HomeMy WebLinkAboutC07-141 Calzadillas LandscapingAGREEMENT
THIS AGREEMENT is dated as of the 105 day of , in the year 2007,
by and between
Board of County Commissioners
Eagle County, Colorado
(hereinafter called OWNER)
and
Calzadillas Landscaping, LLC
(hereinafter called CONTRACTOR)
OWNER and CONTRACTOR, in consideration of the mutual covenants set forth, agree as
follows:
ARTICLE 1 — WORK
CONTRACTOR shall complete all work as specified or indicated in the Contract Documents.
The work is generally described as follows:
Installation of forty trees with irrigation line and pump system along the Seago section
of the Eagle to Gypsum trail.
ARTICLE 2 — OWNER'S REPRESENTIVE
The Project has been designed by Schmueser Gordon Meyer Engineering, Inc., (SGM) who is
hereinafter called ENGINEER, and will assume all duties and responsibilities, and will have the
rights and authority assigned to ENGINEER in the Contract Documents in connection with
completion of the work in accordance with the Contract Documents. The OWNER's
representatives is Ellie Caryl of the ECO Trails Department of Eagle County, hereinafter
OWNER. Additional OWNER's representative is Peter Fralick of the Facilities Department of
Eagle County.
ARTICLE 3 - CONTRACT TIME
3.1 The work will be substantially completed on or before August 1, 2007 on the majority
of the project, and completed at the connection to the railroad tunnel and ready for final
payment in accordance with paragraph 14.13 of the General Conditions on or before
December 31, 2007.
3.2 LIQUIDATED DAMAGES: OWNER and CONTRACTOR recognize that time is of
the essence of this Agreement and that OWNER will suffer financial loss if the work is
not substantially complete within the time specified in paragraph 3.1 above, plus any
extensions thereof allowed in accordance with Article 12 of the General Conditions.
AGREEMENT Page 1
They also recognize the delays, expense, and difficulties involved in proving at a legal
or arbitration proceeding the actual loss suffered by OWNER if the work is not
substantially complete on time. Accordingly, instead of requiring such proof, OWNER
and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty)
CONTRACTOR shall pay OWNER two -hundred dollars ($200.00) for each day that
expires after the time specified in paragraph 3.1 for substantial completion until the
work is substantially complete.
ARTICLE 4 - CONTRACT PRICE
4.1 The funds appropriated for this project are equal to or in excess of the contract amount.
OWNER shall pay CONTRACTOR for performance of the work in accordance with the
ARTICLE 5 — PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER and OWNER
as provided in the General Conditions.
5.1 PROGRESS PAYMENTS: OWNER shall make monthly progress payments on account
of the Contract Price on the basis of CONTRACTOR'S Applications for Payments as
recommended by ENGINEER, as provided below. All progress payments will be on the
basis of the progress of the work measured by the schedule of values provided for in
paragraph 14.1 of the General Conditions.
5.1.1 Prior to Substantial Completion, progress payments will be in an amount equal to:
AGREEMENT
Page 2
90% of the work completed until fifty percent (50%) of the work is
performed, after which no additional retainage shall be withheld, and
90% of materials and equipment not incorporated in the work but
delivered and suitably stored, less in each case the aggregate of payments
previously made.
5.1.2 Upon Substantial Completion, OWNER shall pay an amount sufficient to increase
total payments to CONTRACTOR to 95% of the Contract Price, less such
amounts as ENGINEER shall determine in accordance with paragraph 14.7 of the
General Conditions.
5.2 FINAL PAYMENT: Upon final completion and acceptance in accordance with
paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the
Contract Price as recommended by ENGINEER as provided in said paragraph 14.13.
The final payment shall not be made until after final settlement of this contract has been
duly advertised at least ten days prior to such final payment by publication of notice
thereof at least twice in a public newspaper of general circulation published in Eagle
County, and the Board of County Commissioners has held a public hearing, thereupon
and complied with the Revised Statutes 1973, Section 38-26-107 as amended. Final
payment shall be made in accordance with the requirements of aforesaid statute.
ARTICLE 6 — CONTRACTOR'S REPRESENTATIONS
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
6.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract
Documents, work, locality, and with all local conditions, and federal, state, and local
laws, ordinances, rules and regulations that in any manner affect cost, progress, or
performance of the work.
6.2 CONTRACTOR has studied carefully all reports of investigations and tests of subsurface
and latent physical conditions at the site or otherwise affecting cost, progress, or
performance of the work which were relied upon by ENGINEER in the preparation of the
Drawings and Specifications, and which have been identified in the Supplementary
Conditions.
6.3 CONTRACTOR has made, or caused to be made, examinations, investigations, and tests
and studies of such reports and related data in addition to those referred to in paragraph
6.2 as he deems necessary for the performance of the work at the Contract Price, within
the Contract Time, and in accordance with other terms and conditions of the Contract
Documents; and no additional examinations, investigations, tests, reports, or similar data
are, or will be required by CONTRACTOR for such purposes.
AGREEMENT
Page 3
6.4 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, tests, reports, and data with the terms and conditions of the Contract
Documents.
6.5 CONTRACTOR has given ENGINEER written notice of all conflicts, errors, or
discrepancies that he has discovered in the Contract Documents and the written resolution
thereof by ENGINEER is acceptable to CONTRACTOR.
ARTICLE 7 — CONTRACT DOCUMENTS
The contract Documents which comprise the entire Agreement, made a part hereof, and consist
of the following:
7.1 This Agreement (Pages 1 to 7, inclusive).
7.2 Performance and other Bonds, identified as exhibits , and consisting of pages.
7.3 Notice of Award, Notice to Proceed.
7.4 General Conditions (Pages 1 to 36, inclusive).
7.5 Documentation submitted by CONTRACTOR prior to Notice of Award (Pages to
, inclusive).
7.6 Any modification, including Change Orders, duly delivered after execution of
Agreement.
There are no Contract Documents other than those listed above in this Article 7. The Contract
Documents may only be altered, amended, or repealed by a Modification (as defined in Section 1
of the General Conditions).
ARTICLE 8 —PROHIBITIONS ON PUBLIC CONTRACT FOR SERVICES
8.1 The Contractor shall not knowingly employ or contract with an illegal alien to perform
work under the public contract for services; or enter into a contract with a subcontractor
that fails to certify to the contractor that the subcontractor shall not knowingly employ or
contract with an illegal alien to perform work under the public contract for services.
8.2 The Contractor shall verify or attempt to verify through participation in the Basic Pilot
Verification program, as administered by the United States Department of Homeland
Security, that the Contractor does not employ any illegal aliens. If the Contractor is not
accepted into the Basic Pilot Verification Program prior to entering into a public
contract for services, the contractor shall apply to participate in the Program every three
AGREEMENT
Page 4
months until the contractor is accepted or the public contract for services has been
completed, whichever is earlier. Information on applying for the Basic Pilot
Verification Program can be found at https://www.vis-dhs.com\employerregistration.
8.3 The Contractor shall not use the Basic Pilot Verification Program procedures to
undertake pre-employment screening of job applicants while the public contract for
services is being performed.
8.4 If the Contractor obtains actual knowledge that a Subcontractor performing work under
the public contract for services knowingly employs or contracts with an illegal alien, the
Contractor shall be required to:
a. Notify the Subcontractor and the County within three days that the
Contractor has actual knowledge that the Subcontractor is employing or
contracting with an illegal alien; and
b. Terminate the Subcontract with the Subcontractor if within three days of
receiving the notice required pursuant to subparagraph (i) of the paragraph (d) the
Subcontractor does not stop employing or contracting with the illegal alien;
except that the Contractor shall not terminate the contract with the Subcontractor
if during such three days the Subcontractor provides information to establish that
the Subcontractor has not knowingly employed or contracted with an illegal alien.
C. The Contractor shall comply with any reasonable request by the
Department of Labor and Employment made in the course of an investigation that
the department is undertaking pursuant to its authority.
d. If a Contractor violates these prohibitions, the County may terminate the
contract for a breach of the contract. If the contract is so terminated, the
Contractor shall be liable for actual and consequential damages to the County.
ARTICLE 9 — MISCELLANEOUS
9.1 The terms used in this Agreement which are defined in Article 1 of the General
Conditions shall have the meanings indicated in the General Conditions.
9.2 No assignment by a party hereto of any rights under, or interests in the Contract
Documents will be binding on another party hereto without the written consent of the
party sought to be bound; and specifically, but without limitation, moneys that may
become due and moneys that are due may not be assigned without such consent (except
to the extent that the effect of this restriction may be limited by law), and unless
specifically stated to the contrary in any written consent to an assignment, no assignment
will release or discharge the assignor from any duty or responsibility under the Contract
Documents.
AGREEMENT
Page 5
9.3 OWNER and CONTRACTOR each binds himself, his partners, successors, assigns and
legal representatives to the other party hereto, in respect to all covenants, agreements, and
obligations contained in the Contract Documents.
9.4 ATTORNEY'S FEES: In the event of litigation between the parties hereto regarding the
interpretation of this Agreement, or the obligations, duties or rights of the parties
hereunder, or if suit otherwise is brought to recover damages for breach of this
Agreement, or an action be brought for injunction or specific performance, then and in
such events, the prevailing party shall recover all reasonable costs incurred with regard to
such litigation, including reasonable attorney's fees.
9.5 APPLICABLE LAW: This Agreement shall be governed by the laws of the State of
Colorado. Jurisdiction and venue of any suit, right, or cause of action arising under, or in
connection with this Agreement shall be exclusive in Eagle County, Colorado.
IN WITNESS WHEREOF, the parties hereto have signed this Agreement in triplicate. One
counterpart each has been delivered to OWNER, CONTRACTOR, and ENGINEER. All
portions of the Contract Documents have been signed or identified by OWNER and
CONTRACTOR, or by ENGINEER on their behalf.
This Agreement will be effective on , 2007.
:�ulZ10
COUNTY OF EAGLE, STATE OF COLORADO,
By aJISSINERS
BOARD OF COUNTY
ATTEST: ;COy:
Clerk to the Board oft:fi, Chairman
County Commissioners
CONTRACTOR:
By: « cls
Name:
Title: ✓t �g.r�
AGREEMENT Page 6
STATE OF COLORADO
County of
The foregoing was acknowledged before me this day of V— I I , 2007
by . q� CU tZG A1\QS as of CA lZ CICO X10.5 L .nSCci l rlg (.
WITNESS my hand and official seal.
My commission expires 1Ey Commission Expires 04/24/2038
2.5 Market ., Eagle CU Bi631
Notary Public
AGREEMENT
�pTA RI:
N
'9X�. Fg Ai.6t
Page 7
t
f
r.
ss,
k'
1 0
GENERAL CONDITIONS
TABLE OF CONTENTS
ARTICLE TITLE PAGE
1. DEFINITIONS....................................................................................................................1
2. PRELIMINARY MATTERS..............................................................................................3
3. CONTRACT DOCUMENTS..............................................................................................4
4. AVAILABILITY OF LANDS; PHYSICAL CONDITIONS;
REFERENCEPOINTS.......................................................................................................5
5. BONDS AND INSURANCE..............................................................................................6
6. CONTRACTOR'S RESPONSIBILITIES..........................................................................8
7. WORK BY OTHERS........................................................................................................15
8. OWNER'S RESPONSIBILITIES.....................................................................................15
9. ENGINEER'S STATUS DURING CONSTRUCTION...................................................15
10. CHANGES IN THE WORK.............................................................................................17
11. CHANGE OF CONTRACT PRICE.................................................................................18
12. CHANGE OF CONTRACT TIME...................................................................................22
13. WARRANTY AND GUARANTEE; TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE
OFDEFECTIVE WORK..................................................................................................22
14. PAYMENTS TO CONTRACTOR AND COMPLETION...............................................24
15. SUSPENSION OF WORK AND TERMINATION.........................................................29
16. MISCELLANEOUS..........................................................................................................30
INDEX..............................................................................................................................32
GENERAL CONDITIONS
ARTICLE 1 — DEFINITIONS
Wherever used in these general conditions or in the other Contract Documents, the following terms have
the meanings indicated which are applicable to both the singular and plural thereof.
ADDENDA: Written or graphic instruments issued prior to the opening of bids which clarify,
correct, or change the bidding documents or the contract documents.
AGREEMENT: The written agreement between OWNER and CONTRACTOR covering the
work to be performed; other contract documents are attached to the agreement and made a part
thereof as provided therein.
APPLICATION FOR PAYMENT: The form accepted by ENGINEER which is to be used by
CONTRACTOR in requesting progress or final payment, and which is to include such supporting
documentation as is required by the contract documents.
