners
FCI:
Name: S`n.e.K M t40AS
Title: U; Pras∎6 e.^.4'
G:iBRYANImisc\F'CI ADDENDUM.DOC
2
1
III
PROJECT:
EAGLE COUNTY REGIONAL AIRPORT - SNOW REMOVAL EQUIPMENT
BUILDING (SRE)
GYPSUM, COLORADO
PREPARED FOR
EAGLE COUNTY, COLORADO
sat*
EAGLE COUNTY
FINAL DESIGN GMP-REVISION#1
7/24/2014/UPDATED 7/31/2014
PREPARED BY:FCI Constructors,Inc.
,
FCI Constructors, Inc.
Date: 7/24/2014/UPDATED 7/31/2014
Project:
EAGLE COUNTY REGIONAL AIRPORT-SNOW CONCEPT DESIGN ESTIMATE-
REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP NOV 26,2013 DIFFERENCE
GYPSUM,COLORADO NEW CONSTR. 26,050 NEW CONSTR. 18,777
FINAL DESIGN GMP-REVISION#1 RENOVATION N/A RENOVATION N/A
DESCRIPTION TOTAL SF 26,050 TOTAL SF 18,777
TOTAL COST COST/SF TOTAL COST COST/SF NOTES
010000 GENERAL CONDITIONS $ 162,335 $ 623 $ 162,335 $ 8.65 $ -
310000 SITE WORK $ 574,084 $ 22.04 $ 311,934 $ 16.61 $ 262,150
020000 SITEWORK-BUILDING $ 20,157 $ 0.77 $ 215,689 $ 11.49 $ (195,532)
030000 CONCRETE $ 729,552 $ 28.01 $ 694,515 $ 36.99 $ 35,037
040000 MASONRY $ 123,027 $ 4.72 $ 140,958 $ 7.51 $ (17,931)
050000 METALS $ 64,556 $ 2.48 $ 207,115 $ 11.03 $ (142,559)
060000 WOOD&PLASTICS $ 56,206 $ 2.16 $ 49,417 $ 2.63 $ 6,789
070000 THERMAL&MOISTURE PROTECTION $ 226,434 $ 8.69 $ 115,935 $ 6.17 $ 110,499
140 026 5.38 288 108 15.34 148 082
080000 DOORS&WINDOWS $ $ $ $ $ ( )
090000 FINISHES $ 396,410 $ 15.22 $ 189,559 $ 10.10 $ 206,851
100000 SPECIALTIES $ 14,363 $ 0.55 $ 15,552 $ 0.83 $ (1,189)
110000 EQUIPMENT $ 660 $ 0.03 $ 56,340 $ 3.00 $ (55,680)
120000 FURNISHINGS $ - $ - $ 6,275 $ 0.33 $ (6,275)
130000 SPECIAL CONSTRUCTION $ 844,336 $ 32.41 $ 722,829 $ 38.50 $ 121,507
140000 CONVEYING SYSTEMS $ - $ - $ - $ -
210000 FIRE SUPPRESSION $ 68,900 $ 2.64 $ 77,676 $ 4.14 $ (8,776)
220000 PLUMBING $ 235,623 $ 9.05 $ 255,942 $ 13.63 $ (20,319)
230000 HVAC $ 418,882 $ 16.08 $ 329,470 $ 17.55 $ 89,412
260000 ELECTRICAL $ 326,794 $ 12.54 $ 366,007 $ 19.49 $ (39,213)
270000 LV SPECIAL SYSTEMS $ 20,000 $ 0.77 $ 33,332 $ 1.78 $ (13,332)
SUBTOTAL-DIRECT COST $ 4,422,344 $ 169.76 $ 4,238,988 $ 225.75 $ 183,356
PRECONSTRUCTION FEE $ 17,500 $ 0.67 $ 17,500 $ 0.93 $ - 0.00%
BID/ESTIMATING CONTINGENCY $ - $ - $ 84,780 $ 4.52 $ (84,780)0.00%
GMP/CONSTRUCTION CONTINGENCY $ 88,447 $ 3.40 $ 127,170 $ 6.77 $ (38,723)2.00%
BUILDERS RISK INSURANCE $ 5,719 $ 0.22 $ 5,702 $ 0.30 $ 17
GENERAL LIABILITY INSURANCE $ 19,064 $ 0.73 $ 19,008 $ 1.01 $ 56 0.40%
PROPERTY SURVEY $ - $ - $ - $ - $ - BY OWNER
SOILS INVESTIGATION/GEOTECHNICAL ENGINEERING $ - $ - $ - $ - $ - BY OWNER
MATERIALS TESTING/INSPECTION $ - $ - $ - $ - $ - BY OWNER
PLANNING APPLICATIONS/PERMIT/PLAN REVIEW FEES $ - $ - $ - $ - $ - BY OWNER
BUILDING PERMIT $ - $ - $ - $ - $ - BY OWNER
ARCHITECTURAL DESIGN&ENGINEERING(C/S/M&E) $ - $ - $ - $ - $ - BY OWNER
FCI PAYMENT/PERFORMANCE BONDS $ 30,129 $ 1.16 $ 30,042 $ 1.60 $ 87 1-YEAR WARRANTY
FCI CONSTRUCTION PHASE FEE $ 183,328 $ 7.04 $ 180,928 $ 9.64 $ 2,400 4.00%
FCI FEE HOLIDAY ON 1ST$100k N/A $ - $ (4,000) $ (0.21) $ (4,000)
FCI CONSTRUCTION PHASE FEE-OVER$4MM BUDGET N/A $ - $ - $ - $ -
TOTAL ESTIMATED COST $ 4,766,531 $ 182.98 $ 4,700,118 $ 250.31 $ 58,413
CONCEPTUAL BUDGET/SCOPE ADJUSTMENTS
ACCEPTED VALUE ANALYSIS-AS OF JAN 21,2014 $ (742,196) $ (39.53)
ADDED SCOPE-NORTH APPARATUS BAYS-ROOF STRUCTURE BACK IN BASE BID $ 158,277 $ 8.43
ADDED SCOPE-NORTH APPARATUS BAYS-2 ADDITIONAL BAYS $ 119,304 $ 6.35
ADDED SCOPE-NORTH APPARATUS BAYS-ENCLOSE&CONDITIONED SPACE $ 418,670 $ 22.30
(TOTAL ESTIMATED CONSTRUCTION COST $ 4,766,531 I$ 182.98 $ 4,654,173 $ 178.66 $ 112,358 BASE BID SCOPE I
VALUE ANALYSIS OPTION-FCI SELF-PERFORM CONCRETE I$ (91,668)1 IN/A I I I
TOTAL ESTIMATED CONSTRUCTION COST I$ 4,674,863 1 I$ 4,654,173 1 I$ 20,690 1
Confidential-FCI Constructors,Inc. 2
FCI Constructors, Inc.
Date: 7/24/2014/UPDATED 7/31/2014
Project:
EAGLE COUNTY REGIONAL AIRPORT-SNOW
REMOVAL EQUIPMENT BUILDING(SRE)
GYPSUM,COLORADO
FINAL DESIGN GMP-REVISION#1
BID ALTERNATES
ALTERNATE#1-DELETE RADON GAS VENTING SYSTEM-PIPING&FANS. DEDUCT $ (7,500)
ALTERNATE#2-ADD STORAGE PLATFORMS IN EQUIPMENT STORAGE BAYS. ADD $ 53,757
ALTERNATE#3-ADD WINDOW COVERINGS. ADD $ 4,067
ALTERNATE#4-REVISE STOREFRONT SYSTEM FROM 6"TO 4.5"FRAMING. DEDUCT $ (1,400)
ALTERNATE#5-REVISE DRY PIPE FP SYSTEM TO WET PIPE SYSTEM. DEDUCT $ (9,300)
ALTERNATE#6-ADD NITROGEN GENERATOR SYSTEM TO DRY PIPE FP SYSTEM. ADD $ 16,092
1
Confidential-FCI Constructors,Inc. 3
' FCI Cost Worksheet 7/24/2014/UPDATED 7/31/
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 28,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
310000 SITE WORK
312100 SITE PREPARATION EWING TRUCKING
EROSION CONTROL LOGS LF 946.00 $ 3.90 IF $ 378,389
TEMP CONSTRUCTION FENCING LF 600.00 $ 2.50 LF INCLUDED
EROSION CONTROL BLANKETS SY 813.22 $ 3.50 SY INCLUDED
HYDROSEED/HYDRO MULCH SY 5,699.78 $ 1.15 SY INCLUDED
SOIL/EROSION CONTROL-MAINT. LS 1.00 $ 800.00 LS $ 800
STREET CLEANING-HAUL ROAD LS 1.00 $ 2,000.00 LS $ 2,000
SUBTOTAL-SITE PREPARATION S 381,189
312160 SITE DEMOLITION EWING TRUCKING
REMOVE FULL DEPTH ASPHALT PAVEMENT SF 450.00 $ 1.00 SF INCLUDED
REMOVE EXISTING ASPHALT MILLINGS SF 17,059.00 $ 0.25 SF INCLUDED
SAW CUTTING/REMOVE PARTIAL DEPTH
ASPHALT PAVEMENT SF 1.00 $ 1.00 SF $ 1,500
REMOVE PIPE BOLLARDS EA 22.00 $ 23.00 EA INCLUDED
REMOVE LIGHT POLE&CONCRETE BASE EA 1.00 $ 200.00 EA INCLUDED
PROTECTION OF EXISTING PAVEMENT LS 1.00 $ 1,200.00 LS $ 1,200
PROTECTION OF EXISTING UTILTIES LS 1.00 $ 1,500.00 LS $ 1,500
SUBTOTAL-SITE DEMOLITION $ 4,200
312200 MASS EXCAVATION&SITE GRADING EWING TRUCKING $ -
INITIAL SURVEY LS 1.00 $ - LS $ 8,000
MOBILIZATION LS 1.00 $ - LS INCLUDED
CLEAR/GRUB SITE LS 1.00 $ 2,175.00 LS INCLUDED
CUT EXISTING TO PROPOSED
MASS EXCAVATION-SITE CUT/FILL GRADES CY 171.00 $ 6.00 CY INCLUDED
MASS EXCAVATION-SITE CUT/FILL-PLACE& IMPORT FILL FROM AIRPORT
COMPACT STOCKPILE CY 7,927.20 $ 12.85 CY INCLUDED
MASS EXCAVATION-REMOVE UNSUITABLE AT
BUILDING PAD BUILDING PAD CY 2,666.67 $ 6.00 CY INCLUDED
DISPOSE UNSUITABLE MATERIAL BUILDING PAD CY 2,666.67 $ 8.26 CY $ 12,600
FORM BUILDING PAD-FROM AIRPORT
STOCKPILE BUILDING PAD CY 5,333.33 $ 12.20 CY INCLUDED
SCARIFY&RECOMPACT-SLAB ON GRADE
SUB GRADE-12" PREPARE BUILDING SUBGRADE SY 2,424.89 $ 1.80 SY INCLUDED
SCARIFY&RECOMPACT-SLAB ON GRADE
SUB GRADE-12" PREPARE PAVEMENT SUBGRADES SY 1,723.33 $ 1.80 SY INCLUDED
SCARIFY&RECOMPACT-BUILDING PAD SUB PRIOR TO STRUCTURAL FILL
SOILS-24" PLACEMENT LS 1.00 $ - LS $ 3,800
ROUGH GRADE SITE-+/-.10 FT SF 115,400.00 $ 0.11 SF INCLUDED
GEOSTABILIZATION FABRIC-MIRAFI CONCRETE PAVEMENTS SY 408.22 $ 2.45 SY INCLUDED
GEOSTABILIZATIQN FABRIC-MIRAFI ASPHALT PAVEMENT SY 1,408.00 $ 2.45 SY $ 3,450
RE-SPREAD TOPSOIL FROM ON SITE
STOCKPILE LS 1.00 $ 2,500.00 LS INCLUDED
POT HOLING FOR UTILITIES LS 1.00 $ 2,000.00 LS $ 2,000
LAYOUT HRS 24.00 $ 54.00 HRS $ 1,298
SUBTOTAL-MASS EXCAVATION&GRADING $ 30,946
312610 ASPHALT PAVING ELAM CONSTRUCTION
ASPHALTIC CONCRETE PAVING-ON SITE
PARKING 6'TH PAVEMENT TN 403.20 $ 128.00 TN $ 75,861
ASPHALTIC CONCRETE PAVING-ON SITE
PARKING-BUTT JOINT OVERLAY 2'TH PAVEMENT TN 9.02 $ 140.00 TN INCLUDED
FINE GRADE SUBGRADE SY 1,280.00 $ 1.65 SY INCLUDED
SOIL STERILANT 1 APPLICATIONS-SUBGRADE SY 1,280.00 $ 0.63 SY $ 800
MATERIAL ESCALATION LS 1.00 $ - LS $ 3,500
SUBTOTAL-ASPHALT PAVING $ 80,161
312616 PAVEMENT BASE MATERIAL EWING TRUCKING
CONCRETE PAVEMENT BASE COURSE-CLASS
6 ROAD BASE-6"THICK SNOW MELT APRONS CY 37.78 $ 51.20 CY INCLUDED
CONCRETE PAVEMENT BASE COURSE-CLASS
6 ROAD BASE-6"THICK EXTERIOR PAVEMENT CY 38.13 $ 51.20 CY INCLUDED
31000 SITEWORK FCI Constructors,Inc.Confidential Page 4
FCI Cost Worksheet 7/24/2014/UPDATED 7/31/
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
CONCRETE SIDEWALK BASE COURSE-CLASS
6 ROAD BASE-6"THICK PEDESTRIAN WALKS CY 17.72 $ 51.20 CY INCLUDED
ASPHALT PAVEMENT BASE COURSE-CLASS 6
ROAD BASE-6"THICK CY 256.00 $ 51.20 CY INCLUDED
SUBTOTAL-PAVEMENT BASE MATERIAL $
31000 SITEWORK FCI Constructors,Inc.Confidential Page 5
•
FCI Cost Worksheet 7/24/2014/UPDATED 7/31/
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
310000 SITE WORK
312650 STORM SEWER EWING TRUCKING
STORM SEWER PIPING-12"RCP LF 210.00 $ 58.80 LF INCLUDED
EXTERIOR TRENCH DRAINS LF 90.00 $ 110.00 LF $ 9,900
CONCRETE HEADWALL EA 1.00 $ 3,500.00 EA $ 3,500
STORM CATCH INLET STRUCTURE EA 1.00 $ 3,248.00 EA INCLUDED
STORM SEWER MANHOLES N/A-EXCLUDED EA - $ 3,848.00 EA 8 -
RIP RAP-24"THICK CY 2.00 $ 71.00 CY INCLUDED
SUBTOTAL-STORM SEWER $ 13,400
312660 SANITARY SEWER EWING TRUCKING
SANITARY SEWER-4" LF 40.00 $ 51.10 LF INCLUDED
SEWER TAP EA 1.00 $ 1,650.00 EA INCLUDED
SAND/OIL SEPERATOR W/PLUMBING EA - $ 7,948.00 EA $ -
SAN SEWER MANHOLES EA 1.00 $ 3,846.00 EA INCLUDED
SUBTOTAL-SANITARY SEWER $ -
312666 WATER SERVICE EWING TRUCKING
DOMESTIC/FIRE WATER LINE-6" LF 704.00 $ 55.00 LF INCLUDED
DOMESTIC WATER LINE-6" LF 37.00 $ 55.00 LF INCLUDED
WATER METER&VAULT EA 1.00 $ 11,300.00 EA $ 11,300
INTO BUILDING-1ST FLANGE
FIRE SERVICE ENTRY ABOVE FLOOR EA 1.00 $ 2,850.00 EA $ 2,850
FIRE HYDRANTS EA 2.00 $ 3,821.00 EA INCLUDED
SUBTOTAL-WATER SERVICE $ 14,160
9126685 DRY UTILITY WORK
TRENCH&BACKFILL-NAT GAS, LS 1.00 $ 9,000.00 LS $ 9,000
SUBTOTAL-DRY UTILITY WORK $ 9,000
312830 FENCING AND GATES TAYLOR FENCE
REMOVE C-L FENCING LF 197.00 $ 2.00 LF $ 25,288
REMOVE AUTO OPERATED FENCE GATE EA 1.00 $ 500.00 EA INCLUDED
CHAIN-LINK FENCING-7O'HG.'LV N"^^'ZEO SITE PERIMETER LF 110.00 $ 32.00 LF INCLUDED
CHAIN-LINK FENCE GATES-.7g=64614 X 25'W MOTOR OPERATED EA 1.00 $ 9,080.00 EA INCLUDED
GATE OPERATORS/PROXIMITY READERS RELOCATED EA 1.00 $ 1,028.00 EA INCLUDED
TEMPORARY SECURITY FENCE-
CHAIN-LINK FENCING-72"H-GALVANIZED INSTALL&TAKEDOWN IF 630.00 $ 25.00 LF $ 15,750
SUBTOTAL-FENCING&GATES $ 41,038
312876 MISCELLANEOUS SITE IMPROVEMENTS
BIKE RACKS WA-EXCLUDED EA - $ - EA $ -
BENCHES-6'LONG-FURNISH&DEL N/A-EXCLUDED EA - $ - EA $ -
TRASH RECEPTACLES-FURN&DEL N/A-EXCLUDED EA - $ - EA $ -
SITE FURNITURE-BENCHES N/A-EXCLUDED EA - $ 140.00 EA $ •
SITE FURNITURE-TRASH RECEPTACLES N/A-EXCLUDED EA - $ 70.00 EA $ -
SITE SIGNS-POST AND PANEL N/A-EXCLUDED EA - $ 175.00 EA $ -
SITE FURNITURE-TABLES W/CHAIRS N/A-EXCLUDED EA - $ 1540.00 EA $ -
SITE MONUMENT SIGN N/A-EXCLUDED EA - $ 12,000.00 EA $ -
SUBTOTAL-MISC.SITE IMPROVEMENTS $ -
312900 LANDSCAPING&IRRIGATION
LANDSCAPING
EXCLUDED SF - $ 5,500.00 SF $ -
SUBTOTAL-LANDSCAPING&IRRIGATION $ -
31000 SITEWORK FCI Constructors,Inc.Confidential Page 6
FCI Cost Worksheet 7/24/2014/UPDATED 7/31/
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
310000 SITE WORK-TOTALS $ 574,084
31000 SITEWORK FCI Constructors,Inc.Confidential Page 7
•
FCI Cost Worksheet 7/24/2014/UPDATED 7/:
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
020000 SITE WORK(BUILDING)
022200 EXCAV.&BACKFILL&COMPACT EW/NG TRUCKING
