PROJECT: EGE Root Outbound Baggage CHANGE ORDER NUMBER : One Revision #3
0219 Eldon Wilson Road DATE: April 6, 2008
Gypsum, CO 81837 CONTRACTOR PROJECT #: 2718
CONTRACT DATE: June 21, 2007
TO CONTRACTOR: J. L. Viele Construction, Inc.
1000 S. Frontage Rd. West, Ste. 202 ,
Vail, CO 81657
The Contract is changed as follows:
1. COP #1 -Additional excavation and foundation work at existing curbside. (2 days) $ 5,734.98
2. COP #2 -Lower rim of catch basin and regrade area east of addition for drainage. (5 days) $ 4,473.00
3. COP #3 -Fire alarm panel upgrade. (5 days) $ 23,046.47
4. COP #4 -Fire sprinkler stub outs and dry stand pipes. (6 days) $ 10,495.14
5. COP #5 -Trash enclosure, fencing and gates. (5 days) $ 30,224.64
6. COP #6 -Electrical conduit for future power needs. (3 days) $ 10,267.40
7. COP #7 - Snowmelt ®east sidewalk to trash enclosure. (3 days) $ 8,211.59
8. COP #8 -Additional electrical and conduit for future curbside check-in . (4 days) $ 11,922.24
9. COP #9 -Extend existing terminal HVAC ducts to roof of addition. (28 days) $ 17,836.12
10. COP #10 -Make additional modifications to the south conveyor for structure. (14 days) $ 19,570.25
11. COP #11 -Add doors to the area separation walls and existing curbside check-in. (10 days) $ 9,582.03
12. COP #12 -Provide additional CO detectors to the west end of the building. (3 days) $ 3,814.88
13. COP #13 -Replace the annuciator panel at the west entrance to the terminal. (4 days) $ 4,804.80
14. COP #14 -Provide stainless steel bumpers to the south entrance recess. Remove From Contract
15. COP #15 - Install a gas fired unit heater to the existing curbside check-in area. (4 days) $ 3,443.90
16. COP #16 -Install one radiant tube heater to future curbside/storage. (3 days) $ 3,718.76
17. COP #17 -Install 8 Patio Pal gas fired radiant heaters at existing curbside. (8 days) $ 16,809.92
18. COP #18 -Add bollard at TSA, bumpers to existing cols, install bollard ®south. (2 days) $ 1,563.62
19. COP #19 -Provide AC powered CO detectors and a CO recording device. $ 448.36
20. COP #20 -Provide fence panels for separation of storage areas at future curbside. (2 days) $ 2,189.38
21. COP #21 -Provide steel angles and sheetmetal trim at the overhead doors. (10 days) $ 17,333.79
22. COP #22 -Install light at terminal side of the area separation wall. (5 days) $ 3,945.44
23. COP #23 -Provide fence panel at rated chase. (1 day) $ 446.79
24. COP #24 -Provide and install 4 exterior emergency lights per TOG & ASI #3. (3 days) $ 5,223.07
25. COP #25 -Trouble shoot existing fire alarm wiring to locate ground faults. $ 1,139.40
26. COP #26 -Provide heat tape in gutters & downspouts at future curbside check-in. (3 days) $ 2,809.43
27. COP #27 -Provide em & exit lights at the rated chase & south & east exits. (5 days) $ 3,413.57
TOTAL 222,468.97
Not valid until sl ned b the Owner, Architect and Contractor.
The original (Guaranteed Maximum cost) was .......................................................................... 3,659,964.00
Net change by previously authorized Change Orders ............................................................................... -
The (Guaranteed Maximum Cost) prior to this Change Order was ................................................. 3,659,964.00
The (Guaranteed Maximum Cost) will be changed by this Change Order .................................... 222,468.97
The new (Guaranteed Maximum Cost) including this Change Order will be ........................... 3,882,432.97
The Contract Time will be increased by 138 days
The date of Substantial Completion as of the date of this Change Order therefore is May 7, 2008.
NOTE: The summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which
have been authorized by Construction Change Directive.
Architect: Contractor: Owner:
J. L. Viele Constructio
10 S. Frontage d., Wes _ ~,
V~ , O 81657 f%~
~ ~
BY B BY
~. as ~
L~
DATE DATE DATE
AIA DOCUMENT G701 CHANGE ORDER 1987 EDITION AIA THE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE., N.W., WASHINGTON, D.C. 20006 G701-1987
Co~~(I ~`