BID: The offer or proposal of the bidder submitted on the prescribed form setting forth the prices
for the work to be performed.
BONDS: Bid, performance, and payment bonds, and other instruments of security.
CHANGE ORDER: A written order to CONTRACTOR signed by OWNER authorizing an
addition, deletion, or revision in the work, or an adjustment in the contract price or the contract
time issued after the effective date of the agreement.
CONTRACT DOCUMENTS: Those documents set forth in Article 7 of the Agreement.
CONTRACT PRICE: The monies payable by OWNER to CONTRACTOR under the contract
documents as stated in the agreement.
CONTRACT TIME: The number of days (computed as provided in paragraph 16.2), or the date
stated in the agreement for the completion of the work.
CONTRACTOR: The person, firm, or corporation with whom OWNER has entered into the
agreement.
DAY: A calendar day of twenty-four hours measured from midnight to the next midnight.
DEFECTIVE: An adjective which, when modifying the word "work," refers to work that is
unsatisfactory, faulty or deficient, or does not meet the requirements of any inspection, test, or
approval referred to in the contract documents, or has been damaged prior to ENGINEER'S
recommendation of final payment or prior to the guarantee period under paragraph 13.12.
DRAWINGS: The drawings which show the character and scope of the work to be performed,
and which have been prepared or approved by ENGINEER, and are referred to in the contract
documents.
EFFECTIVE DATE OF THE AGREEMENT: The date indicated in the agreement on which
it becomes effective, but, if no such date is indicated, it means the date on which the agreement is
signed and delivered by the last of the two parties to sign and deliver.
General Conditions Page 1
ENGINEER: The person, firm or corporation named as such in the Agreement. The Engineer
may be a department employee of OWNER, but in such case shall exercise his duties in
conformance with the standards applicable to independent professional engineers.
FIELD ORDER: A written order issued by ENGINEER which orders minor changes in the
work in accordance with paragraph 10.2, but which does not involve a change in the contract
price or the contract time.
MODIFICATION: (a) A written amendment of the contract documents signed by both parties,
(b) a change order, or (c) a field order. A modification may only be issued after the effective date
of the agreement.
NOTICE OF AWARD: The written notice by OWNER to the apparent successful bidder stating
that upon compliance by the apparent successful bidder with the conditions precedent enumerated
therein, within the time specified, OWNER will sign and deliver the agreement.
NOTICE TO PROCEED: A written notice given by OWNER to CONTRACTOR (with a copy
to ENGINEER) fixing the date on which the contract time will commence to run, and on which
CONTRACTOR shall start to perform his obligation under the contract documents.
OWNER: The public body or authority, corporation, association, partnership, or individual with
whom CONTRACTOR has entered into the agreement, and for whom the work is to be provided.
PROJECT: The total construction of which the work to be provided under the contract
documents may be the whole or a part, as indicated elsewhere in the contract documents.
RESIDENT PROJECT REPRESENTATIVE: The authorized representative of ENGINEER
who is assigned to the site or any part thereof.
SHOP DRAWINGS: All drawings, diagrams, illustrations, schedules, and other data which are
specifically prepared by CONTRACTOR, a subcontractor, manufacturer, fabricator, supplier, or
distributor to illustrate some portion of the work, and all illustrations, brochures, standard
schedules, performance charts, instructions, diagrams, and other information prepared by a
manufacturer, fabricator, supplier, or distributor and submitted by CONTRACTOR to illustrate
material or equipment for some portion of the work.
SPECIFICATIONS: Those portions of the contract documents consisting of written technical
descriptions of materials, equipment, construction systems, standards, and workmanship as
applied to the work, and certain administrative details applicable thereto.
SUBSTANTIAL COMPLETION: The work (or a specified part thereof) has progressed to the
point where, in the opinion of ENGINEER as evidenced by his definitive certificate of substantial
completion, it is sufficiently complete, in accordance with the contract documents, so that the
work (or specified part) can be utilized for the purposes for which it was intended; or if there be
no such certificate issued, when final payment is due in accordance with paragraph 14.13. The
terms "substantially complete" and substantially completed" as applied to any work refer to
substantial completion thereof.
WORK: The entire completed construction or the various separately identifiable parts thereof
required to be furnished under the contract documents. Work is the result of performing services,
General Conditions Page 2
--1 Lal �-V11U1L1V115
Page 4
3.5 Neither CONTRACTOR nor any subcontractor, manufacturer, fabricator, supplier, or distributor
shall have or acquire any title to or ownership rights in any of the drawings, specifications, or
other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER; and
they shall not reuse any of them on extensions of the project, or any other project, without written
consent of OWNER and ENGINEER, and specific written verification or adaptation by
ENGINEER.
ARTICLE 4 — AVAILABILITY OF LANDS,• PHYSICAL CONDITIONS• REFERENCE POINTS
AVAILABILITY OF LANDS:
4.1 OWNER shall furnish, as indicated in the contract documents, the lands upon which the work is
to be performed, rights-of-way for access thereto, and such other lands which are designated for
the use of CONTRACTOR. Easements for permanent structures, or permanent changes in
existing facilities, will be obtained and paid for by OWNER, unless otherwise provided in the
contract documents. If CONTRACTOR believes that any delay in OWNER'S furnishing these
lands or easements entitles him to an extension of the contract time, CONTRACTOR may make a
claim therefore as provided in Article 12. This shall be CONTRACTOR's sole remedy and
CONTRACTOR shall not be entitled to a price increase for said delay. CONTRACTOR shall
provide for all additional lands and access hereto that may be required for temporary construction
facilities or storage of materials and equipment.
PHYSICAL CONDITIONS — INVESTIGATIONS AND REPORTS:
4.2 Reference is made to the supplementary conditions for identification of those reports of
investigations and tests of subsurface and latent physical conditions at the site or otherwise
affecting cost, progress, or performance of the work which have been relied upon by ENGINEER
in the preparation of the drawings and specifications. Such reports are not part of the contract
documents.
UNFORESEEN PHYSICAL CONDITIONS:
4.3 CONTRACTOR shall promptly notify OWNER and ENGINEER in writing of any subsurface or
latent physical conditions at the site or in an existing structure differing materially from those
indicated or referred to in the contract documents. ENGINEER will promptly review those
conditions and advise OWNER in writing if further investigation or tests are necessary. Promptly
thereafter, OWNER shall obtain the necessary additional investigations and tests, and furnish
copies to ENGINEER and CONTRACTOR. If ENGINEER finds that the results of such
investigations or tests indicate that there are subsurface or latent physical conditions which differ
materially from those intended in the contract documents, and which could not reasonably have
been anticipated by CONTRACTOR, a change order shall be issued incorporating the necessary
revisions.
REFERENCE POINTS:
4.4 OWNER shall provide engineering surveys for construction to establish reference points which in
his judgment are necessary to enable CONTRACTOR to proceed with the work.
CONTRACTOR shall be responsible for laying out the work (unless otherwise specified in the
general requirements), shall protect and preserve the established reference points, and shall make
no changes nor relocations without the prior written approval of OWNER. CONTRACTOR shall
report to ENGINEER whenever any reference point is lost or destroyed or requires relocation
General Conditions Page 5
because of necessary changes in grades or locations, and shall be responsible for replacement or
relocation of such reference points by professional qualified personnel.
ARTICLE 5 — BONDS AND INSURANCE
PERFORMANCE AND OTHER BONDS:
5.1 CONTRACTOR shall furnish performance and payment bonds, each in an amount at least equal
to the contract price as security for the faithful performance and payment of all
CONTRACTOR'S obligations under the contract documents. These bonds shall remain in effect
at least until two years after the date of final payment, except as otherwise provided by law.
CONTRACTOR shall also furnish other bonds as are required by the Contract Documents. All
bonds shall be in the forms prescribed by the Contract Documents, and be executed by such
sureties as (a) are licensed to conduct business in the state where the project is located, and (b) are
named in the current list of "Companies Holding Certificates of Authority as Acceptable Sureties
on Federal Bonds and as Acceptable Reinsuring Companies" as published in Circular 570
(amended) by the Audit Staff Bureau of Accounts, U.S. Treasury Department. All bonds signed
by an agent must be accompanied by a certified copy of the authority to act.
5.2 If the surety on any bond furnished by CONTRACTOR is declared bankrupt, or becomes
insolvent, or its right to do business is terminated in any state where any part of the project is
located, or it ceases to meet the requirements of clauses (a) and (b) of paragraph 5. 1,
CONTRACTOR shall within five days thereafter substitute another bond and surety, both of
which shall be acceptable to OWNER.
INSURANCE:
5.3 CONTRACTOR'S Liability Insurance: The CONTRACTOR shall purchase and maintain such
insurance as will protect him from claims set forth below which may arise out of or result from
the CONTRACTOR'S operations under the contract, whether such operations be by himself, or
by any subcontractor, or by anyone directly or indirectly employed by any of them, or by anyone
for whose acts any of them may be liable.
All such insurance shall remain in effect until final payment, and at all times thereafter when
CONTRACTOR may be correcting, removing, or replacing defective work in accordance with
paragraph 13.12. In addition, CONTRACTOR shall maintain such completed operations
insurance for at least two years after final payment, and furnish OWNER with evidence of
continuation of such insurance at final payment and one year thereafter.
5.3.1 Claims under Workmen's Compensation, disability benefits, and other similar employee
benefit acts;
5.3.2 Claims for damage because of bodily injury, occupational sickness or disease, or death of
his employees, and claims insured by usual personal injury liability coverage;
5.3.3 Claims for damage because of bodily injury, sickness or disease, or death of any person
other than his employees, and claims insured by usual personal injury liability coverage;
and
5.3.4 Claims for damages because of injury to or destruction of tangible property, including
loss of use resulting therefrom.
General Conditions Page 6
Workmen's Compensation insurance shall provide coverage as required by the laws of
the State of Colorado.
Insurance covering claims for damages to persons or property required by the preceding
paragraph (except subparagraph 5.3. 1) shall be in the following minimum amounts:
Bodily Injury Liability:
Each Person: $1,000,000
Each Accident or Occurrence: $2,000,000
Property Damage Liability:
Each Accident or Occurrence: $1,000,000
Aggregate: $2,000,000
and shall be furnished in types specified as follows:
5.3.5 CONTRACTOR'S Liability Insurance issued to and covering the liability for damage
imposed by law upon the CONTRACTOR and each subcontractor with respect to all
work performed by them under the agreement (construction contract).
5.3.6 CONTRACTOR'S Protective Liability Insurance issued to and covering the liability for
damages imposed by law upon the CONTRACTOR and each subcontractor with respect
to all work under the agreement (construction contract) performed for the
CONTRACTOR by subcontractors.
5.3.7 Completed Operations Liability Insurance issued to and covering the liability for damage
imposed by law upon the CONTRACTOR and each subcontractor arising between the
date of final cessation of the work, and the date of final acceptance thereof out of that part
of the work performed by each.
5.3.8 Comprehensive Automobile Insurance shall be carried in the amount of
$500,000/$1,000,000 for bodily injury and $500,000 for property damage, each
occurrence. All liability and property damage insurance required hereunder shall be
Comprehensive General and Automobile Bodily Injury and Property Damage form of
policy.
5.3.9 The CONTRACTOR shall in addition, and in the amounts required under the above,
obtain Protective Liability Insurance issued to and covering the liability for damages
imposed by law upon the OWNER with respect to all operations under the construction
contract by the CONTRACTOR or his subcontractors, including omissions and
supervisory acts by the OWNER.
5.4 Comprehensive Risk Policy Option: In lieu of the several policies specified for
CONTRACTOR'S Liability Insurance, a comprehensive liability and property damage insurance
policy inclusive of all the insurance and requirements hereinafter set forth, with an umbrella
covering of $2,000,000, subject to the approval of the OWNER, will be permissible.
5.5 Subcontractor's Insurance: Before permitting any of his subcontractors to perform any work
under this contract, CONTRACTOR shall either (a) require each of his subcontractors to procure
and maintain during the life of his subcontracts, Subcontractor's Public Liability and Property
Damage Insurance of the types and in the amounts as may be applicable to his work, which type
General Conditions Page 7
and amounts shall be subject to the approval of the OWNER, or (b) insure the activities of his
subcontractors in his own policy.
5.6 Builder's Risk Insurance: Insofar as the work to be performed under this contract consists
entirely of new construction removed and separated from any existing facility used by OWNER,
CONTRACTOR shall procure and maintain, for the duration of the work of this project, Builder's
Risk Insurance, including the perils of fire, extended coverage (loss due to vehicles, explosion,
wind, flood, riot, etc.), vandalism and malicious mischief, and special extended coverage (loss
due to falling objects, collapse, water damage from faulty or leaking systems, etc.) in the full
amount of the contract price plus the cost of authorized extras. Said amount of insurance
coverage shall be considered to cover the insurable value of the work under this contract which is
considered not to exceed one hundred percent (100%) of the amount of this contract and
authorized extras. Such policy shall not insure any tools or equipment, or temporary structures
erected at the site and belonging to any person or persons, or their subcontractors who are obliged
by contract with the OWNER to do work on the projects.