PLACE/COMPACT DRAINAGE FILL UNDER
SLAB-6" BUILDING SLABS CY 484.98 $ 49.00 CY INCLUDED
PLACE/COMPACT DRAINAGE FILL TO CRAWL
SPACE-4" CRAWL SPACE CY 52.70 $ 49.00 CY INCLUDED
FINE GRADE SUBQRADE BUILDING SLABS SF 21,824.00 $ 0.62 SF INCLUDED
15 MIL VAPOR BARRIER N/A SF 24,006.40 $ 0.37 SF $ -
SCARIFY&RECOMPACT-SUB GRADE-12" BUILDING SLABS SY 2,424.89 $ 1.95 SY INCLUDED
PLACE/COMPACT DRAINAGE FILL TO CRAWL
SPACE-4" CRAWL SPACE CY 52.70 $ 49.00 CY $ 2,582
EXCAVATE FOUNDATIONS-MACHINE OVER-EX BUILDING FNDS CY 1,470.00 $ 8.50 CY INCLUDED
BACKFILL FOUNDATIONS-IMPORT MATL N/A CY - $ 51.20 CY $ -
BACKFILL FOUNDATIONS-NATIVE MAT'L FROM ON SITE STOCKPILE CY 1,470.00 $ 14.20 CY INCLUDED
DISPOSE EXCESS MATERIAL OVER-EX BUILDING FNDS CY - $ 10.26 CY $ -
EXCAVATE FOUNDATIONS-MACHINE CRAWL SPACE CY 760.00 $ 8.50 CY INCLUDED
DISPOSE EXCESS MATERIAL CRAWL SPACE CY 760.00 $ 10.26 CY INCLUDED
LAYOUT/COORDINATION-FDN EX/BF HRS 80.00 $ 54.00 HRS $ 4,320
MEMBRANE LINER-CRAWL SPACE FLOOR&
WALLS-10 MIL POLYOLEFIN RADON GAS BARRIER SF 5,405.40 $ 1.43 SF $ 7,730
TOTAL-EXCAVATION,BACKFILL&COMPACT $ 14,632
026150 FOUNDATION DRAINAGE SYSTEM EWING TRUCKING
PERIMETER FOUNDATION DRAINS-4"DIA LF 350.00 $ 15.25 LF INCLUDED
PERIMETER FOUNDATION DRAINS-4"DIA NON-PERF-DAYLIGHTED LF 250.00 $ 22.10 LF $ 5,525
UNDERSLAB DRAINS-4"PERF PIPING N/A-EXCLUDED LF - $ 12.50 LF $ -
TOTAL-FOUNDATION DRAINAGE SYSTEM $ 5,526
2000 SITE WORK(BUILDING)-TOTALS $ 20,157
2000 SITEWORK-BLDG FCI Constructors,Inc.Confidential Page 8
•
FCI Cost Worksheet 7/24/2014/UPDATED 7/:
Project; EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
030000 CONCRETE
033000 CAST-IN-PLACE CONCRETE FCI CONSTRUCTORS
COLUMN FOOTINGS APPARATUS BAYS
FORM/STRIP COLUMN FOOTINGS SF 1201.00 $ 7.67 SF $ 662,280
SET COLUMN ANCHOR BOLTS SETS - $ 66.00 SETS $ -
GROUT COLUMN BASE PLATES EA - $ 42.00 EA $ -
REBAR TO COLUMN FOOTINGS TN 6.30 $ 1,806.00 TN INCLUDED
CONCRETE TO COLUMN FOOTINGS CY 124.14 $ 184.50 CY INCLUDED
SUBTOTAL-COLUMN FOOTINGS $ 652,290
$ 5,254.47 CY
WALL FOOTINGS
FORM/STRIP WALL FOOTINGS SF 1,994.00 $ 6.15 SF INCLUDED
SHEAR KEYWAY-WALL FOOTINGS N/A LF - $ 2.60 LF $ -
WATERSTOP-BENTONITE N/A LF - $ 5.20 LF $ -
REBAR TO WALL FOOTINGS TN 2.70 $ 1,680.00 TN INCLUDED
CONCRETE TO WALL FOOTINGS 4000 PSI CY 77.10 $ 177.87 CY INCLUDED
SUBTOTAL-WALL FOOTINGS $ -
$ -
STEM WALLS ADMIN WING
FORM/STRIP STEM WALLS SF 5,032.00 $ 8.50 SF INCLUDED
SET EMBED INSERTS FOR JOIST LEDGER
ANGLES N/A EA - $ 63.00 EA $ -
FORM/STRIP SHELF FOR CF LEDGER JSTS LF 102.00 $ 7.00 LF INCLUDED
SET COLUMN ANCHOR BOLTS SETS - $ 66.00 SETS $ -
GROUT COLUMN BASE PLATES EA - $ 47.08 EA $ -
REBAR TO STEM WALLS TN 4.60 $ 1,510.00 TN INCLUDED
POINT&PATCH STEM WALLS SF 2,516.00 $ 0.62 SF INCLUDED
CONCRETE TO STEM WALLS 4000 PSI CY 65.60 $ 184.50 CY INCLUDED
SUBTOTAL-STEM WALLS $ -
$ -
STEM WALLS APPARATUS BAYS
FORM/STRIP STEM WALLS SF 4,605.00 $ 8.50 SF INCLUDED
SET COLUMN ANCHOR BOLTS SETS 22.00 $ 66.00 SETS INCLUDED
GROUT COLUMN BASE PLATES EA 22.00 $ 47.08 EA $ 1,036
REBAR TO STEM WALLS TN 5.92 $ 1,510.00 TN INCLUDED
POINT&PATCH STEM WALLS SF 2,302.50 $ 0.62 SF INCLUDED
RUB FINISH TO EXPOSED WALLS SF 1,792.00 $ 2.16 SF INCLUDED
3/4"CHAMFER EDGE-PILLASTERS LF 176.00 $ 4.55 LF INCLUDED
CONCRETE TO STEM WALLS 4000 PSI CY 73.00 $ 184.50 CY INCLUDED
SUBTOTAL-STEM WALLS $ 1,036
$ 14.19
TIE BEAMS EXCLUDED-NOT SHOWN
FORM/STRIP TIE BEAMS SF - $ 7.00 SF $ -
REBAR TO TIE BEAMS ALLOW 12.0011/LF TN - $ 1,806.00 TN $ -
POINT&PATCH TIE BEAMS SF - $ 0.62 SF $ -
CONCRETE TO TIE BEAMS CY - $ 184.50 CY $ -
SUBTOTAL-TIE BEAMS $ -
#DIV/01
3000 CONCRETE FCI Constructors,Inc.Confidential Page 9
FCI Cost Worksheet 712412014 I UPDATED 7I
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
030000 CONCRETE
033000 CAST-IN-PLACE CONCRETE FCI CONSTRUCTORS
SLAB ON GRADE-8.00"TH APPARATUS BAYS
CONCRETE TO SLAB ON GRADE CY 557.50 $ 178.65 CY INCLUDED
CONSTRUCTION JOINTS LF 492.00 $ 5.40 LF INCLUDED
EDGE FORMS-12" PERIMETER DOOR SILLS LF 158.00 $ 5.70 LF INCLUDED
PERIMETER JOINT FILLER-8"X 1/2" LF 619.00 $ 6.85 LF INCLUDED
REBAR TO SLAB ON GRADE-2 LAYER45'S AT
12"OC TN 51.92 $ 1,806.00 TN INCLUDED
REBAR TO SLAB ON GRADE-CORNER BARS AT COLUMNS TN 0.33 $ 1,806.00 TN INCLUDED
REBAR TO SLAB ON GRADE-AT TRENCH
DRAINS ALLOW 12#/LF TN 0.38 $ 1,806.00 TN INCLUDED
CONSTRUCTION JOINT DOWELS EA 492.00 $ 7.70 EA INCLUDED
CONSTRUCTION JTS-WATERSTOP LF 492.00 $ - LF $ 6,150
6"VOID FORMS N/A-EXCLUDED SF - $ 5.25 SF $ -
CONTROL JOINTS-SAWN/CAULKED LF 976.00 $ 2.15 LF INCLUDED
TROWEL FINISH SLAB ON GRADE SF 20,158.00 $ 0.42 SF INCLUDED
CURE&PROTECT SLAB ON GRADE SF 20,158.00 $ 0.41 SF INCLUDED
FORM COLUMN POCKETS EA 22.00 $ 54.00 EA INCLUDED
GROUT COLUMN POCKETS EA 22.00 $ 38.82 EA INCLUDED
SUBTOTAL-SLAB ON GRADE $ 6,150
$ 0.31 SF
SLAB ON GRADE-5.00"TH
CONCRETE TO SLAB ON GRADE CY 27.98 $ 178.65 CY INCLUDED
CONSTRUCTION JOINTS LF - $ 5.40 LF $ -
EDGE FORMS-12" N/A LF - $ 5.70 LF $ -
PERIMETER JOINT FILLER-6"X 1/2" LF 232.00 $ 5.75 LF INCLUDED
REBAR TO SLAB ON GRADE-1 LAYER45'S AT
12"OC TN 2.14 $ 1,806.00 TN INCLUDED
CONSTRUCTION JOINT DOWELS N/A EA - 5 7.70 EA $ -
6"VOID FORMS N/A-EXCLUDED SF - $ 5.25 SF $ -
CONTROL JOINTS-SAWN/CAULKED LF 256.95 $ 2.15 LF INCLUDED
TROWEL FINISH SLAB ON GRADE SF 1,713.00 $ 0.42 SF INCLUDED
CURE&PROTECT SLAB ON GRADE SF 1,713.00 $ 0.41 SF INCLUDED
FORM COLUMN POCKETS N/A EA - $ 54.00 EA $ -
GROUT COLUMN POCKETS N/A EA - $ 38.82 EA $ -
SUBTOTAL-SLAB ON GRADE $ -
$ - SF
ADMIN WING-OVER CRAWL
SLABS ON METAL DECKING SPACE
CONCRETE TO SLABS ON DECK NORMAL WI-CONCRETE CY 29.66 $ 184.50 CY INCLUDED
WIRE MESH REINF.-6X6AN2.1 SF 4,004.00 S 0.89 SF INCLUDED
REBAR TO SLABS ON DECK N/A TN - $ 1,806.00 TN $ -
WELDED BARS-TO POUR STOP-#4 X 2'6"L N/A-EXCLUDED EA - $ 46.00 EA $ -
TROWEL FINISH SLABS ON DECK SF 3,640.00 $ 0.61 SF INCLUDED
CURE&PROTECT SLABS ON DECK SF 3,640.00 5 0.33 SF INCLUDED
SUBTOTAL-SLABS ON METAL DECKING $ -
$ - SF
EXTERIOR APRON PAVEMENT 6"THICK
CONCRETE TO SLABS ON GRADE 6"THICKNESS CY 33.37 $ 213.85 CY INCLUDED
ADD FOR FIBERMESH REINFORCING N/A CY - $ 9.00 CY $ -
FINE GRADE SUBGRADE SF 1,716.00 $ 0.32 SF INCLUDED
EDGE FORMS-6" LF 127.00 $ 7.00 LF INCLUDED
REBAR TO CONCRETE PAVMNT45 BARS AT CONNECTION TO EX PVMNT TN 0.12 $ 1,806.00 TN INCLUDED
WIRE MESH REINF.-6X6IW2.9 REINFORCED PANEL SF 198.00 $ 1.18 SF INCLUDED
CONSTRUCTION JOINTS LF 288.00 $ 5.40 LF INCLUDED
CONSTRUCTION JOINT DOWELS EA 288.00 $ 10.20 EA INCLUDED
CONTROL JOINTS-SAWN/CAULKED LF 288.00 $ 3.41 LF $ 3,200
FINISH 6"CONCRETE PAVEMENT SF 1,716.00 $ 0.52 SF INCLUDED
CURE&PROTECT CONC PAVEMENT SF 1,716.00 $ 0.41 SF INCLUDED
3000 CONCRETE FCI Constructors,Inc.Confidential Page 10
FCI Cost Worksheet 7124/20141 UPDATED 7/:
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
SUBTOTAL-EXTERIOR APRON PAVEMENT $ 3,200
$ 1.86 SF
3000 CONCRETE FCI Constructors,Inc.Confidential Page 11
FCI Cost Worksheet 7/24/2014/UPDATED 7f
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
030000 CONCRETE
033000 CAST-IN-PLACE CONCRETE FCI CONSTRUCTORS
SNOW MELT APPROACH APRONS 6"THICK
CONCRETE TO SLABS ON GRADE 6°THICKNESS CY 33.06 $ 213.85 CY INCLUDED
ADD FOR FIBERMESH REINFORCING N/A CY - $ 9.00 CY $ -
FINE GRADE SUBGRADE SF 1,700.00 $ 0.32 SF INCLUDED
EDGE FORMS-8" LF 173.00 $ 4.90 LF INCLUDED
REBAR TO CONCRETE PAVMNT45Q12"OC N/A TN - $ 1,806.00 TN $ -
CONSTRUCTION JOINTS LF 225.00 $ 5.40 LF INCLUDED
CONSTRUCTION JOINT DOWELS EA 225.00 $ 10.20 EA INCLUDED
FINISH 6"CONCRETE PAVEMENT SF 1,700.00 $ 0.52 SF INCLUDED
CURE&PROTECT CONC PAVEMENT SF 1,700.00 $ 0.41 SF INCLUDED
2"RIGID INSULATION SF 1,700.00 $ 2.20 SF $ 3,740
SUBTOTAL-SNOW MELT APRONS $ 3,740
CONCRETE WALKS-6"THICK ON SITE WALKS
CONCRETE TO SIDEWALKS CY 15.51 $ 213.85 CY INCLUDED
ADD FOR FIBER MESH REINFORCING N/A CY - $ 11.00 CY $ -
ADD FOR COLORED CONCRETE N/A-EXCLUDED CY - $ 90.00 CY $ -
REBAR TO SIDEWALKS-#4 BARS AT 16"
OC/EW 1.20/i/SF TN 0.48 $ 1,995.00 TN $ 600
FINE GRADE SUBGRADE SF 797.50 $ 0.30 SF INCLUDED
EDGE FORMS-6" LF 133.00 $ 6.55 LF INCLUDED
EXPANSION JOINTS LF 39.88 $ 8.50 IF INCLUDED
SCORE JOINTS LF 159.50 $ 1.93 LF INCLUDED
FINISH SIDEWALKS SF 797.50 $ 0.58 SF INCLUDED
CURE&PROECT SF 797.50 $ 0.26 SF INCLUDED
2"RIGID INSULATION SF 797.50 $ 2.20 SF $ 1,755
SUBTOTAL-SIDEWALKS $ 2,355
CONCRETE VEE PANS PARKING LOTS SF 304.00
CONCRETE TO SLABS ON GRADE CY 7.92 $ 213.85 CY INCLUDED
ADD FOR FIBERMESH REINFORCING N/A CY - $ 9.60 CY $ -
FINE GRADE SUBGRADE SF 304.00 $ 0.32 SF INCLUDED
EDGE FORMS-6" LF 160.00 $ 7.00 IF INCLUDED
REBAR TO CONCRETE PAVMNT45€1212"OC
EW N/A-UNREINFORCED TN - $ 1,730.00 TN $ -
FINISH 6"CONCRETE PAVEMENT SF 304.00 $ 0.69 SF INCLUDED
CURE&PROTECT CONC PAVEMENT SF 304.00 $ 0.41 SF INCLUDED
SUBTOTAL-VEE PANS $ -
TRENCH DRAINS-CONCRETE
ENCASEMENT SURROUND
FORM/STRIP SIDE WALLS LF 267.00 $ 9.20 LF INCLUDED
REBAR TO TRENCH DRAINS TN 0.45 $ 1,995.00 TN INCLUDED
CONCRETE TO TRENCH DRAINS CY 8.16 $ 233.35 CY INCLUDED
SUBTOTAL-TRENCH DRAINS $ -
$ - LF
MEP EQUIPMENT PADS/MISC CONCRETE
HOUSEKEEPING PADS LS 1.00 $ 2,100.00 LS $ 2,100
SET/GROUT PIPE BOLLARDS AROUND BUILDING EA 16.00 $ 258.00 EA INCLUDED
SET/GROUT PIPE BOLLARDS N/A EA - $ 256.00 EA $ -
SUBTOTAL-MEP EQUIPMENT PADS/MISC CONCRETE $ 2,100
3000 CONCRETE FCI Constructors,Inc.Confidential Page 12
FCI Cost Worksheet 7/24120141 UPDATED 71:
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
3000 CONCRETE FCI Constructors,Inc.Confidential Page 13
FCI Cost Worksheet 7/24/2014/UPDATED 71:
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
030000 CONCRETE
033000 CAST-IN-PLACE CONCRETE FCI CONSTRUCTORS
CONCRETE PUMPING/HOISTING
CONCRETE PUMP DYS 5.00 $ 1,800.00 DYS INCLUDED
WINTER CONCRETE BUILDING FLATWORK CY 615.14 $ 24.00 CY $ 28,600
WINTER PROTECTION-BLANKETS LS 1.00 $ 12,180.00 LS $ 12,180
LAYOUT/COORDINATION-CONCRETE HRS 173.00 $ 54.00 HRS $ 9,342
CLEANUP FIRS 160.00 $ 41.00 FIRS $ 6,560
DUMPSTERS PULLS 2.00 $ 1,000.00 PULLS$ 2,000
SUBTOTAL-CONCRETE PUMPING/HOISTING $ 58,682
SUBTOTAL-CAST4N-PLACE CONCRETE $ 729,552
030000 CONCRETE-TOTALS $ 729,552
3000 CONCRETE FCI Constructors,Inc.Confidential Page 14
FCI Cost Worksheet 7/24/2014/UPDATED 7/3
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
040000 MASONRY
042010 UNIT MASONRY BERICH MASONRY
8"CMU WALLS-REINFORCED INTERIOR WALLS SF 3,084.00
8"HOLLOW CMU-SMOOTH FACE PC 3,180.60 $ 10.62 PC $ 104,000
8"BOND BEAM CMU-SMOOTH FACE PC 366.00 $ 11.29 PC INCLUDED
MORTAR CY 6.50 $ 300.00 CY INCLUDED
VERTICAL REINF.STEEL-8"PTNS LB 1,850.40 $ 0.82 LB INCLUDED
ADD FOR GROUTING 8"'WALLS. SF 3,084.00 $ 1.30 SF INCLUDED
SCAFFOLDING SF 3,084.00 $ 0.80 SF INCLUDED
TOOL JOINTS SF 3,084.00 $ 0.15 SF INCLUDED
8"DUROWALL REINFORCING-16"OC LF 2,467.20 $ 0.24 LF INCLUDED
BOND BEAM REINF.STEEL-2 65'S LB 1,160.00 $ 0.82 LB INCLUDED
$ 33.72 SF
EXTERIOR WALLS--4°SPLIT FACE 4"SPLIT FACE CMU VENEER-
