No preview available
HomeMy WebLinkAboutC07-002 Ewing Trucking and Construction_change order 1CHANGE ORDER NUMBER 1 CONTRACTOR: Ewing Trucking and Construction, LLC Contract for: Eagle to Gypsum Trail Phase I, Seago Section Contract Date: October 10, 2006 You are directed to make the changes noted below in the Subject Contract. County represents that lawful appropriations to cover the costs of the additional work described in this change order have been made. EAGLE COUNTY B O Y COMMISSIONERS By: Chairman Date: • q. u� Nature of Changes: DESCRIPTION Quantity INCREASE DECREASE Delete 48" CMP 1 5,225.00 Delete 48" Flared End Section 1 1,500.00 Delete sign install 2 500.00 Delete 48" CMP clean out 1 2,500.00 Unclassifed Excavation Grade Revisions 2,500.00 Remove/Haul Existing CKP Culvert 4,785.00 Haul off Haz Mat Waste 550.00 Install 18" Culvert 1,800.00 Install 18" Flared End Section 1,500.00 Install 30" Arched Pipe 1,300.00 Install 30" Flared End Section 700.00 Add ABC for MSE Walls 11,274.60 Add Addt'l Erosion Control Fence 1,800.00 Add Addt'l Erosion Logs 1,155.00 Totals: 27,364.60 9,725.00 Change Order No. 1 Page 2 These changes result in the following adjustment of Contract Price and Contract Time: Original Contract Price $141,461.00 Contract Price Prior to this Change Order No. 1 $141,461.00 Net Increase Resulting from this Change Order No. 1 $17,639.60 Current Contract Price Including this Change Order No. 6 $159,100.60 Contract Time Prior to this Change Order November 22, 2006 Net Resulting from this Change Order 0 days Current Contract Time Including this Change Order November 22, 2006 - J6V ---� Ellie aryl, Owner's Wepresentative The above changes are accepted: Contractor By -�1,�. L Title:lw(}� Date: / - !�-) - Q