Such insurance shall be placed jointly in the names of the OWNER, CONTRACTOR, and any
and all subcontractors, and any and all others obliged by contract with the OWNER to do work on
this project and at the OWNER'S option, any other person or persons whom the OWNER deems
to have an insurable interest in said property, or any part thereof, payable as their several interests
may appear. CONTRACTOR shall furnish OWNER with certification of said insurance prior to
commencement of any work. Any proceeds obtained from insurance provided for by this
paragraph shall be paid to and held by the OWNER as trustee. The OWNER shall have the right
to withhold payment of such proceeds until such time as the work destroyed or damaged and
covered by such insurance shall be reconstructed and shall pay such proceeds on an installment
basis similar to that provided for by progress payments covering the original work.
5.7 Certificates of Insurance: Certificates of Insurance acceptable to the OWNER shall be filed with
the OWNER prior to commencement of the work. These Certificates shall contain provisions
naming the OWNER as an additional insured under CONTRACTOR'S insurance, as more fully
required by the General Conditions herein, and that coverage afforded under the policies will not
be cancelled until at least thirty days prior written notice has been given the OWNER.
CONTRACTOR and his subcontractors shall not permit any of his subcontractors to start work
until all required insurance have been obtained and certificates with the proper endorsements
have been fled with the OWNER. Failure of the CONTRACTOR to comply with the foregoing
insurance requirement shall in no way waive the OWNER'S rights hereunder.
5.8 Owner's Liability Insurance: The OWNER, at his option, may purchase and maintain such
liability insurance as will protect him against claims which may arise from operations under this
contract. Purchasing and maintaining such insurance, however, will not relieve the
CONTRACTOR from purchasing and maintaining the insurance hereinbefore specified.
5.9 Loss of Use of Insurance: The OWNER, at his option, may purchase and maintain such
insurance as will insure him against loss of use of his property due to fire or other hazards,
however caused.
ARTICLE 6 — CONTRACTOR'S RESPONSIBILITIES
SUPERVISION AND SUPERINTENDENCE:
General Conditions
Page 8
6.1 CONTRACTOR shall supervise and direct the work competently and efficiently, devoting such
attention thereto and applying such skills and expertise as may be necessary to perform the work
in accordance with the contract documents. CONTRACTOR shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction, but CONTRACTOR
shall not be solely responsible for the negligence of others in the design or selection of a specific
means, method, technique, sequence, or procedure of construction which is indicated in and
required by the contract documents. CONTRACTOR shall be responsible to see that the finished
work complies accurately with the contract documents.
6.2 CONTRACTOR shall keep on the work at all times during its progress a competent resident
superintendent, who shall not be replaced without written notice to OWNER and ENGINEER
except under extraordinary circumstances. The superintendent will be CONTRACTOR'S
representative at the site and shall have authority to act on behalf of CONTRACTOR. All
communications given to the superintendent shall be as binding as if given to CONTRACTOR.
LABOR, MATERIALS AND EQUIPMENT:
6.3 CONTRACTOR shall provide competent, suitably qualified personnel to survey and lay out the
work, and perform construction as required by the contract documents. CONTRACTOR shall at
all times maintain good discipline and order at the site. Except in connection with the safety or
protection of persons, or the work, or property at the site or adjacent thereto, and except as
otherwise indicated in the supplementary conditions, all work at the site shall be performed
during regular working hours and CONTRACTOR will not permit overtime work or the
performance of work on Saturday, Sunday, or any legal holiday without OWNER'S written
consent given after prior written notice to ENGINEER.
6.4 Colorado labor shall be employed to perform the work to the extent of not less than eighty
percent of each type or class of labor in the several classifications of skilled and common labor
employed on the project. "Colorado labor" means any person who is a resident of the state of
Colorado, at the time of employment, without discrimination as to race, color, creed, sex, age, or
religion except when sex or age is a bona fide occupational qualification.
6.5 CONTRACTOR shall furnish all materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, and
sanitary facilities, and all other facilities and incidentals necessary for the execution, testing,
initial operation, and completion of work.
6.6 All materials and equipment shall be of good quality and new, except as otherwise provided in
the contract documents. If required by ENGINEER, CONTRACTOR shall furnish satisfactory
evidence (including reports of required test) as to the kind and quality of materials and
equipment.
6.7 All materials and equipment shall be applied, installed, connected, erected, used, cleaned, and
conditioned in accordance with the instructions of the applicable manufacturer, fabricator,
supplier, or distributor, except as otherwise provided in the contract documents.
EQUIVALENT MATERIALS AND EQUIPMENT:
6.8 Whenever materials or equipment are specified or described in the drawings or specifications by
using the name of a proprietary item, or the name of a particular manufacturer, fabricator,
supplier, or distributor, the naming of the item is intended to establish the type, function, and
quality required. Unless the name is followed by words indicating that no substitution is
General Conditions Page 9
permitted, materials or equipment of other manufacturers, fabricators, suppliers, or distributors
may be accepted by ENGINEER if sufficient information is submitted by CONTRACTOR to all
ENGINEER to determine that the material or equipment proposed is equivalent to that named.
The procedure for review by ENGINEER will be as set forth in paragraphs 6.8.1 and 6.8.2 below
as supplemented in the general requirements.
6.8.1 Requests for review of substitute items of material and equipment will not be accepted by
ENGINEER from anyone other than CONTRACTOR. If CONTRACTOR wishes to
furnish or use a substitute item of material or equipment, CONTRACTOR shall make
written application to ENGINEER for acceptance thereof, certifying that the proposed
substitute will perform adequately the functions called for by the general design, be
similar and of equal substance to that specified and be suited to the same use and capable
of performing the same function as that specified. The application will state whether or
not acceptance of the substitute for use in the work will require a change in the drawings
or specifications to adapt the design to the substitute and whether or not incorporation or
use of the substitute in connection with the work I subject of payment of any license fee
or royalty. All variations of the proposed substitute from that specified shall be identified
in the application and available maintenance, repair and replacement service will be
indicated. The application will also contain an itemized estimate of all costs or savings
that will result directly or indirectly from acceptance of such substitute, including costs of
redesign and claims of other contractors affected by the resulting change, all of which
shall be considered by ENGINEER in evaluating the proposed substitute. ENGINEER
may require CONTRACTOR to furnish, at CONTRACTOR'S expense, additional data
about the proposed substitute. ENGINEER will be the sole judge of acceptability, and no
substitute will be ordered or installed without ENGINEER'S prior written acceptance.
OWNER may require CONTRACTOR to furnish, at CONTRACTOR'S expense, a
special performance guarantee or other surety with respect to any substitute.
6.8.2 ENGINEER will record time required by ENGINEER and ENGINEER'S consultants in
evaluating substitutions proposed by CONTRACTOR and in making changes in the
drawings or specifications occasioned thereby, whether or not ENGINEER accepts a
proposed substitute. CONTRACTOR shall reimburse OWNER for the charges of
ENGINEER and ENGINEER'S consultants for evaluating any proposed substitute.
CONCERNING SUBCONTRACTORS:
6.9 CONTRACTOR shall not employ any subcontractor or other person or organization (including
those who are to furnish the principal items of materials or equipment), whether initially or as a
substitute, against whom OWNER or ENGINEER may have reasonable objection. A
subcontractor or other person or organization identified in writing to OWNER and ENGINEER
by CONTRACTOR prior to the Notice of Award, and not objected to in writing by OWNER or
ENGINEER prior to the Notice of Award, will be deemed acceptable to OWNER and
ENGINEER. Acceptance of any subcontractor, other person or organization by OWNER or
ENGINEER shall not constitute a waiver of any right of OWNER or ENGINEER to reject
defective work. If OWNER or ENGINEER, after due investigation, has reasonable objection to
any subcontractor, or other person or organization proposed by CONTRACTOR after the Notice
of Award, CONTRACTOR shall submit an acceptable substitute, and the contract price shall be
increased or decreased by the difference in cost occasioned by such substitution, and an
appropriate change order shall be issued. CONTRACTOR shall not be required to employ any
subcontractor, other person or organization against whom CONTRACTOR has reasonable
objection.
General Conditions
Page 10
6.10 CONTRACTOR shall be fully responsible for all acts and omissions of his subcontractors, and of
( persons and organizations directly or indirectly employed by them, and of persons and
organizations for whose acts any of them may be liable to the same extent that CONTRACTOR is
responsible for the acts and omissions of persons directly employed by CONTRACTOR.
Nothing in the contract documents shall create a contractual relationship between OWNER or
ENGINEER and any subcontractor or other person or organization having a direct contract with
CONTRACTOR, nor shall it create any obligation on the part of OWNER or ENGINEER to pay
or to see to the payment of any monies due any subcontractor, or other person or organization,
except as may otherwise by required by law. OWNER or ENGINEER may furnish to any
subcontractor or other person or organization, to the extent practicable, evidence of amounts paid
to CONTRACTOR on account of specific work done.
6.11 The divisions and sections of the specifications and the identifications of any drawings shall not
control CONTRACTOR in dividing the work among subcontractors, or delineating the work to
be performed by any specific trade.
6.12 All work performed for CONTRACTOR by a subcontractor will be pursuant to an appropriate
agreement between CONTRACTOR and the subcontractor which specifically binds the
subcontractor to the applicable terms and conditions of the contract documents for the benefit of
the OWNER and ENGINEER. CONTRACTOR shall pay each subcontractor a just share of any
insurance monies received by CONTRACTOR on account of losses under policies issued
pursuant to paragraph 5.6.
PATENT FEES AND ROYALTIES:
6.13 CONTRACTOR shall pay all license fees and royalties, and assume all costs incident to the use
in the performance of the work, or the incorporation in the work of any invention, design,
process, product, or device which is the subject of patent rights or copyrights held by others. If a
particular invention, design, process, product, or device is specified in the contract documents for
use in the performance of the work, and if to the actual knowledge of OWNER or ENGINEER its
use is subject to patent rights or copyrights calling for the payment of any license fee or royalty to
others, the existence of such rights shall be disclosed by OWNER in the contract documents.
CONTRACTOR shall indemnify and hold harmless OWNER and ENGINEER and anyone
directly or indirectly employed by either of them from and against all claims, damages, losses,
and expenses (including attorney's fees) arising out of any infringement of patent rights or
copyrights incident to the sue in the performance of the work, or resulting from the incorporation
in the work of any invention, design, process, product, or device not specified in the contract
documents, and shall defend all such claims in connection with any alleged infringement of such
rights.
PERMITS:
6.14 Unless otherwise provided in the Contract Documents, CONTRACTOR shall obtain and pay for
all construction permits and licenses. OWNER shall assist CONTRACTOR, when necessary, in
obtaining such permits and licenses. CONTRACTOR shall pay all governmental charges and
inspection fees necessary for the prosecution of the work, which are applicable at the time of
opening of bids. CONTRACTOR shall pay all charges of utility service companies for
connections to the work, and OWNER shall pay all charges of such companies for capital costs
related thereto.
LAWS AND REGULATIONS:
General Conditions Page 11
6.15 CONTRACTOR shall give all notices and comply with all laws, ordinances, rules, and
regulations applicable to the work. If CONTRACTOR observes that the specifications or
drawings are at variance therewith, CONTRACTOR shall give ENGINEER prompt written
notice thereof, and any necessary changes shall be adjusted by an appropriate modification. If
CONTRACTOR performs any work knowing, or having reason to know, that it is contrary to
such laws, ordinances, rules, and regulations, and without such notice to ENGINEER,
CONTRACTOR shall bear all costs arising therefrom; however, it shall not be CONTRACTOR'S
primary responsibility to make certain that the specifications and drawings are in accordance with
such laws, ordinances, rules, and regulations.
TAXES:
6.16 CONTRACTOR shall pay all sales, consumer, use, and other similar taxes required to be paid by
him in accordance with the law of the place of the project.
USE OF PREMISES:
6.17 CONTRACTOR shall confine construction equipment, the storage of materials and equipment,
and the operations of workmen to areas permitted by law, ordinances, permits, or the
requirements of the contract documents, and shall not unreasonably encumber the premises with
construction equipment or other materials or equipment.