VENEER"""" RUNNING BOND SF 2,805.00
EXTERIOR 4"SPLIT FACE CMU WALL VENEER RUNNING BOND PC 3,225.75 $ 9.21 PC INCLUDED
MORTAR-COLORED CY 11.06 $ 450.00 CY INCLUDED
SCAFFOLDING SF 2,805.00 $ 1.00 SF INCLUDED
WALL ANCHORS EA 1,050.56 $ 0.55 EA INCLUDED
4"DUROWALL REINFORCING-16"OC LF 1,275.20 $ 0.24 LF INCLUDED
WALL FLASHING-MEMBRANE LF 456.00 $ 5.00 LF INCLUDED
INSTALL SHEET METAL FLASHING-FBO LF 228.00 $ 6.00 LF INCLUDED
SOLID SF CMU SILL TRIM LF 47.00 $ 19.50 LF INCLUDED
SET LOOSE LINTELS-SMALL EA 1.00 $ 30.00 EA INCLUDED
SET LOOSE LINTELS-LARGE N/A EA - $ 66.00 EA $ -
TOOL JOINTS-CMU SF 2,805.00 $ 0.15 SF INCLUDED
WASHDOWN WALLS SF 2,805.00 $ 0.20 SF INCLUDED
4"DUROWALL REINFORCING-16"OC LF 2,244.00 $ 0.20 LF INCLUDED
$ • SF
4"CMU WALLS-REINFORCED CMU FOUNDATION VENEER SF 626.00
4"HOLLOW CMU-SMOOTH FACE PC 718.75 $ 8.37 PC INCLUDED
MORTAR CY 1.32 $ 300.00 CY INCLUDED
ADD FOR GROUTING 4"'WALLS. SF 625.00 $ 1.30 SF INCLUDED
SCAFFOLDING SF 625.00 $ 0.80 SF INCLUDED
TOOL JOINTS SF 625.00 $ 0.15 SF INCLUDED
$ - SF
LAYOUT HRS 40.00 $ 54.00 HRS $ 2,160
CLEANUP HRS 80.00 $ 39.00 HRS $ 3,120
DUMPSTERS PULLS 1.00 $ 1,000.00 PULL $ 1,000 I
WINTER PROTECTION MO 1.00 $ 6,747.00 /MO $ 6,747
TEMPORARY HEAT-MASONRY WORK MO 1,00 $ 6,000.00 /MO $ 6,000
SUBTOTAL-UNIT MASONRY $ 123,027
040000 MASONRY-TOTALS $ 123,027
4000 MASONRY FCI Constructors,Inc.Confidential Page 15
FCI Cost Worksheet 7/2412014/UPDATED 7/
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
050000 METALS
053100 METAL DECKING PEAK INTERIORS
FLOOR DECK-0.60"22 GA-G60 COATING 1ST FLOOR SF 4,004.00 $ 2.30 SF $ 33,490
ROOF DECK-0.60"22 GA-G60 COATING ADMIN ROOF SF 6,371.20 $ 2.30 SF INCLUDED
20 GA METAL POUR STOP LF 555.00 $ 5.23 LF INCLUDED
2"X 2"-18 GA ROOF DECK SUPPORT LF 372.00 $ 5.33 LF INCLUDED
SUBTOTAL-METAL DECKING $ 33,490
054400 COLD-FORMED METAL FRAMING PEAK INTERIORS
12"-12 GAGE FLOOR JOISTS HORIZONTAL FRAMING LF 2,846.80 $ 9.85 LF INCLUDED
12"-12 GAGE ROOF JOISTS LF 5,062.20 $ 10.60 LF INCLUDED
12"-16 GAGE FLOOR JOIST LEDGERS LF 99.00 $ 6.20 LF INCLUDED
12"-12 GAGE JOIST BLOCKING-FLOORS EA 225.00 $ 18.78 EA INCLUDED
12"-12 GAGE JOIST BLOCKING-ROOF EA 515.00 $ 18.78 EA INCLUDED
JOIST BLOCKING ATTACHMENT CLIPS EA 1,480.00 $ 2.45 EA INCLUDED
FLOOR/ROOF JOIST HANGERS/CONNECTORS EA 910.80 $ 3.25 EA INCLUDED
22 GA METAL SHEAR WALL SHEATHING SF 608.00 S 3.48 SF INCLUDED
4"-20 GAGE MTL TRACK CRAWL SPACE KNEE WALLS LF 612.00 $ 6.75 LF INCLUDED
4"-18 GAGE MTL STUD FRAMING CRAWL SPACE KNEE WALLS LF 918.00 $ 5.15 LF INCLUDED
SUPERVISION HRS 173.00 $ 68.00 HRS INCLUDED
MISC FASTENERS/EQUIPMENT/SMALL TOOLS LS 1.00 $ 7,500.00 LS INCLUDED
SUBTOTAL-COLD-FORMED METAL FRAMING $ -
055010 MISCELLANEOUS METALS
PIPE BOLLARDS-8"DIA-GALVANIZED FURNISH ONLY EA 16.00 $ 210.00 EA $ 3,360
WF ROOF FRAMING X-FER BEAM TNS 0.73 $ 6,000.00 TNS $ 4,373
LEDGER ANGLE 6 X 4 X 0.315 ANGLES TNS 1.17 $ 6,500.00 TNS $ 7,613
POUR STOP ANGLE-EXP BOLTED TO CONC 3.5X2.5X0.1875 LF 16.00 $ 27.00 LF $ 432
ROOF ACCESS LADDER-WALL MID-
ALUMINUM LF 15.00 $ 135.00 LF $ 2,025
TRENCH DRAIN GRATINGS&LEDGER
ANGLES N/A-SEE PREFAB UNITS SF - $ 45.00 SF $ •
ANCHOR BOLTS FOR PEMB COLS MAIN BUILDING SETS 23.00 $ 140.00 SETS $ 3,220
STEEL LINTELS AT CMU OPENINGS LF 42.50 $ 13.85 LF $ 689
MISC CLIPS,ATTACHMENTS,HW SF 26,050.00 $ 0.28 SF $ 7,294
LAYOUT HRS 40.00 $ 54.00 HRS $ 2,160
SUBTOTAL-MISCELLANEOUS METALS $ 31,066
050000 METALS-TOTALS $ 64,556
COST PER SF $ 2.48
050000 METALS BID ALTERNATE#2
055010 MISCELLANEOUS METALS
CATWALKS GRATINGS-GALVANIZED STORAGE PLATFORM SF 1,035.00 $ 15.75 SF $ 16,301
SUPPORT FRAMING-PRIME PAINTED STORAGE PLATFORM LBS 15,142.00 $ 2.01 LBS $ 30,473
SUBTOTAL-MISCELLANEOUS METALS $ 46,775
5000 METALS FCI Constructors,Inc.Confidential Page 16
FCI Cost Worksheet 7124120141 UPDATED 71
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
III
5000 METALS FCI Constructors,Inc,Confidential Page 17
FCI Cost Worksheet 7/2412014/UPDATED 713
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
060000 WOOD&PLASTICS
061100 ROUGH CARPENTRY FCI CONSTRUCTORS
ROOF BLOCKING-2"X 4"TREATED NAILERS PERIMETER NAILERS LF 83.60 $ 3.65 LF $ 305
3/4"TH EXTER PLYWOOD-COPING
ASSEMBLIES 2-LAYERS SF 906.00 $ 3.28 SF $ 2,967
2"X 6"X 8"COPING BLOCKS UNDER PLYWOOD EA 80.00 $ 8.25 EA $ 680
1/2"TH EXTER PLYWOOD SHEATHING-BACK
SIDE OF PARAPETS N/A-SEE DRYWALL SF - $ 2.10 SF $ -
EXTERIOR WALL BLOCKING-2.5 X 2.5 IN-WALL NAILER LF 177.10 $ 7.20 LF $ 1,276
EXTERIOR WALL BLOCKING-2.5 X 3.0 IN-WALL NAILER LF 33.00 $ 7.40 LF $ 244
EXTERIOR WALL BLOCKING AT ROOF SCUPPER LF 14.00 $ 9.50 LF $ 133
INTERIOR WALL STRAPPING/BLOCKING-
MILLWORK/CASEWORK LF 204.60 $ 5.00 LF $ 1,023
ROUGH TIMBER FRAMING-4"X 6" ROOF CANOPY COLUMNS LF 60.00 $ 21.50 IF $ 1,290
ROUGH TIMBER FRAMING-8"X 10" ROOF CANOPY BEAMS LF 30.80 $ 35.69 LF $ 1,099
ROUGH TIMBER FRAMING-8"X 12" ROOF CANOPY BEAMS LF 48.40 $ 44.81 LF $ 2,169
ROUGH TIMBER FRAMING-8"X 14" ROOF CANOPY BEAMS LF 49.50 $ 50.24 LF $ 2,487
TIMBER FRAMING CONNECTORS EA 20.00 $ 85.00 EA $ 1,700
2"X 6"T&G WOOD DECKING ROOF CANOPIES LF 537.60 $ 4.45 LF $ 2,392
ROUGH HARDWARE LS 1.00 $ 1,500.00 LS $ 1,500
LAYOUT HRS 24.00 $ 54.00 HRS $ 1,298
SUBTOTAL-ROUGH CARPENTRY $ 20,541
064010 MILLWORK DELTA CABINET
LAVATORY COUNTERS-QUARTZ LF 15.50 $ 177.00 LF $ 34,095
WALL MOUNTED COUNTER-PLAS LAM LAUNDRY RM IF 5.00 $ 70.00 LF INCLUDED
BASE CABINETS-PLAS LAM STAFF BREAK RM LF 12.00 $ 233.56 LF INCLUDED
COUNTERTOPS-SOLID SURFACE STAFF BREAK RM LF 12.00 $ 141.71 IF INCLUDED
WALL CABINETS-P LAM STAFF BREAK RM LF - $ 213.56 LF $ -
36"W FULL HT STORAGE CABINETS-PLAS
LAM STAFF BREAK RM EA 1.00 $ 478.24 EA INCLUDED
BASE CABINETS-PLAS LAM TRAINING ROOM LF 15.50 $ 233.56 LF INCLUDED
COUNTERTOPS-QUARTZ TRAINING ROOM LF 16.00 $ 176.71 LF INCLUDED
WALL CABINETS-P LAM TRAINING ROOM IF - $ 213.56 LF $ -
BASE CABINETS-PLAS LAM PRINTING ROOM LF 16.00 $ 233.56 LF INCLUDED
COUNTERTOPS-QUARTZ PRINTING ROOM LF 16.00 $ 176.71 LF INCLUDED
WALL CABINETS-P LAM PRINTING ROOM LF 17.00 $ 213.56 LF INCLUDED
MISC MILLWORK-ALLOW ALLOWANCE SF 5,235.00 $ 0.30 SF $ 1,571
SUBTOTAL-MILLWORK $ 35,666
060000 WOOD&PLASTICS-TOTALS $ 66,206
COST PER SF $ 2.16
I
6000 WOOD&PLASTICS FCI Constructors,Inc.Confidential Page 18
FCI Cost Worksheet 7/24/2014/UPDATED 7/3
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
070000 THERMAL&MOISTURE PROTECTION
071600 DAMPPROOFING
DAMPPROOF PERIM STEM WALLS OUTSIDE FACE OF PERIM FDN SF 1,335.00 $ 1.74 SF $ 2,321
DAMPPROOFING-PROTECTION BD SF 1,335.00 $ 1.25 SF $ 1,669
PERIMETER FOUNDATION INSULATION-1"TH SF 514.00 $ 1.74 SF $ 894
PERIMETER FOUNDATION INSULATION-2"TH SF 3,265.00 $ 2.61 SF $ 8,522
PERIMETER FOUNDATION INSULATION-2"TH-
UNDER SLAB N/A-EXCLUDED SF - $ 2.61 SF $ -
SUBTOTAL-DAMPPROOFING $ 13,405
071800 WATERPROOFING
WATERPROOF CRAWL SPACE FOUNDATION COLD FLUID APPLIED+
WALLS INSULATED DRAINAGE BAORDS SF 1,694.00 $ 8.17 SF $ 13,834
SUBTOTAL-WATERPROOFING $ 13,834
071950 AIR&MOISTURE BARRIERS VAPRO SHIELD/FCI CONSTRUCTORS ONLY
AIR BARRIER(TYVEK)-TO EXTER WALLS N/A-EXCLUDED SF - $ 0.92 SF $ -
RAIN SCREEN MOISTURE BARRIER SYSTEM-
APPLIED TO EXTERIOR SHEATHING-SHEET BEHIND MASONRY&METAL
MEMBRANE WALL PANELS SF 4,562.00 $ 3.22 SF $ 14,690
AIR BARRIER-TO EXTER SOFFITS N/A-EXCLUDED SF - $ 0.92 SF $ -
AIR BARRIER-TO EXTER SOFFITS N/A-EXCLUDED SF - $ 0.92 SF $ -
SUBTOTAL-AIR&MOISTURE BARRIERS $ 14,690
072110 BUILDING INSULATION FCI CONSTRUCTORS
R30 BATTS TO U/S FLOOR DECK-
ENCAPSULATED-CRAWL SPACE N/A-EXCLUDED SF - $ 2.37 SF $ -
4"/R11 FF INSULATION TO EXTERIOR WALLS WITHIN STUD CAVITIES SF 4,562.00 $ 1.09 SF $ 4,969
2.5"/R14 RIGID INSULATION-MASONRY
CAVITY WALLS N/A-EXCLUDED SF - $ 3.25 SF $ -
EXTER METAL STUD FRAMED
2.5"/R10.4 SEMI-RIGID INSULATION WALLS SF 4,562.00 $ 3.78 SF $ 17,244
2.5"/R10.4 SEMI-RIGID INSULATION PARAPET ASSEMBLIES SF 888.00 $ 3.78 SF $ 3,357
3.5"UN-FACED SOUND BATT INSUL INTERIOR SOUND INSUL SF 6,744.00 $ 0.86 SF 8 5,770
MISC SPRAY FOAM INSUL-CLOSED CELL BLIND APPLICATIONS LS 1.00 $ 1,900.00 LS $ 1,900
SUBTOTAL-BUILDING INSULATION $ 33,240
072700 FIRESTOPPING FCI CONSTRUCTORS
FIRE STOPPING-RATED WALLS 1-HR&2-HOUR WALL ASSEMBLY LF 136.00 $ 59.52 LF 8 8,095
SUBTOTAL-FIRESTOPPING $ 8,095
074599 RAIN-SCREEN WALL ASSEMBLY KNIGHT WALL SYSTEMS/FCI CONSTRUCTORS ONLY
RESYSTA HORIZONTAL PANELS-12"W COMPOSITE PANELS SF 872.00 $ - SF $ 22,741
PANEL SUPPORT GRID SYSTEM-W WALL
STAND-OFF CONNECTIONS SF 1,400.00 $ - SF INCLUDED
VERTICAL RIBBED PANELS-24 GA
GALVALUME W/KYNAR PAINT FINISH PANEL 7.2-EXPOSED FASTENERS SF 528.00 $ 4.00 SF $ 2,112
INSTALL GRID SYSTEM HRS 100.00 $ - HRS $ 6,600
INSTALL RESYSTA PANELING HRS 80.00 $ - HRS $ 5,280
INSTALL METAL WALL PANELS HRS 32.00 $ - HRS $ 2,112
PER DIEM/TEMP HOUSING LS 1.00 $ - LS $ 3,000
SCAFFOLDING/EQUIPMENT LS 1.00 $ - LS $ 2,000
SUBTOTAL-RAIN-SCREEN WALL ASSEMBLY $ 43,845
7000 THERM&MOIS PROT FCI Constructors,Inc.Confidential Page 19
FCI Cost Worksheet 7/24/2014 I UPDATED 7/3
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
070000 THERMAL&MOISTURE PROTECTION
075010 MEMBRANE ROOFING THE ROOFING COMPANY
LOW SLOPE ROOFING"'*"' ADMIN WING SF 6,158.00
TPO ROOF MEMBRANE-60 MIL TH SF 6,158.00 $ 1.88 SF $ 68,973
ROOF INSULATION-R 20(UN-TAPERED) SF 6,158.00 $ 3.13 SF INCLUDED
ADD FOR FULL TAPERED INSULATION ALLOWANCE LS 1.00 $ 10,000.00 LS $ 10,000
ADD FOR TAPERED INSULATION-CRICKETS SF 1224.00 $ 3.96 SF INCLUDED
VAPOR BARRIER N/A-EXCLUDED SF - $ 0.22 SF $ -
ROOF COVER BOARD-1/2"TH SF 6,158.00 $ 1.25 SF INCLUDED
MATERAL SF 1,452.00 $ 2.92 SF INCLUDED
MISC FLASHING-MEMBRANE-ROOF
OPENINGS SF 100.00 $ 2.92 SF INCLUDED
ROOF WALKWAY PADS SF 666.00 $ 4.40 SF INCLUDED
FLASH ROOF DRAINS/OVERFLOW DRAINS EA 12.00 $ 73.00 EA INCLUDED
OVERFLOW SCUPPERS EA 1.00 $ 161.00 EA INCLUDED
PERIMETER COPING-PAINTED STEEL-BREAK
METAL LF 299.00 $ 18.00 LF INCLUDED
PAINTED METAL GUTTER N/A LF - $ 16,00 LF $ -
PAINTED METAL DOWNSPOUT N/A LF - $ 16.00 LF $ -
SUBTOTAL-MEMBRANE ROOFING $ 78,973
076140 SHEET METAL FLASHING FCI CONSTRUCTORS
THRU-WALL FLASHING-BOW-INSTALLED BY
MASON PREFINISHED-W/DRIP EDGE LF 228.00 $ 11.00 LF $ 2,608
SILL FLASHING-EXPOSED PREFINISHED-W/DRIP EDGE LF 62.00 $ 13.86 LF $ 869
SUBTOTAL-SHEET METAL FLASHING $ 3,367
077100 ROOF TIE-OFF SYSTEM
ROOF TIE-OFF SYS-SS CABLES&POSTS N/A-EXCLUDED LF - $ 101.64 LF $ •
SUBTOTAL-TIE-OFF SYSTEM $ -
077200 ROOF ACCESSORIES
NEW ROOF HATCH-2'6"X 2'6" N/A-EXCLUDED EA - $ 2,465.00 EA $ -
SMOKE VENTS N/A-EXCLUDED EA - $ 3,151.36 EA $ -
SUBTOTAL-ROOF ACCESSORIES $ -
078010 APPLIED FIREPROOFING
SPRAY-APPLIED FIREPROOFING N/A-EXCLUDED SF - $ 2.30 SF $ -
INTUMESCENT PAINT-ON FIREPROOFING N/A-EXCLUDED SF - $ 7.70 SF $ -
SUBTOTAL-APPLIED FIREPROOFING $ -
078210 UNIT SKYLIGHTS
UNIT SKYLIGHTS-PREFABRICATED
INSULATED UNIT W/CURB-30"X 30" N/A-EXCLUDED EA - $ 1,514.00 EA $ -
SUBTOTAL-UNIT SKYLIGHTS $ .
