CHANGE ORDER NUMBER l
--------------------------------------------------
--------------------------------------------------
CONTRACTOR Rippy Contractors
Contract for Golden Eagle Senior Center Remodel
Contract Date September 20, 2005
--------------------------------------------------
--------------------------------------------------
TO: Rippy Contractors
P.O. Box 3610
Eagle, CO 81631
You are directed to make the changes noted below in the Subject Contract. Appropriations to
cover the costs of additional work have been made.
EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS
DATE:
--------------------------------------------------
--------------------------------------------------
Nature of Changes: See EXHIBIT "A" attached hereto, adding sod, earth grading, rock
mulch border, tree relocating, and irrigation. The landscaping has to be added to the contract
to properly cOI1;lplete the Senior Center project.
Item Amount
No. Description
001 Rental Equipment $252.52
002 Landscape Material $2,381.43
003 (1) Trip to landfill $400.00
004 Labor: Supervision $3,050.00
005 Labor: Landscapers $4,420.00
006 Labor: Landscape Laborer $1,125.00
Grand Total $11,628.95
Change Order No. .1..
Rippy Contractors
Page 2
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to this Change Order $430,110.51
Net Increase Resulting from Change Order #2 $ 11,628.95
Current Contract Price Including this Change Order $441,739.46
--------------------------------------------------
--------------------------------------------------
The above changes are recommended:
Senior Facilities Engineer
Date:
--------------------------------------------------
--------------------------------------------------
The above changes are accepted: Rippy Contractors
By: '/U'-"-'/ i/--;:l..~
Michael Rippy
Title:
Date: 6 t - :z 3 - cr {
G:\Capital Projects (CPROJECT)\Senior Center Remodel\Rippy CO#2 60106.DOC