6.18 During the progress of the work, CONTRACTOR shall keep the premises free from
accumulations of waste materials, rubbish, and other debris resulting from the work. At the
completion of the work, CONTRACTOR shall remove all waste materials, rubbish, and debris
from and about the premises as well as all tools, appliances, construction equipment, and
machinery, and surplus materials, and shall leave the site clean and ready for occupancy by
OWNER. CONTRACTOR shall restore to their original condition those portions of the site not
designated for alteration by the contract documents.
6.19 CONTRACTOR shall not load, nor permit any part of any structure to be loaded, in any manner
that will endanger the structure, nor shall CONTRACTOR subject any part of the work or
adjacent property to stresses or pressures that will endanger it.
RECORD DOCUMENTS:
6.20 CONTRACTOR shall keep one record copy of all specifications, drawings, addenda,
modifications, shop drawings, and samples at the site in good order and annotated to show all
changes made during the construction process. These shall be available to ENGINEER for
examination and shall be delivered to ENGINEER for OWNER upon completion of the work.
SAFETY AND PROTECTION:
6.21 CONTRACTOR shall be responsible for initiating, maintaining, and supervising all safety
precautions and programs in connection with the work. CONTRACTOR shall take all necessary
precautions for the safety of, and shall provide the necessary protection to prevent damage,
injury, or loss to:
6.21.1 all employees on the work and other persons who may be affected thereby,
6.21.2 all the work and all materials or equipment to be incorporated therein, whether in storage
on or off the site, and
General Conditions Page 12
6.21.3 other property at the site, or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, and utilities not designated for removal, relocation or
replacement in the course of construction. CONTRACTOR shall comply with all
applicable laws, ordinances, rules, regulations, and orders of any public body having
jurisdiction for the safety of persons or property, or to protect them from damage, injury,
or loss; and shall erect and maintain all necessary safeguards for such safety and
protection. CONTRACTOR shall notify owners of adjacent property and utilities when
prosecution of the work may affect them. All damage, injury, or loss to any property
referred to in paragraph 6.21.2 or 6.21.3 caused, directly or indirectly, in whole or in part,
by CONTRACTOR, any subcontractor, or anyone directly or indirectly employed by any
of them, or anyone for whose acts any of them may be liable, shall be remedied by
CONTRACTOR (except damage or loss attributable to the fault of drawings or
specifications, or to the acts or omissions of OWNER or ENGINEER, or anyone
employed by either of them, or anyone for whose acts either of them may be liable, and
not attributable, directly or indirectly, in whole or in part, to the fault or negligence of
CONTRACTOR). CONTRACTOR'S duties and responsibilities for the safety and
protection of the work shall continue until such time as all the work is completed and
ENGINEER has issued a notice to OWNER and CONTRACTOR, in accordance with
paragraph 14.13, that the work is acceptable.
6.22 CONTRACTOR shall designate a responsible member of his organization at the site whose duty
shall be the prevention of accidents. This person shall be CONTRACTOR'S superintendent,
unless otherwise designated in writing by CONTRACTOR to OWNER.
EMERGENCIES:
6.23 In emergencies affecting the safety or protection of persons, or the work, or property at the site or
adjacent thereto, CONTRACTOR, without special instruction or authorization from ENGINEER
to OWNER, is obligated to act to prevent threatened damage, injury, or loss. CONTRACTOR
shall give ENGINEER prompt written notice of any significant changes in the work, or deviations
from the contract documents caused thereby.
SHOP DRAWINGS AND SAMPLES:
6.24 After checking and verifying all field measurements, CONTRACTOR shall submit to
ENGINEER for review and approval, in accordance with the accepted schedule of shop drawing
submissions, five copies (unless otherwise specified in the general requirements) of all shop
drawings, which shall have been checked by, and stamped with the approval of, CONTRACTOR,
and identified as ENGINEER may require. The data shown on the shop drawings will be
complete with respect to dimensions, design criteria, materials of construction, and like
information to enable ENGINEER to review the information as required.
6.25 CONTRACTOR shall also submit to ENGINEER for review and approval, with such promptness
as to cause no delay in work, all samples required by the contract documents. All samples will
have been checked by, and stamped with the approval, of CONTRACTOR, identified clearly as
to material, manufacturer, and any pertinent catalog numbers, and the use for which intended.
6.26 At the time of each submission, CONTRACTOR shall, in writing, call ENGINEER'S attention to
any deviations that the shop drawings or samples may have from the requirements of the contract
documents.
General Conditions
Page 13
6.27 ENGINEER will review and approve, with reasonable promptness, shop drawings and samples,
( but ENGINEER'S review and approval shall be only for conformance with the design concept of
the project, and for compliance with the information given in the contract documents, and shall
not extend to means, methods, sequences, techniques, or procedures of construction, or to safety
precautions of programs incident thereto. The review and approval of a separate item as such will
not indicate approval of the assembly in which the item functions. CONTRACTOR shall make
any corrections required by ENGINEER, and shall return the required number of corrected copies
of shop drawings, and resubmit new samples for review and approval. CONTRACTOR shall
direct specific attention in writing to revisions other than the corrections called for by
ENGINEER on previous submittals. CONTRACTOR'S stamp of approval on any shop drawing
or sample shall constitute a representation to OWNER and ENGINEER that CONTRACTOR has
either determined and verified all quantities, dimensions, field construction criteria, materials
catalog numbers, and similar data, or assumes full responsibility for doing so, and that
CONTRACTOR has reviewed or coordinated each shop drawing or sample with the requirements
of the work and the contract documents.
6.28 Where a shop drawing or sample is required by the specifications, no related work shall be
commenced until the submittal has been reviewed and approved by ENGINEER.
6.29 ENGINEER'S review and approval of shop drawings or samples shall not relieve
CONTRACTOR from responsibility for any deviations from the contract documents unless
CONTRACTOR has, in writing, called ENGINEER'S attention to such deviation at the time of
submission, and ENGINEER has given written concurrence and approval to the specific
deviation, nor shall any concurrence or approval by ENGINEER relive CONTRACTOR from
responsibility for errors or omissions in the shop drawings.
CONTINUING THE WORK:
6.30 CONTRACTOR shall carry on the work and maintain the progress schedule during all disputes or
disagreements with OWNER. No work shall be delayed or postponed pending resolution of any
disputes or disagreements, except as CONTRACTOR and OWNER may otherwise agree in
writing.
INDEMNIFICATION:
6.31 To the fullest extent permitted by law, CONTRACTOR shall indemnify and hold harmless
OWNER and ENGINEER, and their agents and employees, from and against all claims, damages,
losses, and expenses including, but not limited to, attorney's fees arising out of, or resulting from,
the performance of the work, provided that any such claim, damage, loss, or expense (a) is
attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible
property (other than the work itself) including the loss of use resulting therefrom, and (b) is
caused, in whole or in part, by any negligent act or omission of CONTRACTOR, any
subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts
any of them may be liable, regardless of whether or not it is caused in part by a party indemnified
hereunder. Nothing in the contract shall be interpreted that the OWNER waives its sovereign
immunity granted under C.R.S. 24-10-105.
6.32 In any and all claims against OWNER or ENGINEER, or any of their agents or employees, by
any employee of CONTRACTOR, any subcontractor, anyone directly or indirectly employed by
any of them, or anyone for whose acts any of them may be liable, the indemnification obligation
under paragraph 6.31 shall not be limited in any way by any limitation on the amount or type of
damages, compensation, or benefits payable by or for CONTRACTOR or any subcontractor
General Conditions
Page 14
under worker's or workmen's compensation acts, disability benefit acts, or other employee
benefit acts.
6.33 The obligations of CONTRACTOR under paragraph 6.31 shall not extend to the liability of
ENGINEER, his agents, or employees arising out of the preparation or approval of maps,
drawings, opinions, reports, surveys, change orders, designs, or specifications.
ARTICLE 7 — WORK BY OTHERS
7.1 OWNER may perform additional work related to the project by himself, or have additional work
performed by utility service companies, or let other direct contracts therefore which shall contain
general conditions similar to these. CONTRACTOR shall afford the utility service companies
and the other contractors who are parties to such direct contracts (or OWNER, if OWNER is
performing the additional work with OWNER'S employees) reasonable opportunity for the
introduction and storage of materials and equipment, and the execution of work, and shall
properly connect and coordinate his work with theirs.
7.2 If any part of CONTRACTOR'S work depends, for proper execution or results, upon the work of
any such other contractor or utility service company (or OWNER), CONTRACTOR shall inspect
and promptly report to ENGINEER in writing any patent or apparent defects or deficiencies in
such work that render it unsuitable for such proper execution and results CONTRACTOR'S
failure to so report shall constitute an acceptance of the other work as fit and proper for
integration with CONTRACTOR'S work, except for latent or nonapparent defects and
deficiencies in the other work.
7.3 CONTRACTOR shall do all cutting, fitting, and patching of his work that may be required to
make its several parts come together properly and integrate with such other work.
CONTRACTOR shall not endanger any work of others by cutting, excavating, or otherwise
altering their work, and will only cut or alter their work with the written consent of ENGINEER
and the others whose work will be affected.
7.4 If the performance of additional work by other contractors or utility service companies or
OWNER was not noted in the contract documents, written notice thereof shall be given to
CONTRACTOR prior to starting any such additional work. If CONTRACTOR believes that the
performance of such additional work by OWNER or others involves additional expense to
CONTRACTOR, or requires an extension of the contract time, CONTRACTOR may make a
claim therefore as provided in Articles 11 and 12.
ARTICLE 8 — OWNER'S RESPONS11B I 'IES
8.1 OWNER shall issue all communications to CONTRACTOR through ENGINEER.
8.2 In case of termination of the employment of ENGINEER, OWNER shall appoint an engineer
whose status under the contract documents shall be that of the former ENGINEER.
ARTICLE 9 — ENGINEER'S STATUS DURING CONSTRUCTION
OWNER'S REPRESENTATIVE:
General Conditions
Page 15
9.1 ENGINEER will be OWNER'S representative during the construction period. The duties and
responsibilities and the limitations of authority of ENGINEER as OWNER'S representative
during construction are set forth in the contract documents, and shall not be extended without
written consent of OWNER and ENGINEER.
VISITS TO SITE:
9.2 ENGINEER will make visits to the site at intervals appropriate to the various stages of
construction to observe the progress and quality of the executed work and to determine, in
general, if the work is proceeding in accordance with the contract documents. ENGINEER will
not be required to make exhaustive or continuous on-site inspections to check the quality or
quantity of the work. ENGINEER'S efforts will be directed toward providing for OWNER a
greater degree of confidence that the completed work will conform to the contract documents.
On the basis of such visits and on-site observations, as an experienced and qualified design
professional, ENGINEER will keep OWNER informed of the progress of the work, and will
endeavor to guard OWNER against defects and deficiencies in the work.
CLARIFICATIONS AND INTERPRETATIONS:
9.3 ENGINEER will issue, with reasonable promptness, such written clarifications or interpretations
of the contract documents (in the form of drawings or otherwise) as ENGINEER may determine
necessary, which shall be consistent with, or reasonably inferable from, the overall intent of the
contract documents.
If CONTRACTOR believes that a written clarification or interpretation justifies an increase in the
contract price or contract time, CONTRACTOR may make a claim therefore, as provided in
Article 11 or Article 12.
REJECTING DEFECTIVE WORK:
9.4 ENGINEER will have authority to disapprove or reject work which is defective, and will also
have authority to require special inspection or testing of the work as fabricated, installed, or
completed.
SHOP DRAWINGS, CHANGE ORDERS, AND PAYMENTS:
9.5 In connection with ENGINEER'S responsibility for shop drawings and samples, see paragraphs
6.24 through 6.29 inclusive.
9.6 In connection with ENGINEER'S responsibilities as to change orders, see Articles 10, 11, and 12.
9.7 In connection with ENGINEER'S responsibilities in respect to applications for payment, etc., see
Article 14.
PROJECT REPRESENTATION:
9.8 ENGINEER may utilize Resident Project Representative to assist ENGINEER in observing the
performance of the work. The duties, responsibilities, and limitations of authority of any such
Resident Project Representative and assistants will be as provided in the supplementary
conditions. If OWNER designates another agent to represent him at the site who is not
ENGINEER'S agent, the duties, responsibilities, and limitations of authority of such other person
will be as provided in the supplementary conditions.
General Conditions
Page 16
DECISIONS ON DISAGREEMENTS:
9.9 ENGINEER will be the initial interpreter of the requirements of the contract documents and judge
of the acceptability of the work thereunder. Claims, disputes, and other matters relating to the
acceptability of the work, or the interpretation of the requirements of the contract documents
pertaining to the execution and progress of the work, shall be referred initially to ENGINEER in
writing with a request for a formal decision which ENGINEER will render in writing within a
reasonable time.