079010 CAULKING&SEALANTS SUMMIT SEALANTS
CAULKING SF 26,050.00 $ 0.65 SF $ 16,985
SUBTOTAL-CAULKING&SEALANTS $ 16,986
7000 THERM&MOIS PROT FCI Constructors,Inc.Confidential Page 20
FCI Cost Worksheet 7124/2014/UPDATED 713
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
070000 THERMAL&MOISTURE PROTECTION-TOTALS $ 226,434
COST PER SF $ 6.69
7000 THERM&MOIS PROT FCI Constructors,Inc.Confidential Page 21
FCI Cost Worksheet 7124120141 UPDATED Ili
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
080000 DOORS&WINDOWS
EVERGREEN CONSTRUCTION
081140 METAL DOORS&FRAMES SPECIALTIES
HM DOORS&FRAMES-FURNISH&DELIVER LS 1.00 $ 20,172.00 LS $ 20,172
HM DOOR FRAMES-3'X 7'-16 GA-WELDED EA 13.00 $ 84.00 EA $ 1,092
HM DOOR FRAMES-3'X 7'2"-16
GA/GALVANIZED-WELDED EA 4.00 $ 90.00 EA $ 360
HM DOOR FRAMES-5'X 7'-16 GA-WELDED
CORNERS EA 1.00 $ 87.00 EA $ 87
HM DOOR FRAMES-3'X 8'0"-16
GA/GALVANIZED-WELDED EA 1.00 $ 96.00 EA $ 96
HM DOOR FRAMES-4'X 8'0"-16
GA/GALVANIZED-WELDED EA 1.00 $ 105.00 EA $ 105
HM DOOR FRAMES-8'X 8'0"-16
GA/GALVANIZED-WELDED EA 2.00 $ 120.00 EA $ 240
HM DOORS-3'X 7'-16 GA/GALVANIZED-FLUSH EA 4.00 $ 240.00 EA $ 980
HM DOORS-3'X 8'-16 GA/GALVANIZED-FLUSH EA 1.00 $ 270.00 EA $ 270
HM DOORS-4'X 8'-16 GA/GALVANIZED-FLUSH EA 5.00 $ 285.00 EA $ 1,425
ADD FOR VISION PANEL CUTOUTS EA 3.00 $ - /EA $ -
ADD FOR RATED DOORS EA 2.00 $ - /EA $ -
LAYOUT HRS 16.00 $ 54.00 HRS $ 864
SUBTOTAL-HOLLOW METAL DOORS&FRAMES $ 25,671
EVERGREEN CONSTRUCTION
082168 SOLID CORE LAMINATE CLAD DOORS SPECIALTIES
SC WOOD DOORS/HPDL FINISH-FURNISH&
DELIVER LS 1.00 $ - LS INCLUDED
SOLID CORE WOOD DRS-HPDL VENEER-2'6"
X 7' EA 2.00 $ 240.00 /EA $ 480
7' EA 13.00 $ 240.00 /EA $ 3,120
ADD FOR VISION LIGHT KITS EA 7.00 $ - /EA $ -
SUBTOTAL-SOLID CORE LAMINATE CLAD DOORS $ 3,600
083050 ACCESS DOORS FCI CONSTRUCTORS
WALL/CEILING ACCESS DORS EA 4.00 $ 260.00 /EA $ 1,040
SUBTOTAL-ACCESS DOORS $ 1,040
OVERHEAD DOOR CO OF
083115 SECTIONAL OVERHEAD DOORS GRAND JUNCTION
SECTIONAL OH DOOR-INSULATED/HS
MOTOR OPERATED-28'0"X 20'0" INSULATED STEEL EA 1.00 $ 19,080.00 EA $ 37,467
SECTIONAL OH DOOR-INSULATED/HS
MOTOR OPERATED-34'0"X 20'0" INSULATED STEEL EA 1.00 $ 22,096.00 EA INCLUDED
SUBTOTAL-SECTIONAL OVERHEAD DOORS $ 37,487
OVERHEAD DOOR CO OF
083120 COILING DOORS&SHUTTERS GRAND JUNCTION
COILING STEEL DOOR-1 HR RATED-12'X 9' WA-DELETED AT DD EA - $ 6,100.00 EA $ -
COILING FIRE SHUTTER-3'6"X 4'2" TRAINING EA 1.00 $ 2,896.00 EA INCLUDED
SUBTOTAL-COILING DOORS&SHUTTERS $ -
8000 DOORS&WINDOWS FCI Constructors,Inc.Confidential Page 22
FCI Cost Worksheet 7/24/20141 UPDATED 7/;
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
II
8000 DOORS&WINDOWS FCI Constructors,Inc.Confidential Page 23
FCI Cost Worksheet 7/24120141 UPDATED 7/;
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
080000 DOORS&WINDOWS
ARCHITECTURAL WINDOW&
084105 ALUMINUM ENTRANCES&STOREFRONT DOORS
EXTERIOR ALUMINUM/GLASS STOREFRONT
SYSTEM-MFG STD EXTRUSIONS-ANODIZED
FIN. SF 133.44 $ 41.83 SF $ 37,800
ALUMINUM FRAMED/GLAZED CURTAINWALL-
ANODIZED FINISH!1"INSUL GLASS 6'MULLION FRAMES SF 560.00 $ 73.25 SF INCLUDED
EXTERIOR ALUM/GLASS ENTRY DOORS-3'X
7'-MED STILE EA 2.00 $ 1,465.50 /EA INCLUDED
DEFLECTION COMPENSATION HEAD
CHANNELS N/A-EXCLUDED LF - $ - LF $ -
ALUM STOREFRONT DOOR HARDWARE EA 2.00 $ 1,600.00 EA INCLUDED
TEMP WEATHER ENCLOSURES-RHINOCLOTH SF 693.44 $ 0.94 SF $ 652
SUBTOTAL- ALUM ENTRANCES&STOREFRONTS $ 38,452
ARCHITECTURAL WINDOW&
085110 ALUMINUM WINDOWS DOORS
ALUMINUM PASS-THRU WINDOWS MECHANIC'S OFFICE EA 1.00 $ 977.00 /EA INCLUDED
SUBTOTAL-ALUMINUM WINDOWS $ -
EVERGREEN CONSTRUCTION
087150 FINISH HARDWARE SPECIALTIES
DOOR HARDWARE-HM/WOOD DOOR
OPENINGS(LABOR W/DOOR INSTALLATION) EA 25.00 $ 550.00 EA INCLUDED
ADD FOR PANIC/EXIT HARDWARE EA 3.00 $ 600.00 EA INCLUDED
ADD FOR ELECTRONIC HARDWARE W/SECURITY SYSTEM EA - $ 1,400.00 EA $ -
SUBTOTAL-FINISH HARDWARE $ .
ARCHITECTURAL WINDOW&
088010 GLASS&GLAZING DOORS
GLAZE HM/HPDL DOORS EA 11.00 $ 107.84 EA INCLUDED
SUBTOTAL-GLASS&GLAZING $ .
ARCHITECTURAL WINDOW&
088115 TRANSLUCENT GLAZED WALL SYSTEM DOORS
TRANSLUCENT GLAZED WALL ASSEMBLY KALWALL OR EQUAL SF 592.00 $ 51.83 SF $ 33,220
TEMP WEATHER ENCLOSURES-RHINOCLOTH SF 592.00 $ 0.94 SF $ 556
SUBTOTAL- TRANSLUCENT GLAZED WALL SYSTEM $ 33,776
089900 ALUMINUM CURTAINWALL SYSTEM
ALUMINUM FRAMED/GLAZED CURTAINWALL- LOW RISE CW SYSTEM-6°
ANODIZED FINISH/1"INSUL GLASS MULLION FRAMES SF - $ 73.25 SF $ -
TEMP WINDOW ENCLOSURES-RHINO CLOTH SF - $ 0.89 SF $ -
EXTERIOR ALUM/GLASS ENTRY DOORS-3'X
7'-MED STILE EA - $ 1,465.50 /EA $ -
SUBTOTAL-ALUMINUM CURTAINWALL SYSTEM $
080000 DOORS&WINDOWS-TOTALS $ 140,026
COST PER SF $ 5.38
8000 DOORS&WINDOWS FCI Constructors,Inc.Confidential Page 24
•
FCI Cost Worksheet 7/24/2014/UPDATED 7/;
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
080000 DOORS&WINDOWS BID ALTERNATE#4
084105 ALUMINUM ENTRANCES&STOREFRONT
EXTERIOR ALUMINUM/GLASS STOREFRONT
SYSTEM-MFG STD EXTRUSIONS-ANODIZED
FIN. SF (560.00) $ 31.00 SF $ (1,400)
SUBTOTAL- ALUM ENTRANCES&STOREFRONTS $ (1,400)
8000 DOORS&WINDOWS FCI Constructors,Inc.Confidential Page 25
FCI Cost Worksheet 7/24/2014 I UPDATED 7/3'
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,060
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
090000 FINISHES
092510 DRYWALL&METAL SUPPORT FRAMING PEAK INTERIORS
EXTERIOR WALLS""""'"'""""'""""'"""'
EXTERIOR WALLS-4"STUDS"'"""`""" LOAD-BEARING ASSEMBLY SF 4,562.00
4"METAL TRACK-T&8-18 GA LF 848.00 $ 6.70 LF $ 249,493
4"METAL STUD FRAMING-16 GA/16"OC LF 3,024.00 $ 4.60 LF INCLUDED
6"METAL TRACK-T&0-14 GA LF 322.00 $ 8.40 LF INCLUDED
6"METAL STUD FRAMING-16 GA/16"OC LF 2,336.00 $ 6.49 LF INCLUDED
BOX HEADER ASSEMBLIES LF 80.00 $ 10.50 LF INCLUDED
ADDITIONAL SUPPORT©SILLS LF 32.00 $ 7.50 LF INCLUDED
BEADS/TRIM LF 15.00 $ 2.95 LF INCLUDED
22 GAGE SHEAR WALL SHEATHING SF - $ 2.75 SF $ 4,000
1 1/2"INSULATION TO EXTERIOR WALLS W/072110 SF - $ 2.75 SF $ -
EXTERIOR GYPSUM SHEATHING-
DENSEGLASS OR EQUAL SF 4,562.00 $ 1.95 SF INCLUDED
EXTERIOR GYPSUM SHEATHING-
DENSEGLASS OR EQUAL BACK SIDE OF PARAPETS SF 644.00 $ 1.95 SF INCLUDED
SIDE SF 3,648.00 $ 1.19 SF INCLUDED
RI9 BATT INSULATION TO EXTERIOR WALLS W/072110 SF - $ 0.85 SF WANSULATION
TAPE&FINISH DW SF 3,648.00 $ 0.84 SF INCLUDED
INTERIOR PARTITIONS"""`""""
DRYWALL PTN-LOAD BEARING WALLS-14' FULL HEIGHT WALLS-1 LAYER
H EACH SIDE-W/SAB INSULATION LF 107.00
4"MTL TRACK-T&B-18 GAGE LF 214.00 $ 5.65 LF INCLUDED
4"MTL STUD FRAMING-16 GAGE LF 1,498.00 $ 5.00 LF INCLUDED
BEADS/TRIM LF 107.00 $ 2.95 LF INCLUDED
5/8"DW TO STUDS SF 2,996.00 $ 1.04 SF INCLUDED
ACOUSTIC INSULATION TO WALLS W/072110 SF - $ 0.86 SF $ -
TAPE&FINISH DW TO CEILING HT SF 2,140.00 $ 0.70 SF INCLUDED
DRYWALL PTN-LOAD BEARING WALLS-14' FULL HEIGHT WALLS-1 LAYER
H EACH SIDE-W/SAB INSULATION LF 25.00
6"MTL TRACK-T&B-14 GAGE LF 50.00 $ 8.25 LF INCLUDED
6"MTL STUD FRAMING-16 GAGE LF 350.00 $ 7.00 LF INCLUDED
BEADS/TRIM LF 25.00 $ 2.95 LF INCLUDED
5/8"DW TO STUDS SF 700.00 $ 1.04 SF INCLUDED
ACOUSTIC INSULATION TO WALLS W/072110 SF - $ 0.86 SF $ -
TAPE&FINISH DW TO CEILING HT SF 500.00 $ 0.70 SF INCLUDED
FULL HEIGHT WALLS-1 LAYER
DRYWALL PTN-DEMSING WALLS-14'H EACH SIDE-W/SAB INSULATION LF 304.00
4"MTL TRACK-T&B LF 608.00 $ 5.43 LF INCLUDED
ADD FOR SLIP/DEFLECTION TRACK LF 304.00 $ 2.90 LF INCLUDED
4"MTL STUD FRAMING LF 4,256.00 $ 3.76 LF INCLUDED
BEADS/TRIM LF 304.00 $ 2.95 LF INCLUDED
5/8"DW TO STUDS SF 8,512.00 $ 1.04 SF INCLUDED
ACOUSTIC INSULATION TO WALLS W/072110 SF - $ 0.86 SF $ -
TAPE&FINISH DW TO CEILING HT SF 6,080.00 $ 0.70 SF INCLUDED
FULL HEIGHT WALLS-1 LAYER
DRYWALL PTN-DEMSING WALLS-14'H EACH SIDE-W/SAB INSULATION LF 31.00
6"MTL TRACK-T&B LF 62.00 $ 6.10 LF INCLUDED
ADD FOR SLIP/DEFLECTION TRACK LF 31.00 $ 3.32 LF INCLUDED
6"MTL STUD FRAMING LF 434.00 $ 4.65 LF INCLUDED
BEADS/TRIM LF 31.00 $ 2.95 LF INCLUDED
518"DW TO STUDS SF 868.00 $ 1.04 SF INCLUDED
ACOUSTIC INSULATION TO WALLS W/072110 SF - $ 0.86 SF $ -
TAPE&FINISH DW TO CEILING HT SF 620.00 $ 0.70 SF INCLUDED
DRYWALL PTN-FURRING OF CMU WALLS- FULL HEIGHT WALLS-1 LAYER 1
14'H SIDE-W/SAB INSULATION LF 95.00
4"MTL TRACK-T&B LF 190.00 $ 5.43 LF INCLUDED
ADD FOR SLIP/DEFLECTION TRACK LF 95.00 $ 2.90 LF INCLUDED
4"MTL STUD FRAMING LF 1,330.00 $ 3.76 LF INCLUDED
BEADS/TRIM LF 95.00 $ 2.95 LF INCLUDED
5/8"DW TO STUDS SF 1,330.00 $ 1.04 SF INCLUDED
9000 FINISHES FCI Constructors,Inc.Confidential Page 26
FCI Cost Worksheet 712412014/UPDATED 713•
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
ACOUSTIC INSULATION TO WALLS W/072110 SF - $ 0.86 SF $ -
TAPE&FINISH DW TO CEILING HT SF 950.00 $ 0.70 SF INCLUDED
090000 FINISHES
092510 DRYWALL&METAL SUPPORT FRAMING
FULL HEIGHT WALLS-1 LAYER
DRYWALL PM-CHASE WALLS-14'H EACH SIDE-W/SAB INSULATION LF 11.00
4"MTL TRACK-T&B LF 22.00 $ 5.43 LF INCLUDED
ADD FOR SLIP/DEFLECTION TRACK LF 11.00 $ 2.90 LF INCLUDED
4"MTL STUD FRAMING LF 154.00 $ 3.76 LF INCLUDED
BEADS/TRIM LF 11.00 $ 2.95 LF INCLUDED
5/8"DW TO STUDS SF 154.00 $ 1.04 SF INCLUDED
ACOUSTIC INSULATION TO WALLS W/072110 SF - $ 0.86 SF $ -
TAPE&FINISH DW TO CEILING HT SF 110.00 $ 0.70 SF INCLUDED
DRYWALL CEILINGS-SINGLE LAYER W/
BLACK IRON SUPPORT`""""'*' INTERIOR GYP BD CEILINGS
1 1/2"MAIN CARRIER CHANNELS LF 239.25 $ 4.48 LF INCLUDED
7/8"CROSS RUNNERS LF 362.50 $ 3.40 LF INCLUDED
5/8"DW TO CEILINGS SF 725.00 $ 1.62 SF INCLUDED
TAPE&FINISH DW CEILINGS SF 725.00 $ 0.59 SF INCLUDED
CF FRAMED HEADERS LF 88.00 $ 10.60 LF INCLUDED
DRYWALL CEILINGS-SINGLE LAYER FURRED
TO U/S ROOF STRUCTURE********* INTERIOR GYP BD CEILINGS
7/8"HAT CHANNELS LF 212.50 $ 3.40 LF INCLUDED
5/8"DW TO CEILINGS SF 425.00 $ 1.62 SF INCLUDED
TAPE&FINISH DW CEILINGS SF 425.00 $ 0.59 SF INCLUDED
DRYWALL DUCT ENCLOSURE-RATED**"""" SF $ - SF
4"MTL TRACK N/A-EXCLUDED LF - $ 6.36 LF $ -
4"MTL STUD FRAMING N/A-EXCLUDED LF - $ 4.40 LF $ -
CORNER BEADS N/A-EXCLUDED LF - $ 2.67 LF $ -
5/8"DW TO FASCIAS/SOFFITS N/A-EXCLUDED SF - $ 1.50 SF $ -
TAPE&FINISH DW FASCIAS/SOFFITS N/A-EXCLUDED SF - $ 0.90 SF $ -
MISCELLANEOUS DRYWALL/INTERIORS ITEMS. *
DRYWALL COLUMN COVERS-INTERIOR N/A-EXCLUDED EA - $ 268.00 EA $ -
SKYLIGHT WELLS N/A-EXCLUDED LF - $ 49.00 LF $ •
CEILING BULKHEADS LF 6.00 $ 38.60 LF INCLUDED
ADD FOR LEVEL 5 FINISH ON EXPOSED
SURFACES N/A-EXCLUDED SF - $ 1.03 SF $ -
ADD FOR TILE BACKER BOARD AT TOILET
ROOMS SF 790.00 $ 1.00 SF INCLUDED
ADD FOR MOLD RESISTANT GYP BOARD SF 1,284.00 $ 0.65 SF INCLUDED
FRP WALL PANELS-60"H WAINSCOT JANITORS'CLOSETS LS 1.00 $ 1,500.00 LS $ 1,500
ACOUSTICAL SEALANTS/TRIM CLOSURES LS 1.00 $ - LS $ 9,800
SHOP DWGS FOR COLD FORMED METAL
FRAMING EXCLUDED LS 1.00 $ - LS $ -
TEMPORARY HEAT FOR INTERIORS MO 2.00 $ 12,500.00 MO $ 25,000
LAYOUT/COORDINATION-INTERIORS HRS 80.00 $ 54.00 HRS $ 4,320
CLEANUP/FINAL CLEANING HRS 100.00 $ 39.00 HRS $ 3,900
DUMPSTERS PULLS 3.00 $ 1,000.00 PULL$ 3,000
SUBTOTAL-DRYWALL&METAL SUPPORT FRAMING $ 301,013
