HomeMy WebLinkAboutC08-032CHANGE ORDER
Distribution to:
[XJ OWNER [X] CONTRACTOR
[ ] ARCHITECT [ ] FIELD
[ ~ OTHER
PROJECT : EAGLE COUNTY HAZARDOUS CHANGE ORDER NO: ONE
HOUSEHOLD WASTE FACILITY INITIATION DATE : 2/5/2008
CONTRACTOR: TilSCA Il, [NC.
PO BOX 4136, 338 S. 7TH STREET
GRAND JUNCTION, CO 81501 CONTRACT DATE : 7!27/2007
You are directed to make the following changes in this Contract
Add Alternate #1 Bio Mass Option Tarm ALLOWANCE
Division IS $74,049.00
Contractors Fee (8%) $5,924.00
Bond /Insurance $2,399.00
Pre-Construction /Design Fee Associated with Bio Mass Scope of Work $8,000.00
TOTAL 90,372.00
Eagle County hereby makes assurance that lawful appropriations to cover the costs of the
additional work have been made.
The original Contract Sum was $550,000.00
_ __ _ _ __
Net change by previously authorized Change Orders _ __
$0.00
_ __ _ _ _ _ __ _ _ __
The Contract Sum prior to this Change Order was _
$550,000.00
_ _
The Contract Sum will be increased by this change order $9Q372.00
--
Thenew Contract Sum including this Change Order will be _ __
$640,372.00
The Contract Time will be increased based on the Notice to Proceed 1/16J08 by 64 calendar days.
_
The Date of Substantial Completion as of the date of this Change Order therefore is ~
15-Sep-08