LIMITATIONS ON ENGINEER'S RESPONSIBILITIES:
9.10 Neither ENGINEER'S authority to act under this Article 9, or elsewhere in the contract
documents, nor any decision made by ENGINEER in good faith either to exercise or not exercise
such authority shall give rise to any duty or responsibility of ENGINEER to CONTRACTOR,
any subcontractor, any manufacturer, fabricator, supplier, or distributor, or any of their agents or
employees, or any other person performing any of the work.
9.11 Whenever, in the contract documents, the terms "as ordered", "as directed", "as required", "as
allowed", or terms of like effect or import are used, or the adjectives "reasonable", "suitable",
"acceptable", "proper", or "satisfactory", or adjectives of like effect or import are used to
describe requirement, direction, review, or judgment of ENGINEER as to the work, it is intended
that such requirement direction, review, or judgment will be solely to evaluate the work for
compliance with the contract documents (unless there is a specific statement indicating
otherwise). The use of any such term or adjective never indicates that ENGINEER shall have
authority to supervise or direct performance of the work, or authority to undertake responsibility
contrary to the provisions of paragraphs 9.12 or 9.13.
9.12 ENGINEER will not be responsible for CONTRACTOR'S means, methods, techniques,
sequences or procedures of construction, or the safety precautions and programs incident thereto,
and ENGINEER will not be responsible for CONTRACTOR'S failure to perform the work in
accordance with the contract documents.
9.13 ENGINEER will not be responsible for the acts or omissions of CONTRACTOR, or of any
subcontractor, or of the agents or employees of any CONTRACTOR or subcontractor, or of any
other persons at the site or otherwise performing any of the work.
ARTICLE 10 — CHANGES IN THE WORK
10.1 Without invalidating the agreement, OWNER may, at any time or from time to time, order
additions, deletions, or revisions in the work; these will be authorized by change orders. Upon
receipt of a change order, CONTRACTOR shall proceed with the work involved. All such work
shall be executed under the applicable conditions of the contract documents. If any change order
causes an increase or decrease in the contract price, or an extension or shortening of the contract
time, an equitable adjustment will be made as provided in Article 11 or Article 12 on the basis of
a claim made by either party.
10.2 ENGINEER may authorize minor changes in the work, not involving an adjustment in the
contract price or the contract time, which are consistent with the overall intent of the contract
documents. These may be accomplished by a field order, and shall be binding on OWNER, and
General Conditions
Page 17
also on CONTRACTOR who shall perform the change promptly. If CONTRACTOR believes
that a field order justifies an increase in the contract price or contract time, CONTRACTOR may
make a claim therefore as provided in Article 11 or Article 12.
10.3 Additional work performed without authorization of a change order will not entitle
CONTRACTOR to an increase in the contract price, or an extension of the contract time, except
in the case of an emergency as provided in paragraph 6.23, and except as provided in paragraphs
10.2 and 13.9.
10.4 OWNER shall execute appropriate change orders prepared by ENGINEER covering changes in
the work which are required by OWNER, or required because of unforeseen physical conditions
or emergencies, or because of uncovering work found not to be defective, or as provided in
paragraphs 11.10 or 11.11.
10.5 If notice of any change affecting the general scope of the work or change in the contract price is
required by the provisions of any bond to be given to the surety, it will be CONTRACTOR'S
responsibility to so notify the surety, and the amount of each applicable bond shall be adjusted
accordingly. CONTRACTOR shall furnish proof of such adjustment to OWNER.
ARTICLE 11 — CHANGE OF CONTRACT PRICE
11.1 The contract price constitutes the total compensation (subject to authorized adjustments) payable
to CONTRACTOR for performing the work. All duties, responsibilities, and obligations
assigned to or undertaken by CONTRACTOR shall be at his expense without change in the
contract price.
11.2 The contract price may only be changed by a change order. Any claim for an increase in the
contract price shall be based on written notice delivered to OWNER and ENGINEER within ten
days of the occurrence of the event giving rise to the claim. Any change in the contract price
resulting from any such claim shall be incorporated in a change order.
11.3 No change orders or other form of order or directive which requires additional compensable work
to be performed may be issued or be effective unless accompanied by a written assurance to the
CONTRACTOR that lawful appropriations to cover the costs of the additional work have been
made.
11.4 The value of any work covered by a change order, or of any claim for an increase or decrease in
the contract price, shall be determined in one of the following ways:
11.4.1 Where the work involved is covered by unit prices contained in the contract documents,
by application of unit prices to the quantities of the items involved (subject to the
provisions of paragraph 11.10).
11.4.2 By mutual acceptance of a lump sum.
11.4.3 On the basis of the cost of the work (determined as provided in paragraphs 11.5 and
11. 6), plus a contractor's Fee for overhead and profit (determined as provided in
paragraph 11.7).
11.5 The term "Cost of the Work" means the sum of all costs necessarily incurred and paid by
CONTRACTOR in the proper performance of the work. Except as otherwise may be agreed to in
General Conditions Page 18
writing by OWNER, such costs shall be in amounts no higher than those prevailing in the locality
(` of the project, shall include only the following items, and shall not include any of the costs
itemized in paragraph 11.6:
11.5.1 Payroll costs for employees in the direct employ of CONTRACTOR in the performance
of the work under schedules of job classifications agreed upon by OWNER and
CONTRACTOR. Payroll costs for employees not employed full time on the work shall
be apportioned on the basis of their time spent on the work. Payroll costs shall include,
but not be limited to, salaries and wages, plus the cost of fringe benefits which shall
include social security contributions, unemployment, excise and payroll taxes, worker's
or workmen's compensation, health and retirement benefits, bonuses, sick leave, vacation
and holiday pay applicable thereto. Such employees shall include superintendents and
foremen at the site. The expenses of performing work after regular working hours, or on
Sunday or legal holidays, shall be included in the above only to the extent authorized by
OWNER.
11.5.2 Cost of all materials and equipment furnished and incorporated in the work, including
costs of transportation and storage thereof, and manufacturers' field services required in
connection therewith. All cash discounts shall accrue to CONTRACTOR unless
OWNER deposits funds with CONTRACTOR with which to make payments, in which
case, the cash discounts shall accrue to OWNER. All trade discounts, rebates and
refunds, and all returns from sale of surplus materials and equipment shall accrue to
OWNER, and CONTRACTOR shall make provisions so that they may be obtained.
11.5.3 Payments made by CONTRACTOR to the subcontractors for work performed by
subcontractors. If required by OWNER, CONTRACTOR shall obtain competitive bids
from subcontractors acceptable to CONTRACTOR, and shall deliver such bids to
OWNER, who will then determine, with the advice of ENGINEER, which bids will be
accepted. If a subcontract provides that the subcontractor is to be paid on the basis of
Cost of the Work Plus a Fee, the subcontractor's Cost of the Work shall be determined in
the same manner as CONTRACTOR'S Cost of the Work. All subcontracts shall be
subject to the other provisions of the contract documents insofar as applicable.
11.5.4 Supplemental costs including the following:
11.5.4.1 The proportion of necessary transportation, travel, and subsistence expenses of
CONTRACTOR'S employees incurred in discharge of duties connected with the
work.
11.5.4.2 Cost, including transportation and maintenance, of all materials, supplies,
equipment, machines, appliances, office and temporary facilities at the site, and
hand tools not owned by the workmen, which are consumed in the performance
of the work, and cost less market value of such items used but not consumed
which remain the property of CONTRACTOR.
11.5.4.3 Rentals of all construction equipment and machinery, and the parts thereof,
whether rented from CONTRACTOR or others in accordance with rental
agreements approved by OWNER with the advice of ENGINEER, and the costs
of transportation, loading, unloading, installation, dismantling and removal
thereof, all in accordance with terms of said rental agreements. The rental of any
such equipment, machinery or parts shall cease when the use thereof is no longer
necessary for the work.
General Conditions
Page 19
11.5.4.4 Sales, use, or similar taxes related to the work, and for which CONTRACTOR is
liable, imposed by any governmental authority.
11.5.4.5 Deposits lost for causes other than CONTRACTOR'S negligence, royalty
payments, and fees for permits and licenses.
11.5.4.6 Losses and damages (and related expenses), not compensated by insurance or
otherwise, to the work otherwise sustained by CONTRACTOR in connection
with the execution of the work, provided they have resulted from causes other
than the negligence of CONTRACTOR, any subcontractor, or anyone directly or
indirectly employed by any of them, or for whose acts any of them may be liable.
Such losses shall include settlements made with the written consent and approval
of OWNER. No such losses, damages, and expenses shall be included in the
Cost of the Work for the purpose of determining Contractor's Fee. If, however,
any such loss or damage requires reconstruction, and CONTRACTOR is placed
in charge thereof, CONTRACTOR shall be paid for services a fee proportionate
to that stated in paragraph 11.7.2.
11.5.4.7 The cost of utilities, fuel, and sanitary facilities at the site.
11.5.4.8 Minor expenses such as telegrams, long distance calls, telephone service at the
site, expressage and similar petty cash items in connection with the work.
11.5.4.9 Cost of premiums for additional bonds and insurance required because of
changes in the work.
11.6 The term "Cost of the Work" shall not include any of the following:
11.6.1 Payroll costs and other compensation of CONTRACTOR'S officers, executives,
principals (of partnership and sole proprietorship), general managers, engineers,
architects, estimators, lawyers, auditors, accountants, purchasing and contracting agents,
expediters, timekeepers, clerks, and other personnel employed by CONTRACTOR
whether at the site or in his principal or a branch office for general administration of the
work, and not specifically included in the agreed upon schedule of job classifications
referred to in subparagraph 11.5.1, all of which are to be considered administrative costs
covered by the Contractor's Fee.
11.6.2 Expenses of CONTRACTOR'S principal and branch office, other than CONTRACTOR'S
office at the site.
11.6.3 Any part of CONTRACTOR'S capital expenses including interest on CONTRACTOR'S
capital employed for the work, and charges against CONTRACTOR for delinquent
payments.
11.6.4 Cost of premiums for all bonds and for all insurance whether or not CONTRACTOR is
required by the contract documents to purchase and maintain the same (except for
additional bonds and insurance required because of changes in the work).
11.6.5 Costs due to the negligence of CONTRACTOR, any subcontractor, or anyone directly or
indirectly employed by any of them, or for whose acts any of them may be liable,
General Conditions
Page 20
including, but not limited to, the correction of defective work, disposal of materials or
equipment wrongly supplied, and making good any damage to property.
11.6.6 Other overhead or general expense costs of any kind, and the costs of any item not
specifically and expressly included in paragraph 11.5.
CONTRACTOR'S FEE:
11.7 The Contractor's Fee allowed to CONTRACTOR for overhead and profit shall be determined as
follows:
11.7.1 a mutually acceptable fixed fee.
11.8 The amount of credit to be allowed by CONTRACTOR to OWNER for any such change which
results in a net decrease in cost, will be the amount of the actual net decrease. When both
additions and credits are involved in any one change, the combined adjustment to overhead and
profit shall be figured on the basis of the net increase or decrease in allowable costs, if any.
ADJUSTMENT OF UNIT PRICES:
11.9 Whenever the cost of any work is to be determined pursuant to paragraphs 11.5 and 11. 6,
CONTRACTOR will submit, in form acceptable to ENGINEER, an itemized cost breakdown
together with supporting data.
11.10 Where the quantity of work with respect to any item that is covered by a unit price differs
materially and significantly from the quantity of such work indicated in the contract documents,
an appropriate change order shall be issued on recommendation of ENGINEER to adjust the unit
price.
CASH ALLOWANCES:
11.11 It is understood that CONTRACTOR has included in the contract price all allowances so named
in the contract documents, and shall cause the work so covered to be done by such subcontractors,
manufacturers, fabricators, suppliers, or distributors, and for such sums within the limit of the
allowances as may be acceptable to ENGINEER. Upon final payment, the contract price shall be
adjust as required, and an appropriate change order issued. CONTRACTOR agrees that the
original contract price includes such sums as CONTRACTOR deems proper for costs and profit
on account of cash allowances. No demand for additional cost or profit in connection therewith
will be valid.
ARTICLE 12 — CHANGE OF THE CONTRACT TIME
12.1 The contract time may only be changed by a change order. Any claim for an extension in the
contract time shall be based on written notice delivered to OWNER and ENGINEER within ten
days of the occurrence of the event giving rise to the claim. Any change in the contract time
resulting from any such claim shall be incorporated in a change order.
12.2 All time limits stated in the contract documents are of the essence of the agreement. The
provisions of Articles 11 and 12 are CONTRACTOR'S sole remedies for delay by any cause
whatsoever, including acts of OWNER.