093150 CERAMIC TILE
PORC CERAMIC FLOOR TILE-THIN SET TOILET ROOMS SF 388.00 $ 15.00 SF $ 23,300
PORC CERAMIC TILE BASE-COVED-
ADHESIVE SET TOILET ROOMS LF 158,00 $ 16.23 LF INCLUDED
PORCELAIN CERAMIC WALL TILE-ADHESIVE
SET-60"WAINSCOT TOILET ROOMS SF 790.00 $ 14.50 SF INCLUDED
ADD FOR EPDXY MORTAR&GROUT N/A-EXCLUDED SF - $ 4.33 SF $ -
ADD FOR ANTI-FRACTURE MEMBRANE TOILET ROOMS SF 388.00 $ 4.40 SF INCLUDED
9000 FINISHES FCI Constructors,Inc.Confidential Page 27
FCI Cost Worksheet 7/2412014/UPDATED 7/3•
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
SUBTOTAL-CERAMIC TILE $ 23,300
095110 ACOUSTICAL CEILINGS PEAK INTERIORS
ACT CEILINGS-2'X 2'-EXPOSED TEE GRID-
DIRECT HUNG FROM STRUCT. TEGULAR EDGE TILE SF 636.00 $ 4.05 SF INCLUDED
ACT CEILINGS-2'X 4'-EXPOSED TEE GRID-
DIRECT HUNG FROM STRUCT. TEGULAR EDGE TILE SF 1,890.00 S 3.90 SF INCLUDED 1
RECESSED SHADE POCKET PAINTED STEEL LF 65.00 $ 22.00 LF $ 1,430
SUBTOTAL-ACOUSTICAL CEILINGS $ 1,430
090000 FINISHES
096600 ACOUSTICAL TREATMENT
ACOUSTICAL WALL PANELS N/A-EXCLUDED SF - $ 27.50 SF S -
SUBTOTAL-ACOUSTICAL TREATMENT $ -
086510 RESILIENT FLOOR&BASE
VCT FLOOR TILE SF 660.00 $ 2.58 SF $ 1,706
LINOLEUM SHEET FLOORING N/A-EXCLUDED SF - $ 6.77 SF $ -
FORBO FLOOR TILE SF 146.00 $ 8.00 SF $ 1,168
4"H RUBBER BASE-COVED LF 1,094.00 $ 2.40 LF $ 2,826
FLOOR PREP-ALLOW 25% SF 201.50 $ 0.60 SF $ 121
SUBTOTAL-RESILIENT FLOORING $ 5,620
096810 CARPET
GLUEDOWN SY 222.48 $ 40.00 SY $ 8,899
SUBTOTAL-CARPET $ 8,899
099000 PAINTING&WALLCOVERING WBS COATINGS
PAINT DRYWALL PTNS-LATEX-SINGLE
COLOR SF 7,902.00 $ 0.79 SF $ 35,288
PAINT CMU PTNS-LATEX SF 4,512.00 $ 0.96 SF INCLUDED
PAINT DRYWALL CEILINGS-LATEX-SINGLE
COLOR SF 1,150.00 $ 1.29 SF INCLUDED
PAINT DRYWALL PTNS-EPDXY-SINGLE
COLOR N/A-EXCLUDED SF - $ 1.21 SF $ -
PAINT CMU PTNS-EPDXY SF - $ 1.38 SF INCLUDED
PAINT EXPOSED STEEL STRUCTURE SF 2,052.00 $ 0.77 SF INCLUDED
PAINT HM DOOR FRAMES EA 22.00 $ 60.80 EA INCLUDED
PAINT HM DOORS EA 10.00 $ 56.50 EA INCLUDED
PAINT EXPOSED COLUMNS TO 10 FTAFF EA 22.00 $ 244.00 EA INCLUDED
PAINT PIPE BOLLARDS EA - $ 55.50 EA $ -
PAINT EXPOSED STEEL TRANSFER BEAM LF 26.00 $ 9.13 LF INCLUDED
SEALER/GRAFITTI GUARD-EXTERIOR CMU
WALLS ONLY SF 2,805.00 $ 1.35 SF INCLUDED
SEALER/GRAFITTI GUARD-EXPOSED
EXTERIOR CONC WALLS SF 1,792.00 $ 1.35 SF INCLUDED
STAIN&SEALER-COMPOSITE PLANK SIDING SF - $ 1.80 SF $ -
STAIN&SEALER-WOOD BEAMS&T&G
WOOD EXTER SOFFITS SF 224.00 $ 1.80 SF INCLUDED
MISC TOUCHUP PAINTING HRS 48.00 $ 57.00 HRS $ 2,736
WALLCOVERING $ 38,024
099100 PAVEMENT MARKINGS
LINE STRIPPING/PAVEMENT MARKINGS-
INTERIOR APPARATUS BAYS N/A-EXCLUDED SF - $ 0.22 SF $ -
SUBTOTAL-PAVEMENT MARKINGS $ -
9000 FINISHES FCI Constructors,Inc.Confidential Page 28
FCI Cost Worksheet 7/2412014/UPDATED 713'
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
099650 CONCRETE FLOOR SEALING WBS COATINGS
CHEM RESISTANT FLOOR COATING SF - $ 0.66 SF $ -
STANDARD HOUSEKEEPING FLOOR SEALER INTERIOR APPARATUS BAYS SF 22,102.00 $ 0.75 SF $ 16,242
SUBTOTAL-CONCRETE FLOOR SEALING $ 16,242
099665 CONCRETE FLOOR STAIN
ACID FLOOR STAIN SF 155.00 $ 156.20 SF $ 1,882
SUBTOTAL-CONCRETE FLOOR STAIN $ 1,882
090000 FINISHES-TOTALS $ 396,410
COST PER SF $ 15.22
9000 FINISHES FCI Constructors,Inc.Confidential Page 29
FCI Cost Worksheet 7124/2014/UPDATED 713'
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
090000 FINISHES BID ALTERNATE#2
099000 PAINTING&WALLCOVERING
PAINT EXPOSED STEEL STRUCTURE STORAGE PLATFORM SF 704.00 $ - SF $ 3,000
WALLCOVERING _ $ 3,000
9000 FINISHES FCI Constructors,Inc.Confidential Page 30
FCI Cost Worksheet 7/24/2014/UPDATED 713
Project: EAGLE COUNTY REGIONAL AIRPORT.SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
100000 SPECIALTIES
101000 VISUAL DISPLAY BOARDS
MARKERBOARDS-10'X 4' N/A-EXCLUDED EA - $ 550.00 EA $ -
TACK BOARD-4'X 4' N/A-EXCLUDED EA - $ 240.00 EA $ -
SUBTOTAL-VISUAL DISPLAY BOARDS $ -
101505 TOILET PARTITIONS SIMPSON&SIMPSON
TOILET PTNS-FLR MTD/OH BRACED-STEEL-
BAKED ENAMEL FIN EA 1.00 $ 880.00 EA $ 7,195
TOILET PTNS-HC-FLR MTD/OH BRACED-
STEEL-BAKED ENAMEL FIN EA 2.00 $ 1,060.00 EA INCLUDED
URINAL SCREENS-WALL MTD-STEEL-BAKED
ENAMEL FIN EA 1.00 $ 250.00 EA INCLUDED
SUBTOTAL-TOILET PARTITIONS $ 7,195
102600 WALL&CORNER PROTECTION
CORNER GUARDS-48"STAINLESS STEEL-
SURF MOUNTED N/A-EXCLUDED EA - $ 52.00 EA $ -
SUBTOTAL-WALL&CORNER PROTECTION $ -
103510 FLAGPOLES
20 FT TAPERED FLAGPOLE-EXPOSED
HALYARD N/A-EXCLUDED LS LS $ -
EXCAV/SET ANCHOR
SLEEVE/CONCRETE/ERECTION N/A-EXCLUDED EA $ 984.00 EA $ -
SUBTOTAL-FLAGPOLES $ -
104010 IDENTIFYING DEVICES(SIGNAGE) FCI CONSTRUCTORS
INTERIOR ROOM SIGNS FURNISH 8 INSTALL EA 21.00 $ 74.80 EA $ 1,671
WALL MOUNTED LETTERING-NON
ILLUMINATED/CAST ALUM-18"HIGH N/A-EXCLUDED EA - $ 180.00 EA $ -
WALL MOUNTED LETTERING-NON
ILLUMINATED/CAST ALUM-12"HIGH N/A-EXCLUDED EA - $ 160.00 EA $ -
WALL MOUNTED LETTERING-NON
ILLUMINATED/CAST ALUM-8"HIGH N/A-EXCLUDED EA - $ 101.00 EA $ -
METAL CLAD BACKING PLATES-EXTERIOR
SIGN PANELS N/A-EXCLUDED SF - $ 46.00 SF $ -
BUILDING DEDICATION PLAQUE EA 1.00 $ 1,240.00 EA $ 1,240
BUILDING DIRECTORY N/A-EXCLUDED EA - $ 795.00 EA $ -
SUBTOTAL-INDENTIFYING DEVICES $ 2,811
104420 METAL LOCKERS
METAL LOCKERS-PAINTED STEEL STAFF LOCKERS EA 8.00 $ 255.00 EA $ 2,040
LOCKER BENCH 3'6"LONG-BUILT IN EA 1.00 $ 640.00 EA $ 640
SUBTOTAL-METAL LOCKERS $ 2,680
105205 FIRE EXTINGUISHERS&CABS FCI CONSTRUCTORS
FIRE EXTINGUISHERS AS SHOWN EA 3.00 $ 85.00 EA $ 255
FIRE EXTINGUISHER MOUNTING BRACKETS AS SHOWN EA 3.00 $ 55.00 EA $ 165
FIRE EXTINGUISHER CABINETS AS SHOWN EA - $ 185.00 EA $ -
FIRE EXTINGUISHERS ALLOWANCE FOR ADMIN AREA EA 2.00 $ 85.00 EA $ 170
FIRE EXTINGUISHER CABINETS ALLOWANCE FOR ADMIN AREA EA 2.00 $ 185.00 EA $ 370
10000 SPECIALTIES FCI Constructors,Inc.Confidential Page 31
FCI Cost Worksheet 7/24/2014/UPDATED 713
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
SUBTOTAL-FIRE EXTINGUISHERS&CABINETS $ 960
10000 SPECIALTIES FCI Constructors,Inc.Confidential Page 32
FCI Cost Worksheet 7/24/2014/UPDATED 713
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
100000 SPECIALTIES
106120 OPERABLE WALLS
OPERABLE WALL ASSEMBLY-MANUAL
OPERATED-VINYL FACED FABRIC N/A-EXCLUDED LF - $ 516.00 LF $ -
SUBTOTAL-OPRABLE WALLS $ -
108010 TOILET ROOM ACCESSORIES SIMPSON&SINPSON
TOILET PAPER HOLDER EA 4.00 $ 68.00 EA INCLUDED
HANDICAP BRAG BARS EA 12.00 $ 109.00 EA INCLUDED
LIQUID SOAP DIPSENSER EA 5.00 $ 70.00 EA INCLUDED
SEAT COVER DISPENSER EA 4.00 $ 75.00 EA INCLUDED
PAPER TOWEL DISPENSERNVAST
RECEPTACLE TOILET RMS EA 3.00 $ 447.00 EA INCLUDED
PAPER TOWEL DISPENSER EMPLOYEE BREAK RM EA 1.00 $ 91.00 EA INCLUDED
SANITARY NAPKIN DISPENSER N/A-EXCLUDED EA - $ 225.00 EA $ -
SANITARY NAPKIN DISPOSAL EA 2.00 $ 70.00 EA INCLUDED
FRAMED MIRROR-24"X 36" EA 1.00 $ 195.00 EA INCLUDED
FRAMED MIRROR-24"X 48" EA 1.00 $ 205.00 EA INCLUDED
FRAMED MIRROR-54"X 36" EA 2.00 $ 420.00 EA INCLUDED
ELECTRIC HAND DRYER N/A-EXCLUDED EA - $ 540.00 EA $ -
JANITOR'S MOP RACK EA 1.00 $ 210.00 EA INCLUDED
UNDERCOUNTER LAV GUARD N/A-EXCLUDED EA - $ 70.00 EA $ -
SHOWER RODS EA 1.00 $ 52.00 EA INCLUDED
HC GRAB BARS-SHOWERS EA 2.00 $ 95.00 EA INCLUDED
TOWEL/CLOTHES HOOKS EA 8.00 $ 30.00 EA INCLUDED
FOLD-DOWN SHOWER SEATS EA 1.00 $ 275.00 EA INCLUDED
SUBTOTAL-TOILET ROOM ACCESSORIES $ -
109950 MISCELLANEOUS SPECIALTIES FCI CONSTRUCTORS
KNOX BOX EA 1.00 $ 717.12 EA $ 717
SUBTOTAL-MISCELLANEOUS SPECIALTIES $ 717
10000 SPECIALTIES-TOTALS $ 14,363
COST PER SF $ 0.5$
10000 SPECIALTIES FCI Constructors,Inc.Confidential Page 33
FCI Cost Worksheet 7/24/2014/UPDATED 7/3
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
110000 EQUIPMENT
111119 MAINTENANCE EQUIPMENT
VEHICLE MAINT EQUIPMENT N/A-EXCLUDED LS - $ - LS $ -
SUBTOTAL-MAINTENANCE EQUIPMENT $ -
111120 WASH EQUIPMENT
HOTSEY PRESSURE WASHER N/A-OWNER FF&E LS - $ 13,000.00 LS $ -
MOBILE PLATFORM LIFTS N/A-OWNER FF&E LS - $ 10,000.00 LS $ -
SUBTOTAL-WASH EQUIPMENT $ -
111190 FUEL DISPENSING EQUIPMENT
FUEL DISPENSING EQUIPMENT N/A-EXCLUDED LS - $ - LS $ -
SUBTOTAL-FUEL DISPENSING EQUIPMENT $ - 1
111310 AUDIO VISUAL EQUIPMENT
PROJECTION SCREEN-CLG MTD-ELEC
OPERATED-7'X 7'W N/A-EXCLUDED EA - $ 2,230.00 EA $ -
FLAT SCREEN TV MONITORS-BRACKET MTD N/A-OWNER FF&E EA - $ 660.00 EA $ -
FLAT SCREEN TV MONITOR MOUNTS-CLG
MTD N/A-OWNER FF&E EA - $ 285.00 EA $ -
AV PROJECTOR-CEILING MOUNTS N/A-OWNER FF&E EA - $ 245.00 EA $ -
AV EQUIPMENT N/A-OWNER FF&E LS - $ 25,000.00 LS $ -
SUBTOTAL-AUDIO VISIUAL EQUIPMENT $ -
114550 RESIDENTIAL APPLIANCES FCI CONSTRUCTORS
OFCI REFRIGERATOR EA 1.00 $ 120.00 EA $ 120
OFCI DISHWASHER-UNDERCOUNTER EA 1.00 $ 180.00 EA $ 180
OFCI MICROWAVE OVEN-1 CF CAP EA 1.00 $ 60.00 EA $ 60
OFCI COFFE MAKER- EA 1.00 $ 60.00 EA $ 60
STOVE/RANGE N/A-EXCLUDED EA - $ 150.00 EA $ -
DUCTLESS EXHAUST HOOD N/A-EXCLUDED EA - $ 120.00 EA $ -
OFCI WASHER EA 1.00 $ 120.00 EA $ 120
OFCI CLOTHES DRYER EA 1.00 $ 120.00 EA $ 120
SUBTOTAL-RESIDENTIAL APPLIANCES $ 660
110000 EQUIPMENT-TOTALS $ 660
COST PER SF $ 0.03
11000 EQUIPMENT FCI Constructors,Inc.Confidential Page 34
FC1 Cost Worksheet 7124/2014/UPDATED 7/1
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
120000 FURNISHINGS
124840 FLOOR MATS AND FRAMES
ENTRY MATS-RECESSED PEDIMAT N/A-EXCLUDED SF - $ 29.32 SF $ -
SUBTOTAL-FLOOR MATS $ -
1249110 WINDOW TREATMENTS
MANUAL ROLLER SHADES SF - $ 20.75 SF $ -
BLACK-OUT SHADES-MAUNAL OPER N/A-EXCLUDED SF - $ 21.00 SF $ -
SUBTOTAL-WINDOW TREATMENTS $ -
120000 FURNISHINGS-TOTALS $ -
COST PER SF $ -
BID ALTERNATE#3
1249110 WINDOW TREATMENTS AMABASSADOR BUNDS&SHUTTER
TRAINING ROOM&OPEN OFFICE
MANUAL ROLLER SHADES ONLY SF 372.00 $ 20.75 SF $ 3,766
SUBTOTAL-WINDOW TREATMENTS $ 3,766
$ 0.14 SF
120000 FURNISHINGS-TOTALS $ 3,766
12000 FURNISHINGS FCI Constructors,Inc.Confidential Page 35
FCI Cost Worksheet 7/24/2014/UPDATED 7r
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
130000 SPECIAL CONSTRUCTION
132710 PRE-ENGINEERED METAL BUILDINGS
PRE-ENGINEERED METAL BUILDING-FURNISH&DELIVER
METAL BUILDING-MAIN FRAMES,COLUMNS,
END WALLS-PRIME PTD-FURNISH HIGH BAY APPARATUS BAYS SF 20,194.00 $ 11.00 SF $ 837,137
ROOF PURLINS-12"DEEP-36"OC HIGH BAY APPARATUS BAYS LF 8,021.20 $ 2.85 LF INCLUDED
BRACING STRUTS EVERY3RDPURLIN EA 192.72 $ 5.00 EA INCLUDED
CABLE BRACES HIGH BAY APPARATUS BAYS EA 8.00 $ 450.00 EA INCLUDED
EXTERIOR WALL FRAMING-CF PURLINS
PRIME PTD-6"DEEP-48"OC BI-PASS GIRTS LF 3,864.58 $ 2.10 LF INCLUDED
EXTERIOR SOFFIT FRAMING-CF PURLINS
PRIME PTD LF 388.30 $ 4.00 LF INCLUDED
ROOF TOP EQUIPMENT CURBS LS 1.00 $ 3,500.00 LS $ 9,500
EXTERIOR WALL PANELS-CONCEALED
FASTENERS-FACTORY PAINT FIN-24 GA SF 14,053.00 $ 2.00 SF INCLUDED
INTERIOR LINER WALL PANELS-CONCEALED
FASTENERS-FACTORY PAINT FIN-26 GA TO 14'AFF SF 5,264.00 $ 1.65 SF INCLUDED
STANDING SEAM ROOF PANELS-22 GA PTD
STEEL-FACTORY FIN-MAIN ROOF HIGH BAY APPARATUS BAYS SF 21,333.00 $ 4.65 SF INCLUDED