General Conditions
Page 21
ARTICLE 13 — WARRANTY AND GUARANTEE: TESTS AND INSPECTION•
CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK
WARRANTY AND GUARANTEE:
13.1 CONTRACTOR warrants and guarantees to OWNER and ENGINEER that all work will be in
accordance with the contract documents and will not be defective. Prompt notice of all defects
shall be given to CONTRACTOR. All defective work, whether or not in place, may be rejected,
corrected, or accepted as provided in this Article 13.
ACCESS TO WORK:
13.2 ENGINEER, ENGINEER'S representatives, other representatives of OWNER, testing agencies,
and governmental agencies with jurisdictional interests will have access to the work at reasonable
times for their observation, inspection and testing. CONTRACTOR shall provide proper and safe
conditions for such access.
TESTS AND INSPECTIONS:
13.3 CONTRACTOR shall give ENGINEER timely notice of readiness of work for all required
inspections, tests or approvals.
13.4 If any law, ordinance, rule, regulation, code, or order of any public body having jurisdiction
requires any work (or part thereof) to specifically be inspected, tested, or approved,
CONTRACTOR shall assume full responsibility therefore, pay all costs in connection therewith,
and furnish ENGINEER the required certificates of inspection, testing, or approval.
CONTRACTOR shall also be responsible for and shall pay all costs in connection with any
inspection or testing required in connection with OWNER'S or ENGINEER'S acceptance of a
manufacturer, fabricator, supplier or distributor of materials or equipment proposed to be
incorporated in the work, or of materials or equipment submitted for approval prior to
CONTRACTOR'S purchase thereof for incorporation of the work. The cost of all other
inspections, tests, and approvals required by the contract documents shall be paid by OWNER
(unless otherwise specified).
13.5 Any inspections, tests, or approvals, other than those required by law, ordinance, rule, regulation,
code, or order of any public body having jurisdiction, shall be performed by organizations
acceptable to OWNER and CONTRACTOR (or by ENGINEER if so specified).
13.6 If any work that is to be inspected, tested, or approved is covered without written concurrence of
ENGINEER, it must, if requested by ENGINEER, be uncovered for observation. Such
uncovering shall be at CONTRACTOR'S expense, unless CONTRACTOR has given
ENGINEER timely notice of CONTRACTOR'S intention to cover such work and ENGINEER
has not acted with reasonable promptness in response to such notice.
13.7 Neither observations by ENGINEER nor inspections, tests, or approvals by others shall relieve
CONTRACTOR from his obligations to perform the work in accordance with the contract
documents.
UNCOVERING WORK:
General Conditions Page 22
13.8 If any work is covered contrary to the written request of ENGINEER, it must, if requested by
ENGINEER, be uncovered for ENGINEER'S observation and replaced at CONTRACTOR'S
expense.
13.9 If ENGINEER considers it necessary or advisable that covered work be observed by ENGINEER,
or inspected or tested by others, CONTRACTOR, at ENGINEER'S request, shall uncover,
expose, or otherwise make available for observation, inspection, or testing as ENGINEER may
require, that portion of the work in question, furnish all necessary labor, material, and equipment.
If it is found that such work is defective, CONTRACTOR shall bear all the expenses of such
uncovering, exposure, observation, inspection, and testing of satisfactory reconstruction,
including compensation for additional professional services, and an appropriate deductive change
order shall be issued. If, however, such work is not found to be defective, CONTRACTOR shall
be allowed an increase in the contract price, or an extension of the contract time, or both, directly
attributable to such uncovering, exposure, observation, inspection, testing, and reconstruction.
OWNER MAY STOP THE WORK:
13.10 If the work is defective, or CONTRACTOR fails to supply sufficient skilled workmen or suitable
materials or equipment, OWNER may order CONTRACTOR to stop the work, or any portion
thereof, until the cause for such order has been eliminated; however, this right of OWNER to stop
the work shall not give rise to any duty on the part of OWNER to exercise this right for the
benefit of CONTRACTOR or any other party.
CORRECTION OR REMOVAL OF DEFECTIVE WORK:
13.11 If required by ENGINEER, CONTRACTOR shall promptly, without cost to OWNER and as
specified by ENGINEER, either correct any defective work, whether or not fabricated, installed,
or completed, or, if the work has been rejected by ENGINEER, remove it from the site and
replace it with nondefective work in a manner acceptable to the ENGINEER.
TWO YEAR CORRECTION PERIOD:
13.12 If, within two years after the date of substantial completion, or such longer period of time as may
be prescribed by law, or by the terms of any applicable special guarantee required by the contract
documents, or by any other specific provision of the contract documents, any work is found to be
defective, CONTRACTOR shall promptly, without cost to OWNER, and in accordance with
OWNER'S written instructions, either correct such defective work, or, if it has been rejected by
OWNER, remove it from the site, and replace it with nondefective work. If CONTRACTOR
does not promptly comply with the terms of such instructions, or in an emergency where delay
would cause serious risk of loss or damage, OWNER may have the defective work corrected or
the rejected work removed and replaced, and all direct and indirect costs of such removal and
replacement, including compensation for additional professional services, shall be paid by
CONTRACTOR.
ACCEPTANCE OF DEFECTIVE WORK:
13.13 If, instead of requiring correction or removal and replacement of defective work, OWNER (and,
prior to ENGINEER'S recommendation of final payment, also ENGINEER) prefers to accept it,
OWNER may do so. In such case, if acceptance occurs prior to ENGINEER'S recommendation
of final payment, a change order shall be issued incorporating the necessary revisions in the
contract price; or, if the acceptance occurs after such recommendation, an appropriate amount
shall be paid by CONTRACTOR to OWNER.
General Conditions
Page 23
OWNER MAY CORRECT DEFECTIVE WORK:
13.14 If CONTRACTOR fails, within a reasonable time after written notice of ENGINEER, to proceed
to correct defective work, or to remove and replace rejected work as required by ENGINEER in
accordance with paragraph 13.11, or if CONTRACTOR fails to perform the work in accordance
with the contract documents (including any requirements of the progress schedule), OWNER
may, after seven days written notice to CONTRACTOR, correct and remedy any such deficiency.
In exercising his rights under this paragraph OWNER shall proceed expeditiously. To the extent
necessary to complete corrective and remedial action, OWNER may exclude CONTRACTOR
from all part of the site, take possession of all or part of the work, and suspend CONTRACTOR'S
services related thereto, take possession of CONTRACTOR'S tools, appliances, construction
equipment, and machinery at the site, and incorporate in the work all materials and equipment
stored at the site, or for which OWNER has paid CONTRACTOR, but which are stored
elsewhere. CONTRACTOR shall allow OWNER, OWNER'S representatives, agents, and
employees such access to the site as may be necessary to enable OWNER to exercise his rights
under this paragraph. All direct and indirect costs of OWNER in exercising such rights shall be
charged against CONTRACTOR in an amount verified by ENGINEER, and a change order shall
be issued incorporating the necessary revisions in the contract documents and a reduction in the
contract price. Such direct and indirect costs shall include, in particular but without limitation,
compensation for additional professional services required, and all costs of repair and
replacement of work of others destroyed or damaged by correction, removal, or replacement of
CONTRACTOR'S defective work. CONTRACTOR shall not be allowed an extension of the
contract time because of any delay in performance of the work attributable to the exercise by
OWNER of OWNER'S rights hereunder.
ARTICLE 14 — PAYMENTS TO CONTRACTOR AND COMPLETION
SCHEDULES:
14.1 At least ten days prior to submitting the first application for a progress payment, CONTRACTOR
shall (except as otherwise specified in the general requirements) submit to ENGINEER a progress
schedule, a final schedule of shop drawing submissions, and, where applicable, a schedule of
values of the work. These schedules shall be satisfactory in form and substance to ENGINEER.
The schedule of values shall include quantities and unit prices aggregating the contract price, and
shall subdivide the work into component parts in sufficient detail to serve as the basis for progress
payments during construction. Upon acceptance of the schedule of values by ENGINEER, it
shall be incorporated into a form of application for payment acceptable to ENGINEER.
APPLICATION FOR PROGRESS PAYMENT:
14.2 At least ten days before each progress payment falls due (but not more often than once a month),
CONTRACTOR shall submit to ENGINEER for review an application for payment filled out and
signed by CONTRACTOR covering the work completed as of the date of the application, and
accompanied by such supporting documentation as is required by the contract documents, and
also as ENGINEER may reasonably require. If payment is requested on the basis of materials
and equipment not incorporated in the work, but delivered and suitably stored at the site or at
another location agreed to in writing, the application for payment shall also be accompanied by
such data, satisfactory to OWNER, as will establish OWNER'S title to the material and
equipment, and protect OWNER'S interest therein, including applicable insurance. Each
General Conditions Page 24
subsequent application for payment shall include an affidavit of CONTRACTOR stating that all
previous progress payments received on account of the work have been applied to discharge in
full all of CONTRACTOR'S obligations reflected in prior applications for payment. The amount
of retainage with respect to progress payments will be as stipulated in the agreement.
CONTRACTOR'S WARRANTY OF TITLE:
14.3 CONTRACTOR warrants and guarantees that title to all work, materials, and equipment covered
by any application for payment, whether incorporated in the project or not, will pass to OWNER
at the time of payment free and clear of all liens, claims, security interests, and encumbrances
(hereafter in these General Conditions referred to as "Liens").
REVIEW OF APPLICATIONS FOR PROGRESS PAYMENT:
14.4 ENGINEER will, within ten days after receipt of each application for payment, either indicate in
writing a recommendation of payment and present the application to OWNER, or return the
application to CONTRACTOR indicating in writing ENGINEER'S reasons for refusing to
recommend payment. In the latter case, CONTRACTOR may make the necessary corrections
and resubmit the application. OWNER shall, within twenty days of presentation to him of the
application for payment with ENGINEER'S recommendation, pay CONTRACTOR the amount
recommended.
14.5 ENGINEER'S recommendation of any payment requested in an application for payment will
constitute a representation by ENGINEER to OWNER that, based on ENGINEER'S on-site
observations of the work in progress as an -experienced and qualified design professional, and on
ENGINEER'S review of the application for payment, and the accompanying data and schedules,
the work has progressed to the point indicated; that, to the best of ENGINEER'S knowledge,
information, and belief, the quality of the work is in accordance with the contract documents
(subject to an evaluation of the work as a functioning project upon substantial completion, and to
the results of any subsequent tests called for in the contract documents and any qualifications
stated in the recommendation); and, that CONTRACTOR is entitled to payment of the amount
recommended. However, by recommended any such payment, ENGINEER will not thereby be
deemed to have represented that exhaustive or continuous on-site inspections have been made to
check the quality or the quantity of work, or that the means, methods, techniques, sequences, and
procedures of construction have been reviewed, or that any examination has been made to
ascertain how or for what purpose CONTRACTOR has used the monies paid or to be paid to
CONTRACTOR on account of the contract price, or that title to any work, materials, or
equipment has passed to OWNER free and clear of any Liens.
14.6 ENGINEER'S recommendation of final payment will constitute an additional representation by
ENGINEER to OWNER that the conditions precedent to CONTRACTOR'S being entitled to
final payment as set forth in paragraph 14.13 have been fulfilled.
14.7 ENGINEER may refuse to recommend the whole, or any part of any payment if, in his opinion, it
would be incorrect to make such representations to OWNER. He may also refuse to recommend
any such payment, or, because of subsequently discovered evidence, or the results of subsequent
inspections or tests, nullify any such payment previously recommended to such extent as may be
necessary in ENGINEER'S opinion to protect OWNER from loss because:
14.7.1 the work is defective, or completed work has been damaged requiring correction or
replacement,
General Conditions Page 25
14.7.2 written claims have been made against OWNER, or Liens have been filed in connection
with the work,
14.7.3 the contract price has been reduced because of modifications,
14.7.4 OWNER has been required to correct defective work, or complete the work in
accordance with paragraph 13.14,
14.7.5 of CONTRACTOR'S unsatisfactory prosecution of the work in accordance with the
contract documents, or
14.7.6 CONTRACTOR'S failure to make payment to subcontractors, or for labor, materials, or
equipment.
SUBSTANTIAL COMPLETION:
14.8 When CONTRACTOR considers the entire work ready for its intended use, CONTRACTOR
shall, in writing to OWNER and ENGINEER, certify that the entire work is substantially
complete, and request that ENGINEER issue a certificate of substantial completion. Within a
reasonable time thereafter, OWNER, CONTRACTOR, and ENGINEER shall make an inspection
of the work to determine the status of completion. If ENGINEER does not consider the work
substantially complete, ENGINEER will notify CONTRACTOR in writing giving his reasons
therefor. If ENGINEER considers the work substantially complete, ENGINEER will prepare and
deliver to OWNER a tentative certificate of substantial completion which shall fix the date of
substantial completion. There shall be attached to the certificate a tentative list of items to be
completed or corrected before final payment. OWNER shall have seven days after receipt of the
tentative certificate during which he may make written objection to ENGINEER as to any
provisions of the certificate or attached list. If, after considering such objections, ENGINEER
concludes that the work is not substantially complete, ENGINEER will, within fourteen days
after submission of the tentative certificate to OWNER, notify CONTRACTOR in writing stating
his reasons therefor. If, after consideration of OWNER'S objections, ENGINEER considers the
work substantially complete, ENGINEER will, within said fourteen days, execute and deliver to
OWNER and CONTRACTOR a definitive certificate of substantial completion (with a revised
tentative list of items to be completed or corrected) reflecting such changes from the tentative
certificate as he believes justified after consideration of any objections from OWNER. At the
time of delivery of tentative certificate of substantial completion, ENGINEER will deliver to
OWNER and CONTRACTOR a written recommendation as to division of responsibilities
pending final payment between OWNER and CONTRACTOR with respect to security,
operation, safety, maintenance, heat, utilities, and insurance. Unless OWNER and
CONTRACTOR agree otherwise in writing and so inform ENGINEER prior to his issuing the
definitive certificate of substantial completion, ENGINEER'S aforesaid recommendation will be
binding on OWNER and CONTRACTOR until final payment.
14.9 OWNER shall have the right to exclude CONTRACTOR from the work after the date of
substantial completion, but OWNER shall allow CONTRACTOR reasonable access to complete
or correct items on the tentative list.
PARTIAL UTILIZATION:
14.10 Use by OWNER of completed portions of the work maybe accomplished prior to substantial
completion of all the work subject to the following:
General Conditions Page 26
14.10.1 OWNER, at any time, may request CONTRACTOR in writing to permit OWNER to use
{ any part of the work which OWNER believes to be substantially complete and which
may be so used without significant interference with construction of the other parts of the
work. If CONTRACTOR agrees, CONTRACTOR will certify to OWNER and
ENGINEER that said part of the work is substantially complete, and request ENGINEER
to issue a certificate of substantial completion for that part of the work. Within a
reasonable time thereafter, OWNER, CONTRACTOR, and ENGINEER shall make an
inspection of that part of the work to determine its status of completion. If ENGINEER
considers that part of the work to be substantially complete, ENGINEER will execute,
and deliver to OWNER and CONTRACTOR, a certificate to that effect, fixing the date of
substantial completion as to that part of the work, attaching thereto a tentative list of
items to be completed or corrected before final payment. Prior to issuing a certificate of
substantial completion as to part of the work, ENGINEER will deliver to OWNER and
CONTRACTOR a written recommendation as to the division of responsibilities pending
final payment between OWNER and CONTRACTOR with respect to security, operation,
safety, maintenance, utilities, and insurance for that part of the work which shall become
binding upon OWNER and CONTRACTOR at the time of issuing the definitive
certificate of substantial completion as to that part of the work, unless OWNER and
CONTRACTOR shall have otherwise agreed in writing. OWNER shall have the right to
exclude CONTRACTOR from any part of the work which ENGINEER has so certified to
be substantially complete, but OWNER shall allow CONTRACTOR reasonable access to
complete or correct items on the tentative list.
14.10.2 In lieu of the issuance of a certificate of substantial completion as to part of the work,
OWNER may take over operation of a facility constituting part of the work, whether or
not it is substantially complete, if such facility is functionally and separately usable;
provided that prior to any such takeover, OWNER and CONTRACTOR have agreed as
to the division of responsibilities between OWNER and CONTRACTOR for security,
operation, safety, maintenance, correction period, heat, utilities, and insurance with
respect to such facility.
14.10.3 No occupancy of part of the work, or taking over of operations of a facility will be
accomplished before the insurers providing the property insurance have acknowledged
notice thereof and in writing effected any changes in coverage necessitated thereby. The
insurers providing the property insurance shall consent by endorsement on the policy or
policies, but the property insurance shall not be cancelled or permitted to lapse on
account of any such partial use or occupancy.
FINAL INSPECTION:
14.11 Upon written notice from CONTRACTOR that the work is complete, ENGINEER will make a
final inspection with OWNER and CONTRACTOR, and will notify CONTRACTOR in writing
of all particulars in which this inspection reveals that the work is incomplete or defective.
CONTRACTOR shall immediately take such measures as are necessary to remedy such
deficiencies.
FINAL APPLICATION FOR PAYMENT:
14.12 After CONTRACTOR has completed all such corrections to the satisfaction of ENGINEER, and
delivered all maintenance and operating instructions, schedules, guarantees, bonds, certificates of
inspection, marked -up record documents, and other documents, all as required by the contract
General Conditions Page 27
documents, and after ENGINEER has indicated that the work is acceptable (subject to the
provisions of paragraph 14.14), CONTRACTOR may make application for final payment
following the procedure for progress payments. The final application for payment shall be
accompanied by all documentation called for in the contract documents, and such other data and
schedules as ENGINEER may reasonably require, together with complete and legally effective
releases or waivers (satisfactory to OWNER) of all liens arising out of, or filed in connection with
the work. In lieu thereof, and as approved by OWNER, CONTRACTOR may furnish receipts or
releases in full; an affidavit of CONTRACTOR that the releases and receipts include all labor,
services, material, and equipment for which lien could be filed, and that all payrolls, material, and
equipment bills, and other indebtedness connected with the work, for which OWNER or his
property might in any way be responsible, have been paid or otherwise satisfied; and consent of
the surety, if any, to final payment. If any subcontractor, manufacturer, fabricator, supplier, or
distributor fails to furnish a release or receipt in full, CONTRACTOR may furnish a bond or
other collateral satisfactory to OWNER to indemnify OWNER against any lien.
FINAL PAYMENT AND ACCEPTANCE:
14.13 If, on the basis of ENGINEER'S observation of the work during construction and final inspection,
and ENGINEER'S review of the final application for payment and accompanying documentation,
all as required by contract documents, ENGINEER is satisfied that the work has been completed
and CONTRACTOR has fulfilled all of his obligations under the contract documents,
ENGINEER will, within ten days after receipt of the final application for payment, indicate in
writing his recommendation of payment, and present the application to OWNER for payment.
Thereupon, ENGINEER will give written notice to OWNER and CONTRACTOR that the work
is acceptable subject to the provisions of paragraph 14.15. Otherwise, ENGINEER will return the
application to CONTRACTOR, indicating in writing the reasons for refusing to recommend final
payment, in which case CONTRACTOR shall make the necessary corrections, and resubmit the
application. If the application and accompanying documentation are appropriate as to form and
substance, OWNER shall, within thirty days after receipt thereof, pay CONTRACTOR the
amount recommended by ENGINEER.
CONTRACTOR'S CONTINUING OBLIGATION:
14.14 CONTRACTOR'S obligation to perform and complete the work in accordance with the contract
documents shall be absolute. Neither recommendation of any progress or final payment by
ENGINEER, nor the issuance of a certificate of substantial completion, nor any payment by
OWNER to CONTRACTOR under the contract documents, nor any use or occupancy of the
work or any part thereof by OWNER, nor any act of acceptance by OWNER, nor any failure to
do so, nor the issuance of a notice of acceptability by ENGINEER pursuant to paragraph 14.13,
nor any correction of defective work by OWNER shall constitute an acceptance of work not in
accordance with the contract documents or a release of CONTRACTOR'S obligation to perform
the work in accordance with the contract documents.
WAIVER OF CLAIMS:
14.15 The making and acceptance of final payment shall constitute:
14.15.1 a waiver of all claims by OWNER against CONTRACTOR, except claims arising from
unsettled liens, from defective work appearing after final inspection pursuant to
paragraph 14.11, or from failure to comply with the contract documents or the terms of
any special guarnatees specified therein; however, it shall not constitute a waiver by
General Conditions Page 28
OWNER of any rights in respect of CONTRACTOR'S continuing obligations under the
contract documents; and
14.15.2 a waiver of all claims by CONTRACTOR against OWNER other than those previously
made in writing and still unsettled.
ARTICLE 15 — SUSPENSION OF WORK AND TERMINATION
OWNER MAY SUSPEND WORK:
15.1 OWNER may, at any time and without cause, suspend the work, or any portion thereof, for a
period of not more than ninety days, by notice in writing to CONTRACTOR and ENGINEER
which shall fix the date on which work shall be resumed. CONTRACTOR shall resume the work
on the date so fixed. CONTRACTOR may, at the OWNER'S sole discretion, be allowed an
increase in the contract price, or an extension of the contract time, or both, directly attributable to
any suspension, if he makes a claim therefor as provided in Articles 11 and 12.
15.2 Upon the occurrence of any one or more of the following events:
15.2.1 if CONTRACTOR is adjudged bankrupt or insolvent,
15.2.2 if CONTRACTOR makes a general assignment for the benefit of creditors,
15.2.3 if a trustee or receiver is appointed for CONTRACTOR or for any of CONTRACTOR'S
property,
15.2.4 if CONTRACTOR files a petition to take advantage of any debtor's act, or to reorganize
under the bankruptcy or similar laws,
15.2.5 if CONTRACTOR repeatedly fails to supply sufficient skilled workmen, or suitable
materials or equipment,
15.2.6 if CONTRACTOR repeatedly fails to make prompt payments to subcontractors, or for
labor, materials, or equipment,
15.2.7 if CONTRACTOR disregards laws, ordinances, rules, regulations, or orders of any public
body having jurisdiction,
15.2.8 if CONTRACTOR disregards the authority of ENGINEER, or
15.2.9 if CONTRACTOR otherwise violates, in any substantial way, any provisions of the
contract documents,
OWNER may, after giving CONTRACTOR and his surety seven days written notice, terminate
the services of CONTRACTOR, exclude CONTRACTOR from the site, and take possession of
the work and of all CONTRACTOR'S tools, appliances, construction equipment, and machinery
at the site, and use the same to the full extent they could be used by CONTRACTOR (without
liability to CONTRACTOR for trespass or conversion), incorporate in the work all materials and
equipment stored at the site, or for which OWNER has paid CONTRACTOR but which are
stored elsewhere, and finish the work as OWNER may deem expedient. In such case,
CONTRACTOR shall not be entitled to receive any further payment until the work is finished. If
General Conditions
Page 29
the unpaid balance of the contract price exceeds the direct and indirect costs of completing the
work, including compensation for additional professional services, such excess shall be paid to
CONTRACTOR. If such costs exceed such unpaid balance, CONTRACTOR shall pay the
difference to OWNER. Such costs incurred by OWNER shall be verified by ENGINEER and
incorporated in a change order, but in finishing the work, OWNER shall not be required to obtain
the lowest figure for the work performed.
15.3 Where CONTRACTOR'S services have been so terminated by OWNER, the termination shall not
affect any rights of OWNER against CONTRACTOR then existing, or which may thereafter
accrue. Any retention or payment of monies due CONTRACTOR by OWNER will not release
CONTRACTOR from liability.
15.4 Upon seven days written notice to CONTRACTOR and ENGINEER, OWNER may, without
cause and without prejudice to any other right or remedy, elect to abandon the work and terminate
the agreement. In such case, CONTRACTOR shall be paid for all work executed and expenses
sustained through the date of termination.
CONTRACTOR MAY STOP WORK OR TERMINATE:
15.5 If, through no act or fault of CONTRACTOR, the work is suspended for a period of more than
ninety days by OWNER, or under an order of court or other public authority, or ENGINEER fails
to act on any application for payment within thirty days after it is submitted, or OWNER fails for
thirty days to pay CONTRACTOR any sum finally determined to be due, then CONTRACTOR
may, upon seven days written notice to OWNER and ENGINEER, terminate the agreement and
recover from OWNER payment for all work executed through the date of termination.
ARTICLE 16 —MISCELLANEOUS
GIVING NOTICE:
16.1 Whenever any provision of the contract documents requires the giving of written notice, it shall
be deemed to have been validly given if delivered in person to the individual, or to a member of
the firm, or to an officer of the corporation for whom it is intended, or if delivered at or sent by
registered or certified mail, postage prepaid, to the last business address known to the giver of the
notice.
COMPUTATION OF TIME:
16.2 When any period of time is referred to in the contract documents by days, it shall be calendar
days and be computed to exclude the first and include the last day of such period. If the last day
of any such period falls on a Saturday or Sunday, or on a day made a legal holiday by the law of
the applicable jurisdiction, such day shall be omitted from the computation.