INTERIOR LINER CEILING PANELS-EXPOSE
FASTENERS-FACTORY PAINT FIN-26 GA N/A-EXCLUDED SF - $ 1.40 SF $ -
EXTERIOR PERIMETER FASCIA TRIM 24GA PREFORMED/PAINTED LF 672.10 $ 3.50 LF INCLUDED
EXTERIOR PERIMETER SOFFIT PANELS 24 GA PREFORMED/PAINTED SF 646.80 $ 3.50 SF INCLUDED
SNOW GUARDS-2 LINE PTD STEEL AS SHOWN LF 501.00 $ 16.00 LF INCLUDED
SNOW GUARDS-2 LINE PTD STEEL ADD FOR ADD'L NEEDED LF 501.00 $ 16.00 LF INCLUDED
PERIMETER GUTTERS&DOWNSPOUTS N/A-EXCLUDED LF - $ - LF $ -
EXIT DOOR CANOPY STRUCTURE EA 3.00 $ 1,120.00 EA INCLUDED
THERMAL BLOCK INSULATION-ROOF PURLINS FURNISH LF 8,021.20 $ 3.00 LF INCLUDED
THERMAL BLOCK INSULATION-WALL GIRTS FURNISH LF 3,864.58 $ 3.00 LF INCLUDED
SUBTOTAL•MATERIALS FURNISHED&DEUVERED $ 840,637
PRE-ENGINEERED METAL BUILDING-ERECTION W/INSTALL OF INSULATION
METAL BUILDING ERCTION-STRUCTURE MAIN FRAMES/END WALLS DY 18.00 $ 5,650.00 DY INCLUDED
INSTALL ROOF PURLINS HIGH BAY APPARATUS BAYS LF 8,021.20 $ 2.34 LF INCLUDED
INSTALL WALL GIRTS HIGH BAY APPARATUS BAYS LF 3,864.58 $ 2.08 LF INCLUDED
INSTALL WALL PANELS HIGH BAY APPARATUS BAYS SF 14,053.00 $ 1.17 SF INCLUDED
INSTALL WALL LINER PANELS HIGH BAY APPARATUS BAYS SF 5,264.00 $ 1.17 SF INCLUDED
INSTALL ROOF PANELS HIGH BAY APPARATUS BAYS SF 21,333.00 $ 1.50 SF INCLUDED
INSTALL CEILING LINER PANELS N/A-EXCLUDED SF - $ 2.34 SF $ -
INSTALL EXTERIOR PERIMETER FASCIA TRIM 24GA PREFORMED/PAINTED LF 672.10 $ 3.13 LF INCLUDED
INSTALL EXTERIOR PERIMETER SOFFIT
PANELS 24 GA PREFORMED/PAINTED SF 646.80 $ 3.13 SF INCLUDED
INSTALL SNOW GUARDS-2 LINE PTD STEEL AS SHOWN LF 501.00 $ 7.50 LF INCLUDED
INSTALL SNOW GUARDS-2 LINE PTD STEEL ADD FOR ADD'L NEEDED LF 501.00 $ 7.50 LF INCLUDED
EXIT DOOR CANOPY STRUCTURE EA 3.00 $ 1,200.00 EA INCLUDED
EXTERIOR WALL INSULATION-R13 BATTS
VINYL FABRIC FACED-2 LAYERS INSTALL SF 28,106.00 $ 0.59 SF INCLUDED
ROOF INSULATION-R19 BATTS VINYL FABRIC
FACED INSTALL SF 21,333.00 $ 1.17 SF INCLUDED
ROOF INSULATION-R13 BATTS VINYL FABRIC
FACED INSTALL SF 21,333.00 $ 0.90 SF INCLUDED
THERMAL BLOCK INSULATION-ROOF PURUNS INSTALL LF 8,021.20 $ 1.00 LF INCLUDED
THERMAL BLOCK INSULATION-WALL GIRTS INSTALL LF 3,864.58 $ 1.00 LF INCLUDED
SMALL TOOLS&SAFETY LS 1.00 $ 2,200.00 LS INCLUDED
MANLIFTS LS 1.00 $ 8,000.00 LS INCLUDED
130000 SPECIAL CONSTR FCI Constructors,Inc.Confidential Page 36
FCI Cost Worksheet 7/24/2014/UPDATED 7/:
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
SUBTOTAL-METAL BUILDING ERECTION $ -
130000 SPECIAL CONSTRUCTION
132710 PRE-ENGINEERED METAL BUILDINGS
PRE-ENGINEERED METAL BUILDING INSULATION-FURNISH&DELIVER
EXTERIOR WALL INSULATION-R13 BATTS
VINYL FABRIC FACED FURN&DEL SF 28,106.00 $ 0.45 SF INCLUDED
ROOF INSULATION-R19 BATTS VINYL FABRIC
FACED FURN&DEL SF 21,333.00 $ 1.10 SF INCLUDED
ROOF INSULATION-R13 BATTS VINYL FABRIC
FACED FURN&DEL SF 21,333.00 $ 0.35 SF INCLUDED
MISC THERMAL BREAK INSULATION LS 1.00 $ 1,500.00 LS INCLUDED
SUBTOTAL-METAL BUILDING INSULATION-FURNISH $ -
LAYOUT/COORDINATION-BLDG STRUCTURE&
ENCLOSURE HR 200.00 $ 54.00 HR $ 10,800
CLEANUP LABOR-BLDG STRUCTURE&
ENCLOSURE HR 200.00 $ 38.56 HR $ 7,712
DUMPSTERS EA 5.00 $ 1,000.00 EA $ 5,000
POST AWARD SCOPE CHANGES LS 1.00 $ 15,000.00 LS $ 15,000
ACCEPTANCE OF PEMB BID PKG BID
ALTERNATE 3A LS (1.00) $ 34,813.00 LS $ (34,813)
SUBTOTAL-PRE ENGINEERED METAL BUILDINGS $ 3,699
130000 SPECIAL CONSTRUCTION-TOTALS $ 844,336
COST PER SF $ 32.41
130000 SPECIAL CONSTR FCI Constructors,Inc.Confidential Page 37
FCI Cost Worksheet 7124120141 UPDATED 713
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
210000 FIRE SUPPRESSION SYSTEMS
215300 FIRE PROTECTION WORK CURTIS ENGINEERING
FIRE SPRINKLERS-WET PIPE SYSTEM+
STANDPIPES ADMINISTRATION AREA SF 5,611.00 $ 2.85 SF $ 68,900
FIRE SPRINKLERS-WET PIPE SYSTEM+
STANDPIPES INTERIOR APPARATUS BAYS SF 20,439.00 $ 2.90 SF INCLUDED
FIRE SPRINKLERS-ADD FOR DRY TYPE
SYSTEM SF 22,094.00 $ 1.00 SF INCLUDED
FIRE SPRINKLERS-FREEZE PROOF SYSTEM-
EXTERIOR BUILDING OVERHANG SOFFITS SF - $ - SF INCLUDED
BOOSTER PUMP N/A-EXCLUDED LS - $ - LS $ -
JOCKEY PUMP N/A-EXCLUDED LS - $ - LS $ -
SUBTOTAL-FIRE PROTECTION WORK $ 68,900
$ 2.64 SF
210000 FIRE SUPPRESSION-TOTALS $ 68,900
COST PER SF $ 2.64
BID ALTERNATE#5
215300 FIRE PROTECTION WORK CUR71S ENGINEERING
FIRE SPRINKLERS-ADD FOR DRY TYPE
SYSTEM SF (22,094.00) $ 0.50 SF $ (9,300)
SUBTOTAL-FIRE PROTECTION WORK $ (9,300)
$ (0.36)SF
210000 FIRE SUPPRESSION-TOTALS $ (9,300)
BID ALTERNATE#6
215300 FIRE PROTECTION WORK CURTIS ENGINEERING
FIRE SPRINKLERS-ADD FOR DRY TYPE
SYSTEM ADD NITROGEN GENERATOR LS 1.00 $ 14,900.00 LS $ 14,900
SUBTOTAL-FIRE PROTECTION WORK $ 14,900
$ 0.67 SF
210000 FIRE SUPPRESSION-TOTALS $ 14,900
210000 FIRE SUPPRESSION FCI Constructors,Inc.Confidential Page 38
FCI Cost Worksheet 7/24/2014/UPDATED 7/3
Project: EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
22/230000 MECHANICAL
220000 PLUMBING
ADMINISTRATION WING SF 5,611.00 $ - SF $ 218,723
STORAGE/WORK APPARATUS BAYS SF 20,439.00 $ - SF INCLUDED
PLUMBING EQUIPMENT LS 26,050.00 $ - LS INCLUDED
DOMESTIC WATER PIPING LS 26,050.00 $ - LS INCLUDED
SANITARY SERVICE PIPING LS 26,050.00 $ - LS INCLUDED
VENT PIPING SF 26,050.00 $ - SF INCLUDED
WASH EQUIPMENT-ROUGH IN&SERVICES SF 26,050.00 $ - SF INCLUDED
MAINT EQUIPMENT-ROUGH IN&SERVICES SF 26,050.00 $ - SF INCLUDED
NAT GAS PIPING/RADIANT HEATERS SF 26,050.00 $ - SF INCLUDED
PLUMBING FIXTURES-W/TRIM SF 26,050.00 $ - SF INCLUDED
PLUMBING-SAND/OIL SEPERATOR SF 26,050.00 $ - SF INCLUDED
PLUMBING-PREFAB TRENCH DRAINS FURNISH LF 64.00 $ 60.00 LF INCLUDED
PLUMBING-PREFAB TRENCH DRAINS INSTALL LF 64.00 $ 21.00 LF INCLUDED
PLUMBING PIPING INSULATION SF 26,050.00 $ - SF INCLUDED
RADON GAS VENTING SYSTEM ALLOW-NOTHING SHOWN LS 1.00 $ 7,500.00 LS INCLUDED
1.5"WATER METER INSIDE MECH ROOM LS 1.00 $ 8,500.00 LS $ 8,500
LAYOUT/COORDINATION-PLUMBING WORK HRS 100.00 $ 54.00 HRS $ 5,400
TEST/FLUSH SANITIZE SYSTEMS LS 1.00 $ - LS INCLUDED
SEISMIC BRACING ALLOWANCE LS 1.00 $ 3,000.00 LS $ 3,000
SUBTOTAL-PLUMBING $ 235,623
$ 9.05 SF
230000 HVAC
ADMINISTRATION WING SF 5,611.00 $ 22.50 SF $ 405,540
STORAGE/WORK APPARATUS BAYS SF 20,439.00 $ 15.20 SF INCLUDED
HVAC EQUIPMENT SF 26,050.00 $ - SF INCLUDED
SHEET METAL-DUCTWORK SF 26,050.00 $ - SF INCLUDED
GRILLES/REGISTERS/DIFFUSERS SF 26,050.00 $ - SF INCLUDED
HYDRONIC HVAC PIPING SF 26,050.00 $ - SF INCLUDED
HVAC SYS-VEHICLE EXHAUST/CO2
MONITORS SF 26,050.00 $ - SF INCLUDED
IN-FLOOR RADIANT HEAT N/A-EXCLUDED SF - $ - SF INCLUDED
SNOW MELT SYSTEM EXTERIOR 8'CONC APRONS SF 1,700.00 $ 12.00 SF INCLUDED
SNOW MELT SYSTEM CONCRETE WALKS SF 325.00 $ 12.00 SF INCLUDED
HVAC INSULATION SF 26,050.00 $ - SF INCLUDED
HVAC CONTROLS SF 26,050.00 $ - SF INCLUDED
TEST&BALANCE SF 26,050.00 $ - SF INCLUDED
LAYOUT/COORDINATION-...HVAC WORK FIRS 173.00 $ 54.00 HRS $ 9,342
COMMISSIONING SF 26,050.00 $ - SF INCLUDED
SEISMIC BRACING ALLOWANCE LS 1.00 $ 4,000.00 LS $ 4,000
SUBTOTAL-HVAC $ 418,882
$ 16.08 SF
221230000 MECHANICAL-TOTALS $ 654,505
COST PER SF $ 25.12
22 23 PLUMBING&HVAC FCI Constructors,Inc.Confidential Page 39
FCI Cost Worksheet 7/24/2014 t UPDATED 7/3
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
22/230000 MECHANICAL BID ALTERNATE#1
220000 PLUMBING
RADON GAS VENTING SYSTEM LS (1.00) $ 7,500.00 LS $ (7,500)
SUBTOTAL-PLUMBING $ (7,500)
22 23 PLUMBING&HVAC FCI Constructors,Inc.Confidential Page 40
FC1 Cost Worksheet 7/24/2014/UPDATED 7/31
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,050
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
260000 ELECTRICAL
261000 ELECTRICAL WORK TRI-PHASE ELECTRIC
ADMINISTRATION WING SF 5,611.00 $ 23.10 SF $ 292,452
STORAGE/WORK APPARATUS BAYS SF 20,439.00 $ 13.80 SF INCLUDED
TEMP LIGHT&POWER SF - $ - SF $ 22,000
800A 480V SECONDARY SERVICE LS 1.00 $ - LS INCLUDED
MOTOR&EQUIPMENT CONNECTIONS LS 1.00 $ - LS INCLUDED
POWER DISTRIBUTION/BRANCH POWER LS 1.00 $ - LS INCLUDED
LIGHTING-FIXTURES-EXTERIOR LS 1.00 $ - LS INCLUDED
LIGHTING-FIXTURES-INTERIOR LS 1.00 $ - LS INCLUDED
LIGHTING CONTROLS LS 1.00 $ - LS INCLUDED
TRIM OUT/FINAL CONNECTIONS LS 1.00 $ - LS INCLUDED
FIRE ALARM SYSTEM LS 1.00 $ - LS INCLUDED
LIGHTNING PROTECTION SYSTEM LS 1.00 $ 18,000.00 LS INCLUDED
DATA/COMMUNICATIONS-CABLE MGT LS 1.00 $ - LS INCLUDED
DATA/COMMUNICATIONS-CONDUIT TO PHONE
CO PEDESTAL LF 2,200.00 $ 12.00 LF INCLUDED
ACCESS CONTROL LS 1.00 $ - LS INCLUDED
SECURITY SYSTEM-ROUGH IN ONLY LS 1.00 $ - LS INCLUDED
AV SYSTEM-ROUGH IN ONLY LS 1.00 $ - LS INCLUDED
STATE ELECTRICAL PERMIT LS 1.00 $ - LS INCLUDED
LAYOUT/COORDINATION-ELECTRICAL HRS 173.00 $ 54.00 HRS $ 9,342
EXTERIOR CANOPY GUTTERS&
HEAT TAPING EXTERIOR SURFACES DOWNSPOUTS LF 82.00 $ 15.00 LF INCLUDED
SEISMIC BRACING ALLOWANCE LS 1.00 $ 3,000.00 LS $ 3,000
SUBTOTAL-ELECTRICAL $ 326,794
260000 ELECTRICAL-TOTALS $ 326,794
COST PER SF $ 12.64
260000 ELECTRICAL FCI Constructors,Inc.Confidential Page 41
•
FCI Cost Worksheet 7/24/2014/UPDATED 7/31
Project EAGLE COUNTY REGIONAL AIRPORT-SNOW REMOVAL EQUIPMENT BUILDING(SRE) FINAL DESIGN GMP-REVISION#1
GYPSUM,COLORADO SF 26,060
UNIT OF UNIT PRICE
DESCRIPTION MEASURE QUANTITY TOTAL TOTAL
27/280000 LOW VOLTAGE/SPECIAL SYSTEMS
272010 COMMUNICATIONS&DATA CABLE&WIRE TRI-PHASE ELECTRIC
COMM/DATA SYSTEM-CABLE&VURE SF 26,050.00 $ 1.00 SF INCLUDED
SUBTOTAL-COMMUNICATIONS SYSTEMS $ -
282010 ACCESS CONTROL SYSTEMS TRI-PHASE ELECTRIC
ACCESS CONTROL-RELOCATE AT EXTERIOR
SECURITY GATE EA 1.00 $ 2,000.00 EA INCLUDED
ACCESS CONTROL-DEVICES&WARE MATRIX SYSTEM EA 5.00 $ 4,000.00 EA S 20,000
SUBTOTAL-ACCESS CONTROL $ 20,000
282020 SECURITY SYSTEMS TRI-PHASE ELECTRIC
SECURITY SYSTEM-DEVICES&WARE FIXED CAMERAS&CABLE EA 4.00 $ 2,000.00 EA INCLUDED
SUBTOTAL-ACCESS CONTROL $ -
27/280000 LV/SPECIAL-TOTALS $ 20,000
COST PER SF $ 0.77
270000 COMM SYSTEMS FCI Constructors,Inc.Confidential Page 42
Snow Removal Equipment Building (SRE) Final Design GMP Estimate-R1
Eagle County Airport Clarifications & Assumptions
Gypsum, CO. July 24, 2014
C. Exclusions
1. Unloading, handling, or installation of Owner/User provided materials or
equipment unless noted in the documents.
2. Sculptures or artwork.
3. Telephone/data equipment (telephone switching, handsets, PBX units,
computers, network servers, printers, scanners, etc.)
4. All loose equipment and furnishings equipment.
• Furniture- tables, chairs/seats, desks, modular furniture, demountable office
partitions, etc.
• Furnishings — loose shelving, filing cabinets, trash bins, loose storage
cabinets.
• Equipment other than is specifically identified in this estimate.
• Vending machines or equipment.
5. All AudioNisual, cabling, equipment.
6. Security system monitoring or alarm elements.
7. Vehicle maintenance equipment.
8. Vehicle wash equipment.
9. Fuel dispensing equipment.
10.All costs associated with attainment of LEED certification.
12. Third party commissioning costs.
2 FCI Constructors,Inc.
.