GENERAL:
16.3 Should OWNER or CONTRACTOR suffer injury or damage to his person or property because of
any error, omission or act of the other party or of any of the other party's employees or agents, or
General Conditions
Page 30
others for whose acts the other party is legally liable, claim shall be made in writing to the other
party within a reasonable time of the first observances of such injury or damage.
16.4 The duties and obligations imposed by these general conditions and the rights and remedies
available hereunder to the parties hereto, and, in particular, but without limitation, the warranties,
guarantees, and obligations imposed upon CONTRACTOR by paragraphs 6.30, 13.1, 13.11,
13.14, 14.3, and 15.2, and all of the rights and remedies available to OWNER and ENGINEER
thereunder, shall be in addition to, and shall not be construed in any way as a limitation of, any
rights and remedies available to any or all of them which are otherwise imposed or available by
law or contract, by special warranty or guarantee, or by other provisions of this paragraph shall be
as effective as if repeated specifically in the contract documents in connection with each
particular duty, obligations, right and remedy to which they apply. All representations,
warranties, and guarantees made in the contract documents shall survive final payment and
termination or completion of this agreement.
General Conditions
Page 31
INDEX TO GENERAL CONDITIONS
ARTICLE OR
PARAGRAPH
Accessto the work................................................................... ......................13.2
...........................................
Addenda, definition of (see Specifications)..................................................................................................1
Agreement, definition of ..............................................
Application for Payment, definition of.......................................................................................................... l
Applicationfor Payment, Final..............................................................................................................14.12
Application for Progress Payment............................................................................................................14.2
Application for Progress Payment, review of.................................................................................. 14.4-14.7
Availabilityof Lands..................................................................................................................................4.1
Award, Notice of, defined.............................................................................................................................1
BeforeStarting Construction............................................................................................................... 2.5-2.7
Bid, definition of..........................................................................................
Bonds and Insurance, in General...................................................................................................................5
Bonds, definition of....................................................................................................................................... l
Bonds, delivery of .................................
Bonds, Performance and Other.........................................................................................................5.1 & 5.2
CashAllowances....................................................................................................................................11.11
ChangeOrder, definition of........................................................................................................................... l
Changesin the Work...........................................................................................
Claims, Waiver of — on Final Payment...................................................................................................14.15
Clarifications and Interpretations...............................................................................................................9.3
Cleaning.................................................................................................................................................... 6.18
Completion.........................................................................
Completion, Substantial...............................................................................................................14.8 & 14.9
Conference, Pre-Construction....................................................................................................................2.8
Construction Machinery, Equipment, Etc................................................6.5
...................................................
Continuing Work......................................................................................................................................6.30
ContractDocuments, definition of................................................................................................................ l
Contract Documents, Intent and Reuse.........................................................................................................3
ContractDocuments, Reuse of...................................................................................................................3.5
ContractPrice, Change of............................................................................................................................ l l
ContractPrice, definition of..........................................................................................................................1
ContractTime, Change of...........................................................................................................................12
Contract Time, Commencement of............................................................................................................2.3
ContractTime, definition of..........................................................................................................................1
Contractor, definition of........................................................................................
Contractor May Stop Work or Terminate.................................................................................................15.5
Contractor's Continuing Obligation.......................................................................................................14.14
Contractor's Duty to Report Discrepancy in Documents.................................................................2.5 & 3.2
Contractor's Fee, Costs Plus.....................................................................................................................11.7
Contractor's Liability Insurance.................................................................................................................5.3
Contractor's Responsibilities, in General......................................................................................................6
Contractor's Warranty of Title.................................................................................................................14.3
Copies of Documents..................................................... ..2.2
........................................................................
Correction or Removal of Defective Work............................................................................................13.11
CorrectionPeriod, Two Year.................................................................................................................13.12
General Conditions Page 32
Correction, Removal or Acceptance of Defective Work, in General ..........................................
Cost of Work 13.11-13.14
Costs, Supplemental .
.........................................................................11.5 & 11.6
........11.5.4
Day, definition of ................
DDefectiveWork, Acceptance of.............................................................................................................13.13
efective Work, Correction or Removal of...........................................................................................13.11
DDefective, definition o£.................................................................................................................................1
Defective Work, in General.........................................................................................................................13
Defective Work, Rejection.........................................................................................................................9.4
efinitions.....................................................................................................................................................1
Delivery of Bonds .................... 2.1
.......................................................
Disagreements, Decisions by Engineer......................................................................................................9.9
DDocuments, Copies of................................................................................................................................2.2
ocuments, Record..........................................................................................................
Documents, Reuse 6.20
3.5
Drawings, definition of ................................................................................................................................. l
Effective Date of Agreement, definition of................................................................................................... I
Emergencies.............................................................................................................................................6.23
Engineer, definition of ..............
Engineer's Notice Work is acceptable......................................................................................................14.4
Engineer's Responsibilities, Limitations on.................................................................................... 9.10-9.13
Engineer's Status During Construction, in General......................................................................................9
Engineer's Recommendation of Payment..................................................................................14.4 & 14.13
Equipment, Labor, and Materials........................................................................................................ 6.3-6.6
Equivalent Materials and Equipment.........................................................................................................6.7
FiFee, Contractors, Costs Plus.....................................................................................................................11.7
eld Order, definition of .........................................................
FiFieldOrder, Issued by Engineer...............................................................................................................10.2
Final Application for Payment...............................................................................................................14.12
nal Inspection..............................................................................
......................................................14.11
Final Payment, Recommendation of .....................•................................. .................................14.12 & 14.13
FinalPayment, Acceptance....................................................................................................................14.13
General Requirements, definition of.............................................................................................................1
GeneralProvisions........................................................................................................................16.3 & 16.4
GivingNotice...........................................................................................................................................16.1
Guarantee of Work, by Contractor...........................................................................................................13.1
I
Indemnification................................................................................................................................ 6.31-6.33
Inspection, Final.....................................................................................................................................14.11
Inspection, Tests and ............. 13.3-13.7
................................
Insurance, Bonds and, in General.................................................................................................
Insurance, Builders Risk.............................................................................................................................5.6
Insurance, Certificates of ..........................................
Insurance, Contractor's Liability ................................................................................................................5.3
Insurance, Owner's Liability ..................................................
Intent of Contract Documents................................................................................................ 3.1-3.4 & 9.11
Interpretations and Clarifications................................................................................................................9.3
Investigations of Physical Conditions........................................................................................................4.2
General Conditions
Page 33
A N
Labor, Materials and Equipment ..................................... 6.3-6.7
Lawsand Regulations ................................. .........................................6.15
.....................................................
Liability Insurance, Contractor's................................................................................................................5.3
Liability Insurance, Owner's ...............
Limitations on Engineer's Responsibilities..............................................................................................9.10
Materials and Equipment, Furnished by Contractor...................................................................................6.3
Materials or Equipment, Equivalent...........................................................................................................6.8
MiscellaneousProvisions............................................................................................................................16
Modifications, definition of......................................................................................... 1
Notice, Giving of......................................................................................................................................16.1
Noticeof Award, definition of......................................................................................................................1
Noticeof Acceptability of Project..........................................................................................................14.13
Noticeto Proceed, definition of..................................................................................................................... l
Noticeto Proceed, Giving of......................................................................................................................2.3
"Or -Equal" Items........................................................................................................................................6.8
OtherContractors............................................................................
OvertimeWork, Prohibition of..................................................................................................................6.3
Owner, definition of................................................................................. 1
.............................................. ..
Owner May Correct Defective Work.....................................................................................................13.14
Owner May Stop Work ................................. ....13.10
......................................................................
Owner May Suspend Work, Terminate................................................................................ 15.1-15.4
...........
Owner's Duty to Execute Change Orders..............................................................................................11.10
Owner's Liability Insurance
...................................................................................
Owner's Representative, Engineer to Serve as...........................................................................................9.1
Owner's Responsibilities, in General ........................................
Owner's Separate Representatives at Site..................................................................................................9.8
PartialUtilization.....................................................................................................14.10
.............................
Partial Utilization, Property Insurance................................................................................................14.10.3
PatentFees and Royalties.........................................................................................................................6.13
Paymentsto Contractor, in General.............................................................................................................14
Payment, Recommendation of..................................................................................................... 14.4-14.7.6
Performanceand Other Bonds............................................................................................................. 5.1-5.2
Permits ................ 6.14
............................................................................................................
Physical Conditions, Investigations and Reports
PhysicalConditions, Unforeseen................................................................................................................4.3
Pre -Construction Conference.....................................................................................................................2.8
PreliminaryMatters.......................................................................................................................................2
Premises, Uses of.......................................
...................................................................................... 6.17-6.19
Price, Change of Contract............................................................................................................................ l l
Price, Contract, definition of.........................................................................................................................1
Progress Payment, Applications for.........................................................................................................14.2
ProgressSchedule...........................................................................................................................2.6 & 14.1
Project, definition of ...................' ....
..........
..........................................
Project Representative, Resident definition of............................................................................................. l
Project Representation, Provision for.........................................................................................................9.8
Project, Starting..........................................................................................................................................2.4
Protection, Safety and...................................................................................................................... 6.21-6.22
General Conditions
Page 34
Payment .....................................................................................................
RecRecommendationof
ord Documents ..............................................................................................................................
14.4 & 14.13
Reference Points
. .. 6.20
Regulations, Laws and
4.4
Rejecting Defective Work ..........................................................................................................................
................................................................ 6.15
Removal or Correction of Defective Work 9.4
............................................................................................ 13.11
Resident Project Representative, definition of
Resident Project Representative, Provision
for
Responsibilities, Contractor's
.......................................................................................... 9.8
Responsibilities, Owner's
Reuse of Documents
8
Royalties, Patent Fees and ........................................................................................................................
3.5
6.13
Protection .......................................................................................................................
SSafetyand
amples ....................................................................................................................................
6.21-6.22
Schedules of Shop Drawing Submissions ............ .. 6.24
Schedule of Values ................................................................
............................................................................... .. 2.6 & 14.1
. .....
ShopDrawings and Samples ...........................................................................................................
......................................................... 2.6 & 14.1
Shop Drawings, definition of
6.24-6.29
Site, Visits to by Engineer ..........................................................................................................................
Specifications, definition of
9.2
Before
StaStartingConstruction, ..............................................................................................................
rting the Project .....................................................................................................................................
2.5-2.8
Work, by Contractor
2.4
StoppStopping .................................................................................................................
ing Work, by Owner ......................................................................................................................
15.513.10
Subcontractor, definition of
in General ................................................................................................................
SSubcontractors,
ubstantial Completion, Certification of ..................................................................................................
6.9-6.12
Substantial Completion, definition of
14.8
......................................................................................................................
SSubsurfaceConditions
Costs ...............................................................................................................................
4.2 & 4.3
Supplemental
Consent to Payment
11.5.4
Surety, .....................................................................................................
Notice of Changes ........................................................................................................................
14.12 & 14.14
Surety,
Qualification of ....................................................................................................................
10.5
Surety,
Work, by Owner
5.1 & 5.2
Suuspending ...................................................................................................................
spension of Work and Termination, in General
15.1
...................................................................................... 15
Superintendent, Contractor's
......................................................................................................................
Supervision and Superintendence
6.2
.....................................................................................................
6.1 & 6.2
Taxes, Payment by Contractor .................................................................................................................
Termination, by Contractor
6.16
Termination, by Owner
15.5
15.1-15.4
Termination, Suspension of Work and, in General
and Inspections .......................................................................................................................
..................................................................................... 15
TiTests
Change of Contract ...........................................................................................................................
13.3-13.7
Time,
me, Computation of ..............................................................................................................................
12
Time, Contract, definition of
16.2
UncoveringWork ......................................................................................................................... 13.8 & 13.9
Unit Prices
11.4.1
............................................................
Unit Prices, Adjustment of ......................................................... 11.10
General Conditions
Page 35
1 h
Useof Premises............................................................................................................................... 6.17-6.19
Values, Schedule of..................................................................................................................................14.1
Visitsto Site, by Engineer..........................................................................................................................9.2
Warranty and Guarantee, by Contractor...................................................................................................13.1
Warrantyof Title, Contractor's................................................................................................................14.3
Work, Access to........................................................................................................................................13.2
Workby Others, in General...........................................................................................................................7
Work, Cost of...............................................................................................................................11.5 & 11.6
WorkContinuing During Disputes...........................................................................................................6.30
Work, definition of........................................................................................................................................1
Work, Neglected by Contractor................................................................................................................13.4
Work, Stopping by Contractor.................................................................................................................15.5
Work, Stopping by Owner............................................................................................................... 15.1-15.4
General Conditions Page 36