Snow Removal Equipment Building (SRE) Final Design GMP Estimate-R1
Eagle County Airport Clarifications &Assumptions
Gypsum, CO. July 24, 2014
D. Clarifications/Assumptions
Site Work
1. The area of disturbance and development is approximately 2.65 acres.
2. Fill material required under proposed building foundations as well as forming of
the building pad is from an on-site stockpile of existing material provided at no
cost (other than transport to the project site). It is assumed that the moisture
content of the existing structural fill stockpile material is within allowable limits.
Therefore, no additional costs are included for drying and spreading of the
structural fill material prior to placement and compaction.
3. Site furnishings are excluded- part of Owner FF& E scope/budget.
4. Treatment of finish graded (un-paved) areas within the site areas of disturbance
is limited to the scope of work defined on drawing C9.00 (no "landscaping" work
indicated).
Foundations & Substructure
5. A 4" diameter perimeter foundation drain is included at perimeter of crawl space
only. In addition, per direction of the architect, an additional 250 If of non-
perforated 4" piping is included to allow for discharge of accumulated water
within the foundation drainage system.
6. An under-slab (or crawl space floor) drainage system is not included.
7. Allowances have been included for a crawl space floor and wall membrane liner
and exhaust system for"soil gas".
8. All building concrete reinforcing steel is un-coated material (no epoxy or
galvanized treatment).
9. Epoxy coated smooth bar dowels are provided at exterior apron pavements.
10. Reinforcing steel at exterior pedestrian walk is standard un-coated material.
11. Over-excavation for the building slab on grade and building foundations has been
included to the prescribed depths noted on the structural drawings. No additional
allowances have been included for increased depth(s) of excavation.
12. No allowances have been made for anti-corrosion inhibitors (i.e. DCI) as
admixtures to site of building concrete.
13. Silica flume additive is not included at any concrete.
3 FCI Constructors,Inc.
Snow Removal Equipment Building (SRE) Final Design GMP Estimate-R1
Eagle County Airport Clarifications & Assumptions
Gypsum, CO.
July 24, 2014
D. Clarifications/Assumptions
Foundations & Substructure
Superstructure
14.All cold-formed framing elements are included with manufacturer's standard
finish.
15.Applied fireproofing of the steel structure is not anticipated and is therefore not
included.
Exterior Closure
16. Operable sections of the glazed wall assemblies are manually operated. Motor
operated units are not included.
17. The translucent glazed wall assemblies are included with manufacturer's
standard white (Crystal) color. Panels are 2.75" thick, with a U-value of 0.20.
Framing is thermally broken aluminum with a clear anodized finish.
Roofing
18.A membrane roofing system (60 mil white TPO) is provided at the Administration
wing. The roof assembly includes a base R-value Of 20. Pricing is based on all
layers of the roofing insulation being attached to the roof deck substrate
simultaneously. The premium cost for attachment of each layer of insulation
separately is not included.
20. Roof top equipment screen walls are not included.
Interior Construction / Finishes
21. Interior metal stud and drywall partitions are typically included to the roof c-joists
above. Framing for non-load bearing is 20-gage material. Walls are included with
sound batt insulation place within the stud cavities. The finish on exposed to view
drywall is a Level 4 orange peel finish.
4 FCI Constructors,Inc.
Snow Removal Equipment Building (SRE) Final Design GMP Estimate-R1
Eagle County Airport Clarifications &Assumptions
Gypsum, CO. July 24, 2014
D. Clarifications/Assumptions
Interior Construction / Finishes
22. The following types of gypsum board products are not included in this estimate:
• Paperless gypsum board.
• Abuse or impact resistant gypsum board.
23. Engineering costs for metal stud framing construction are not included.
24. The cost for epoxy tile grout is not included.
25. Fire rated glazing material is not included.
Specialties/ Equipment/ Furnishings
26. Interior room identification signage has been included as an allowance. The cost
of a site monument sign or building mounted signage or lettering is not included.
27. Corner guards or wall protective surfacing/plating is not included.
28. Loose storage shelving systems are not included.
29.AV equipment is not included (not shown or specified).
30. Visual display boards are not included (not shown or specified).
31. Office work stations are not included.
Fire Protection
32.The base bid scope of work includes a dry-pipe system in the Equipment Storage
area and a wet pipe system in the Administration office area. Alternate#5 revises
the dry-pipe system to a wet pipe system.
33. The cost of fire sprinklers in the crawl space is not included.
34.A fire pump and/or jockey pump is not included.
5 FCI Constructors,Inc.
Snow Removal Equipment Building (SRE) Final Design GMP Estimate-R1
Eagle County Airport Clarifications & Assumptions
Gypsum, CO. July 24, 2014
D. Clarifications/Assumptions
Plumbing
35. Roof overflow drains are not included. Roof overflow capacity is achieved by a
through-wall scupper located over the Tools and Parts Storage room.
HVAC
37. Water treatment system for HVAC hydronic piping is not included (systems use
Glycol in lieu of water).
Electrical
39. Per the scope of work indicated on drawing E3.01 (Plan Note #2), a total of two
(2) pole mounted site lighting fixtures are included (not the 1 fixture as noted on
drawing C2.00).
40. There are a total of four (4) security cameras noted on drawing E2.00 (Plan Note
3). Since the cameras are not specified, an allowance of $8,000 has been
included for the purchase of the cameras. Per the notation on E2.00 Cat6 cabling
is run from each of the cameras to the telephone back board. No other security
system components are included.
41. Emergency power generator scope is limited to the underground conduits run to
the location of the unit. No wiring of equipment is included.
42. The cost of emergency radio amplification system is not included.
43. The work associated with the primary electrical service is limited to installation of
junction vault at connection to existing, installation of conduit to primary
transformer, and trench & backfill for new conduits. Conduit and vault are to
furnished at no cost by HCE to the electrician.
44. Lighting fixtures included are "or equal" to the basis of design fixtures & they
comply with the Buy America requirements.
46.An allowance of$10,000 has been included for seismic bracing for all MEP work.
End of Clarifications &Assumptions.
6 FCI Constructors,Inc.
0
i
I
E
s
4
1
„1
8
A
•
ffi
1 Y
e
I
t I
as 'I1Mg � Y
C a I E a o • -
I a
E { E
al
n 1 .
1 1 .
m �
I g 1 t a t ¢c 'II
- - _•._1 -
5II x S 1 111 a
6 ` 8
a .
o � 21
F 8 2
w
1 m
a
El i
#; i 6
q
E
t
o I T 3 3 7 ! ,- A' i ; : 5 1 3 3 m o d ' 3 3 3' 4 4 a d r
� � ry o � � `� � 4 r � 4 � � a o � h a
I.. $ $ $ ' $ 8 $ r f $ $ $ $ $ 8 $ o °a $ 8 n 8 $ , , $ , $ < 7 1
pp ry $ w � � U •
3 = v, y [ 8 5 v k m °E E m
a 6 m j s e v , - 1 _ a I A m E , m a s $ s Y
1 •m A I A '9 g € s r . a a
=11;;. 3 E II, 8 1 22 I E m a n g l Y @ e rc m rc ¢i 1 ?
wS L Na a a z a8 a 3 3 $ 3 w S ,� s LL '1 s" 9 .<
O
7.,4
T
. f
i. ........._ --- -._-..--- ......... r .._.._. -- ...._.._. __...--. ... ........... -. -
c
g
_ 1
V_ $ & w
i 1 m 8 si 6 $
1 a s
E u e u 5 �
S 6 • A 1 1 N y b 8 2
a ! i i F ng E n a*
c s -,e 9
E S C a • N a H1LL - _
-..-.. 3 E x E P. l G -t- w 1 :�
€ j e F .1 ,1 a g 1 ; ' s ' i 1
.. 1 € 2 g E m I ' 0 il
g eu F
I_ ji -
, t
•
a
3
f
i
E
i
1-411 " 4 1 " " i " 1 " 4HHHH h
E
9
3a a a , a a g a a a a , 8 a .. a . a a B m a a a s a a g a , 4 a , i
1 z ° a A4 . w 1€ E e e s 3 % s
1]
1 ° o ° a pY g ` a t 8 1 e LL g ; Ali - a 1
1 F
F w a p F ; 8 t 3 ° m 8 S - 9 8 P Y - I I - ; , a S £ LL
F o e 1 1 e 13 1 g e 1 F ° 1 ? a F F m u g g i s. I
! 2 g ° A 12 1,0 1 & 2 g 9 e abe g 1 < E g & • g e r e w e 'E -
ICI I'
W a $ 1 1 i a d s a i ; m I d a aw w a E i ,$ a 4 e a a a e i- a R
N 1 s s F s H s 1 1 s s < ' -
g.
•
7,'..
u
S 5 a
1 8LL8 , � � ' IC
1 i g o s i l g '
3 _
s I11
1. g�j 1 i
2 ► 5 3 t S a
—141_. .. .....
.3. 1+13
4 I- -
a
•
8
S
•
•
i
t
I
•
•
s •
•
s rN
t s a a a e e e g b e e . _ ' _ :. _ . cc 2
•
E
Ha o $ $ a a ! a a a a a a , a a a a a 'a a a a 2 4
s "' B LI s g 8 e , £ $ w ' ; a e 3 ca
W—E a
i i 4 s _ a a 2 i a f a i $ . $ _ 8 I 8 : a s
w R
R R R i i Li S Q S R
CNA SURETY
Performance Bond
Bond No. 929599675
CONTRACTOR: SURETY:Western Surety Company :SD Corporation
(Name,legal status and address) (Name,legal status and principal place
of business)
FCI Constructors, Inc. 333 S.Wabash Avenue
30701-70 B, Building A 41st Floor
Chicago, IL 60604 This document has important legal
Grand Junction,CO 81504 consequences. Consultation with
OWNER: an attorney is encouraged with
(Name, legal status and address) respect to its completion or
modification.
Eagle County Any singular reference to
PO Box 850 Contractor,Surety,Owner or
other party shall be considered
Eagle, CO 81631 plural where applicable.
CONSTRUCTION CONTRACT AlA Document 1+312-2010
Date: December 17,2013 combines two separate bonds,a
Four Mdtion Six Hundred Seventy Fax Performance Bond and a
Amount: $4,674,863.00 Thousand Epht Hundred sixty Three Doitws and Oo/1oo Payment Bond,into one form.
This is not a single combined
Description: Performance and Payment Bond.
(Name and location)
Eagle County Regional Airport Snow Removal Equipment Facility(SRE)
BOND
Date: August 21, 2014
(Not earlier than Construction Contract Date)
Amount` $4,674,863.00 Far M5ion Six Hundred Seventy Four
Thousand Eight Hundred sixty Twee oouars and 00/100
Modifications to this Bond: ® None ❑ See Section 16
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corporate Seal) Company: 1 Corporate Seal)
FCI Construc ors, Inc. Western Surety C. y
Signature: 4, A Alt Signature: I
Name .> Fp ..1 Name `nstin aazar 7
and Title: *(-1.4. ck.a. and Title: Attorney-in-Fact
(Any additional signatures appear on the last page of this Performance Bond.)
(FOR INFORMATION ONLY—Name,address and telephone)
AGENT or BROKER: OWNER'S REPRESENTATIVE:
(Architect,Engineer or other party:)
US! Colorado LLC
1515 Wynkoop, Suite 200
Denver, CO 80202
800-873-8500
Printed in cooperation with the American Institute of Architects(ALA).
The language in this document conforms to the language used in AIR Document A312-Performance Bond 2010 Edition.
§T The Contractor and Surety,jointly and severally,bind themselves,their heirs,executors,administrators,successors
and assigns to the Owner for the performance of the Construction Contract,which is incorporated herein by reference.
§2 If the Contractor performs the Construction Contract,the Surety and the Contractor shall have no obligation under
this Bond,except when applicable to participate in a conference as provided in Section 3.
§3 If there is no Owner Default under the Construction Contract,the Surety's obligation under this Bond shall arise
after
.1 the Owner first provides notice to the Contractor and the Surety that the Owner is considering declaring
a Contractor Default. Such notice shall indicate whether the Owner is requesting a conference among
the Owner,Contractor and Surety to discuss the Contractor's performance. If the Owner does not
request a conference,the Surety may,within five(5)business days after receipt of the Owner's notice,
request such a conference. lithe Surety timely requests a conference,the Owner shall attend. Unless
the Owner agrees otherwise,any conference requested under this Section 3.1 shall be held within ten
(10)business days of the Surety's receipt of the Owner's notice. If the Owner,the Contractor and the
Surety agree,the Contractor shall be allowed a reasonable time to perform the Construction Contract,
but such an agreement shall not waive the Owner's right,if any,subsequently to declare a Contractor
Default;
.2 the Owner declares a Contractor Default,terminates the Construction Contract and notifies the Surety;
and
.3 the Owner has agreed to pay the Balance of the Contract Price in accordance with the terms of the
Construction Contract to the Surety or to a contractor selected to perform the Construction Contract.
§4 Failure on the part of the Owner to comply with the notice requirement in Section 3.1 shall not constitute a failure
to comply with a condition precedent to the Surety's obligations,or release the Surety from its obligations,except to
the extent the Surety demonstrates actual prejudice.
§5 When the Owner has satisfied the conditions of Section 3,the Surety shall promptly and at the Surety's expense
take one of the following actions:
§5.1 Arrange for the Contractor,with the consent of the Owner,to perform and complete the Construction Contract;
§5.2 Undertake to perform and complete the Construction Contract itself;through its agents or independent
contractors;
§5.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for
performance and completion of the Construction Contract,arrange for a contract to be prepared for execution by the
Owner and a contractor selected with the Owner's concurrence,to be secured with performance and payment bonds
executed by a qualified surety equivalent to the bonds issued on the Construction Contract,and pay to the Owner the
amount of damages as described in Section 7 in excess of the Balance of the Contract Price incurred by the Owner as
a result of the Contractor Default;or
§5.4 Waive its right to perform and complete,arrange for completion,or obtain a new contractor and with reasonable
promptness under the circumstances:
.1 After investigation,determine the amount for which it may be liable to the Owner and,as soon as
practicable after the amount is determined,make payment to the Owner,or
.2 Deny liability in whole or in part and notify the Owner,citing the reasons for denial.
§6 If the Surety does not proceed as provided in Section 5 with reasonable promptness,the Surety shall be deemed to
be in default on this Bond seven days after receipt of an additional written notice from the Owner to the Surety
demanding that the Surety perform its obligations under this Bond,and the Owner shall be entitled to enforce any
remedy available to the Owner. If the Surety proceeds as provided in Section 5.4,and the Owner refuses the payment
or the Surety has denied liability,in whole or in part,without further notice the Owner shall be entitled to enforce any
remedy available to the Owner.
Printed in cooperation with the American Institute of Architects(AIA).
The language in this document conforms to the language used in AlA Document A312-Performance Bond-2010 Edition. 2
§7 If the Surety elects to act under Section 5.1,5.2 or 5.3,then the responsibilities of the Surety to the Owner shall not
be greater than those of the Contractor under the Construction Contract,and the responsibilities of the Owner to the
Surety shall not be greater than those of the Owner under the Construction Contract. Subject to the commitment by the
Owner to pay the Balance of the Contract Price,the Surety is obligated,without duplication,for
.1 the responsibilities of the Contractor for correction of defective work and completion of the
Construction Contract;
.2 additional legal,design professional and delay costs resulting from the Contractor's Default,and
resulting from the actions or failure to act of the Surety under Section 5;and
.3 liquidated damages,or if no liquidated damages are specified in the Construction Contract,actual
damages caused by delayed performance or non-performance of the Contractor.
§8 If the Surety elects to act under Section 5.1,5.3 or 5.4,the Surety's liability is limited to the amount of this Bond.
§9 The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the
Construction Contract,and the Balance of the Contract Price shall not be reduced or set off on account of any such
unrelated obligations. No right of action shall accrue on this Bond to any person or entity other than the Owner or its
heirs,executors,administrators,successors and assigns.
§10 The Surety hereby waives notice of any change,including changes of time,to the Construction Contract or to
related subcontracts,purchase orders and other obligations.
§11 Any proceeding,legal or equitable,under this Bond may be instituted in any court of competent jurisdiction in
the location in which the work or part of the work is located and shall be instituted within two years after a declaration
of Contractor Default or within two years after the Contractor ceased working or within two years after the Surety
refuses or fails to perform its obligations under this Bond,whichever occurs first. If the provisions of this Paragraph
are void or prohibited by law,the minimum period of limitation available to sureties as a defense in the jurisdiction of
the suit shall be applicable.
§12 Notice to the Surety,the Owner or the Contractor shall be mailed or delivered to the address shown on the page
on which their signature appears.
§13 When this Bond has been furnished to comply with a statutory or other legal requirement in the location where
the construction was to be performed,any provision in this Bond conflicting with said statutory or legal requirement
shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be
deemed incorporated herein. When so furnished,the intent is that this Bond shall be construed as a statutory bond and
not as a common law bond.
§14 Definitions
§14.1 Balance of the Contract Price. The total amount payable by the Owner to the Contractor under the Construction
Contract after all proper adjustments have been made,including allowance to the Contractor of any amounts received
or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is
entitled,reduced by all valid and proper payments made to or on behalf of the Contractor under the Construction
Contract.
§14.2 Construction Contract. The agreement between the Owner and Contractor identified on the cover page,
including all Contract Documents and changes made to the agreement and the Contract Documents.
§14.3 Contractor Default. Failure of the Contractor,which has not been remedied or waived,to perform or otherwise to
comply with a material term of the Construction Contract.
§14.4 Owner Default. Failure of the Owner,which has not been remedied or waived,to pay the Contractor as required
under the Construction Contract or to perform and complete or comply with the other material terms of the
Construction Contract,
§14.5 Contract Documents. Alt the documents that comprise the agreement between the Owner and Contractor.
§15 If this Bond is issued for an agreement between a Contractor and subcontractor,the term Contractor in this Bond
shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor.
Printed in cooperation with the American Institute of Architects(AM).
The language In this document conforms to the language used In AlA Document A312-Performance Bond-2010 Edition. 3
§16 Modifications to this bond are as follows:
(Space is provided below for additional signatures of added parties,other than those appearing on the cover page.)
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corporate Seal) Company: (Corporate Seal)
Signature: Signature:
Name and Title: Name and Title:
Address Address
Printed in cooperation with the American institute of Architects(AM).
The language in this document conforms to the language used in AM Document A312-Performance Bond-2010 Edition. 4
CNA SURETY
Payment Bond
Bond No. 929599675
CONTRACTOR: SURETY:Western Surety Company : SD Corporation
(Name,legal status and address) (Name,legal status and principal place
of business)
FCI Constructors, Inc. 333 S.Wabash Avenue
3070 1-70 B,Building A 41st Floor This document has Important legal
Grand Junction, CO 81504 Chicago,It.60604
consequences. Consultation with
OWNER: an attorney Is encouraged with
(Name,legal status and address) respect to its completion or
modification.
Eagle County Any singular reference to
PO Box 850 Contractor,Surety,Owner or
other party shall be considered
Eagle, CO 81631 plural where applicable.
CONSTRUCTION CONTRACT AIA Document A312-2010
Date: December 17, 2013 combines two separate bonds,a
Performance Bond and a
Amount: $4,674,863.00 rhhousand EygN Hundred Sixty Tk odlars and wino Payment Bond,Into one form.
This is not a single combined
Description: Performance and Payment Bond.
(Name and location)
Eagle County Regional Airport Snow Removal Equipment Facility(S RE)
BOND
Date: August 21, 2014
(Not earlier than Construction Contract Date)
our Milian Six Hundred Seventy Four
Amount: $4,674,863.00 Thousand Eight Hundred Sixty Three Dollars and 00/100
Modifications to this Bond: ® None ❑ See Section 18
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corporate Sean Company: (Corporate Seal)
FCI Constructors, Inc. Western Surety ' • :ny
in
Signature: :.1=lilaartat►. Signature:
Name E. •as n)P. .) Name n . a -r PP-
and Title: _S 1 ii. and Title: Attorney-in-Fact
(Any additional signatures appear on the last page of this Payment Bond)
(FOR INFORMATION ONLY—Name,address and telephone)
AGENT or BROKER: OWNER'S REPRESENTATIVE:
(Architect,Engineer or other party:)
USI Colorado LLC
1515 Wynkoop, Suite 200
Denver, CO 80202
800-873-8500
Printed In cooperation with the American Institute of Architects MIA).
The language In this document conforms to the language used in NA Document A312-Payment Bond•2010 Edition. 5
§1 The Contractor and Surety,jointly and severally,bind themselves,their heirs,executors,administrators,successors
and assigns to the Owner to pay for labor,materials and equipment furnished for use in the performance of the
Construction Contract,which is incorporated herein by reference,subject to the following terms.
§2 If the Contractor promptly makes payment of all sums due to Claimants,and defends,indemnifies and holds
harmless the Owner from claims,demands,liens or suits by any person or entity seeking payment for labor,materials
or equipment furnished for use in the performance of the Construction Contract,then the Surety and the Contractor
shall have no obligation under this Bond.
§3 If there is no Owner Default under the Construction Contract,the Surety's obligation to the Owner under this Bond
shall arise after the Owner has promptly notified the Contractor and the Surety(at the address described in Section 13)
of claims,demands,liens or suits against the Owner or the Owner's property by any person or entity seeking payment
for labor,materials or equipment furnished for use in the performance of the Construction Contract and tendered
defense of such claims,demands,liens or suits to the Contractor and the Surety.
§4 When the Owner has satisfied the conditions in Section 3,the Surety shall promptly and at the Surety's expense
defend,indemnify and hold harmless the Owner against a duly tendered claim,demand,lien or suit.
§5 The Surety's obligations to a Claimant under this Bond shall arise after the following:
§5.1 Claimants,who do not have a direct contract with the Contractor,
.1 have furnished a written notice of non-payment to the Contractor,stating with substantial accuracy the
amount claimed and the name of the party to whom the materials were,or equipment was,furnished or
supplied or for whom the labor was done or performed,within ninety(90)days after having last
performed labor or last furnished materials or equipment included in the Claim;and
.2 have sent a Claim to the Surety(at the address described in Section 13).
§5.2 Claimants,who are employed by or have a direct contract with the Contractor,have sent a Claim to the Surety(at
the address described in Section 13).
§6 If a notice of non-payment required by Section 5.1.1 is given by the Owner to the Contractor,that is sufficient to
satisfy a Claimant's obligation to furnish a written notice of non-payment under Section 5.1.1.
§7 When a Claimant has satisfied the conditions of Sections 5.1 or 5.2,whichever is applicable,the Surety shall
promptly and at the Surety's expense take the following actions:
§7.1 Send an answer to the Claimant,with a copy to the Owner,within sixty(60)days after receipt of the Claim,
stating the amounts that are undisputed and the basis for challenging any amounts that are disputed;and
§7.2 Pay or arrange for payment of any undisputed amounts.
§7.3 The Surety's failure to discharge its obligations under Section 7.1 or Section 7.2 shall not be deemed to
constitute a waiver of defenses the Surety or Contractor may have or acquire as to a Claim,except as to undisputed
amounts for which the Surety and Claimant have reached agreement. If,however,the Surety fails to discharge its
obligations under Section 7.1 or Section 7.2,the Surety shall indemnify the Claimant for the reasonable attorney's
fees the Claimant incurs thereafter to recover any sums found to be due and owing to the Claimant.
§8 The Surety's total obligation shall not exceed the amount of this Bond,plus the amount of reasonable attorney's
fees provided under Section 7.3,and the amount of this Bond shall be credited for any payments made in good faith
by the Surety.
§S Amounts owed by the Owner to the Contractor under the Construction Contract shall be used for the performance
of the Construction Contract and to satisfy claims,if any,under any construction performance bond. By the
Contractor furnishing and the Owner accepting this Bond,they agree that all funds earned by the Contractor in the
performance of the Construction Contract are dedicated to satisfy obligations of the Contractor and Surety under this
Bond,subject to the Owner's priority to use the funds for the completion of the work.
Printed In cooperation with the American Institute of Architects(AtA).
The language In this document conforms to the language used In AIA Document A3i2..Payment Bond-2010 Edition. 6
§10 The Surety shall not be liable to the Owner,Claimants or others for obligations of the Contractor that are
unrelated to the Construction Contract. The Owner shall not be liable for the payment of any costs or expenses of any
Claimant under this Bond,and shall have under this Bond no obligation to make payments to,or give notice on behalf
of,Claimants or otherwise have any obligations to Claimants under this Bond.
§11 The Surety hereby waives notice of any change,including changes of time,to the Construction Contract or to
related subcontracts,purchase orders and other obligations.
§12 No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent
jurisdiction in the state in which the project that is the subject of the Construction Contract is located or after the
expiration of one year from the date(1)on which the Claimant sent a Claim to the Surety pursuant to
Section 5.1.2 or 5.2,or(2)on which the last labor or service was performed by anyone or the last materials or
equipment were furnished by anyone under the Construction Contract,whichever of(1)or(2)first occurs. If the
provisions of this Paragraph are void or prohibited by law,the minimum period of limitation available to sureties as a
defense in the jurisdiction of the suit shall be applicable.
§13 Notice and Claims to the Surety,the Owner or the Contractor shall be mailed or delivered to the address shown
on the page on which their signature appears. Actual receipt of notice or Claims,however accomplished,shall be
sufficient compliance as of the date received.
§14 When this Bond has been furnished to comply with a statutory or other legal requirement in the location where
the construction was to be performed,any provision in this Bond conflicting with said statutory or legal requirement
shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be
deemed incorporated herein. When so furnished,the intent is that this Bond shall be construed as a statutory bond and
not as a common law bond.
§15 Upon request by any person or entity appearing to be a potential beneficiary of this Bond,tho Contractor and
Owner shall promptly furnish a copy of this Bond or shall permit a copy to be made.
§16 Definitions
§16.1 Claim. A written statement by the Claimant including at a minimum:
.1 the name of the Claimant;
.2 the name of the person for whom the labor was done,or materials or equipment furnished;
.3 a copy of the agreement or purchase order pursuant to which labor,materials or equipment was
furnished for use in the performance of the Construction Contract;
.4 a brief description of the labor,materials or equipment furnished;
.5 the date on which the Claimant last performed labor or last furnished materials or equipment for use in
the performance of the Construction Contract;
.6 the total amount earned by the Claimant for labor,materials or equipment furnished as of the date of
the Claim;
.7 the total amount of previous payments received by the Claimant;and
.8 the total amount due and unpaid to the Claimant for labor,materials or equipment furnished as of the
date of the Claim.
§16.2 Claimant. An individual or entity having a direct contract with the Contractor or with a subcontractor of the
Contractor to furnish labor,materials or equipment for use in the performance of the Construction Contract. The term
Claimant also includes any individual or entity that has rightfully asserted a claim under an applicable mechanic's lien
or similar statute against the real property upon which the Project is located. The intent of this Bond shall be to
include without limitation in the terms labor,materials or equipment"that part of water,gas,power,light,heat,oil,
gasoline,telephone service or rental equipment used in the Construction Con tract,architectural and engineering
services required for performance of the work of the Contractor and the Contractor's subcontractors,and all other
items for which a mechanic's lien may be asserted in the jurisdiction where the labor,materials or equipment were
furnished.
§16.3 Construction Contract. The agreement between the Owner and Contractor identified on the cover page,
including all Contract Documents and all changes made to the agreement and the Contract Documents.
Printed In cooperation with the American Institute of Architects(AM).
The language In this document conforms to the language used In NA Document A312-Payment Bond-2010 Edition. 7
§16.4 Owner Default. Failure of the Owner,which has not been remedied or waived,to pay the Contractor as required
under the Construction Contract or to perform and complete or comply with the other material terms of the
Construction Contract.
§16.5 Contract Documents. All the documents that comprise the agreement between the Owner and Contractor.
§17 if this Bond is issued for an agreement between a Contractor and subcontractor,the term Contractor in this Bond
shall be deemed to be Subcontractor and the term Owner shall be deemed to be Contractor.
§18 Modifications to this bond are as follows:
(Space is provided below for additional signatures of added parties,other than those appearing on the cover page.)
CONTRACTOR AS PRINCIPAL SURETY
Company: (Corporate Seal) Company: (Corporate Seat)
Signature: Signature:
Name and Title: Name and Title:
Address Address
Printed In cooperation with the American Institute of Architects(ALA).
The language in this document conforms to the language used in AA Document A312-Payment Bond-2010 Edition. 8
Western Surety Company
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Presents,That WESTERN SURETY COMPANY,a South Dakota corporation,is a duly organized and existing corporation
having its principal office in the City of Sioux Falls,and State of South Dakota,and that it does by virtue of the signature and seal herein affixed hereby
make,constitute and appoint
Douglas C Baesler, Kristin L Salazar,Cory Clauss,Mary E Hanks, Individually
of Denver,CO,its true and lawful Attorneys)-in-Fact with full power and authority hereby conferred to sign,seal and execute for and on its behalf bonds,
undertakings and other obligatory instruments of similar nature
- In Unlimited Amounts-
and to bind it thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of the corporation and all the acts of said
Attorney,pursuant to the authority hereby given,are hereby ratified and confirmed.
This Power of Attorney is made and executed pursuant to and by authority of the By-Law printed on the reverse hereof,duly adopted,as indicated,by
the shareholders of the corporation.
In Witness Whereof.WESTERN SURETY COMPANY has caused these presents to be signed by its Vice President and its corporate seal to be
hereto affixed on this 18th day of Lune,2013.
.ycr}, WESTERN SURETY COMPANY
a
to
As Das%
aui T Bruflat,Vice President
State of South Dakota
ss
County of Minaehaha
On this 18th day of June,2013,before me personally came Paul T.Bruflat,to me known,who being by me duly sworn,did depose and say that he
resides in the City of Sioux Falls,State of South Dakota;that he is the Vice President of WESTERN SURETY COMPANY described in and which executed
the above instrument;that he knows the seal of said corporation;that the seal affixed to the said instrument is such corporate seal,that it was so affixed
pursuant to authority given by the Board of Directors of said corporation and that he signed his name thereto pursuant to like authority,and acknowledges
same to be the act and deed of said corporation.
My commission expires t
J.MOHR
June 23,2015 f NOTARY PIJOLIC
SOUTH CUIKOTA { ,/} 4r i 61/A A')
J.Mohr,Notary Public
CERTIFICATE
I,L Nelson,Assistant Secretary of WESTERN SURETY COMPANY do hereby certify that the Power of Attorney hereinabove set forth is still in
force,and further certify that the By-Law of the corporation pri d on the reverse ereof is -ill in force. In testimRny1 w ereof I have hereunto subscribed
my name and affixed the seal of the said corporation this _a day of , !!r��)l� L1�
Q,"atnep� WESTERN SURETY COMPANY
pPO"4';*
z
�,S�Ayfp
�•••L.Nelson,Assistant Secretary
Form F4280,7,2012
""Ace`, DATE(MAUDDIYYYY)
14.--../ CERTIFICATE OF LIABILITY INSURANCE 8/18/2014
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER.THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER,AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder Is an ADDITIONAL INSURED,the pollcy(ies)must be endorsed, If SUBROGATION IS WAIVED,subject to
the terms and conditions of the policy,certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder In lieu of such endorsement(s).
PRODUCER NONT CT Ma
Clanne_Sewolt
US!Colorado,LLC Construction rts4tc°1 E,11800-873-8500 FAX Ne1:303 831-5296
1515 Wynkoop Street EM
Suite 200 oDesss:den.contractors@usi.biz
Denver CO 80202 INSURER(S)AFFORDING COVERAGE NAIC C
INSURER A:Arch insurance Company U 1.50
INSURED FCICON INSURER B:St PauLEi[e_and..Marine Insurance C 24767
FCI Constructors,Inc. INSURERC:
PO Box 1767 INSURER D:
Grand Junction CO 81502
INSURER E:
INSURER F:
COVERAGES CERTIFICATE NUMBER:630661248 REVISION NUMBER:
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT,TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN,THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS.
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES.LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
tLTR TYPE OP INSURANCE (NCR I wVDRI POLICY NUMBER I IMMIDDYIYYYYI I I1 WD0IDIYEYYY LIMITS
A GENERALLJAaILITY FAGLB9175000 0/1/2013 10/1/2014 EACH OCCURRENCE 11,000.000
EMIDAMAGETCTRERTEO
COMMERCIAL GENERAL LIABILITY PREMIKS(EayccVnenpl 1100,000
.■CLAIMS-MADE I _,.J OCCUR MED EXP(Any one person) $10,000
■ PERSONAL,&ADV INJURY S1,000,000
,J ■. -. GENERAL AGGREGATE 12,000,000
GENt AGGREGATE LIMIT APPLIES PER PRODUCTS•COMPROP AGG 12,000.000
!^
POLICY 1 PZ:4j 7 Lac 1
A AUTOMOBILE LIABILITY ZACAT9155900 10)112013 10/1/2014 CDMIIINED SINGLE LII.NT
(Ea scddem) 11,OOD,000
X ANY AUTO BODILY (JURY(Per person) S
ALL OWNED SCHEDULED BODILY INJURY(Per acodenl S
AUTOS AUTOS
N-O 'PROPERLY DAMAGE
X AUTOS ED
Per PERTY j $
HIRED AUTOS AUTOS
5
8 X UMBRELLALULB OCCUR 2UP15P9635713NF 10/1/2013 10/112014 EACH OCCURRENCE I$25000,000
EXCESS LAB CLAIMS-MADE AGGREGATE $25,000,000
DE0 X RETENTION$10,000 i S
A WORKERS COMPENSATION QAWCI9300900 10/1/2013 10/1/2014 X ITOCRYSL1MIU78 101)
AND EMPLOYERS'LIABILITY Y 1 N
ANY PROPRIETORIPARTNEILEXECUTlVE Ni A E.L.EACH ACCIDENT $1,000,000
OFFICER/MEMBER EXCLUDED?
(Mandatory In NH) E L DISEASE-EA EMPLOYEE S1,000,000 ,
U yea,deecdDe under
DESCRIPTION OF OPERATIONS below E .DISEASE•POLICY LIMIT 51,000.000
DESCRIPTION OF OPERATIONS I LOCATIONS I VEHICLES(Attach ACORD 101,Additional Remarks Schedule,If mars apace Is reoWnd)
RE: Eagle County Airport—Snow Removal Equipment Building(SRE)
As required by written contract or written agreement,the following provisions apply subject to the policy terms,conditions,limitations and
exclusions:the Certificate Holder is included as Additional Insured for work,acts or omissions which includes completed operations under
the General Liability but only with respect to liability arising out of the Named Insured's work performed on behalf of the certificate holder.
CERTIFICATE HOLDER CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
Eagle County ACCORDANCE WITH THE POLICY PROVISIONS.
Attn: Rick Ullom,Project Manager
PO Box 850 AUTHORIZED REPRESENTATIVE
Eagle CO 81631
Villkk\SoOSAIIIWallal.
i
C)1988-2010 ACORD CORPORATION. All rights reserved.
ACORD 25(2010/05) The ACORD name and logo are registered marks of ACORD
ACC MCP EVIDENCE OF PROPERTY INSURANCE DATE`NINVDD"YYY'
6/25/2014
THIS EVIDENCE OF PROPERTY INSURANCE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE
ADDITIONAL INTEREST NAMED BELOW. THIS EVIDENCE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE
COVERAGE AFFORDED BY THE POLICIES BELOW. THIS EVIDENCE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE
ISSUING INSURER(S),AUTHORIZED REPRESENTATIVE OR PRODUCER,AND THE ADDITIONAL INTEREST.
AGENCY � C AQU.800-973-8500 COMPANY
LEILE
USI Colorado, LLC Construction Travelers Indemnity Company
1515 Wynkaop Street
Suits 200
Denver, CO 90202
aC.Ne303 63i-5295 ADORIESS: den-cantractors00usi.bir
CODE; SUB CODE:
AGENCY -tcot-I
SItHIQMERJR l:
INSURED LOAN NUMBER POLICY NUMBER
FCI Constructors, OT660142O86.14TIL13
PO Box 1767
Grand Junction, CO 81502 EFFECTIVE DATE EXPIRATION DATE
CONTINUED UNTIL
li/It' t13 11/1/2 014
1 1 TERMINATED IF CHECKED
THIS REPLACES PRIOR EVIDENCE DATED:
PROPERTY INFORMATION
LOCATION/DESCRIPTION
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED.
NOTWITHSTANDING ANY REQUIREMENT. TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
EVIDENCE OF PROPERTY INSURANCE MAY BE ISSUED OR MAY PERTAIN,THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS
SUBJECT TO ALL THE TERMS,EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INFORMATION
COVERAGE I PERILS I FORMES j AMOUNT OF INSURANCE OEDUCTIBLE
Builder's Risk. - Special Form-Reporting Form
Fire Resistive 50,000,000 10,000
Frame/ Joisted Masonry 10,000,000 10,000
Flood a Earth Movement, sub limit 10,000,000 25,000
REMARKS(Including Special Conditions)
RE: Eagle County Airport - Snow Removal Equipment Building (SRE)
CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE
DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.
ADDITIONAL INTEREST
NAME AND ADDRESS MORTGAGEE ADDITIONAL INSURED
LOSS PAYEE
Eagle County LOANM
Attn: Rick Mum, Project Manager
PO Box 850
*,....,. Eagle CO 81031. AUTHORIZED REPRESENTATIVE
ACORD 27(2009112) 01993-2009 ACORD CORPORATION. All rights reserved.