CHANGE ORDER NUMBER 2
--------------------------------------------------
--------------------------------------------------
CONTRACTOR Martinez Western Constructors, Inc.
Contract for Fairgrounds Utility Line Extensions
Contract Date January 24, 2006
--------------------------------------------------
--------------------------------------------------
TO: Martinez Western Constructors, Inc.
You are directed to make the changes noted below in the Subject Contract. Appropriations to
cover the costs of additional work have been made.
TY COMMISSIONERS
By:
DATE:
--------------------------------------------------
--------------------------------------------------
Nature of Changes:
1.) The contractor encountered the existing water line in the same alignment as the
proposed water main. Holes were bored to determine the extent of the conflict
(+$2,066.75).
2.) The pressure reducing vault was relocated requiring a field design change. The new
location required additional materials and labor (+$506.50).
3.) The valves at the water main tie-in did not need to be replaced as originally expected
resulting in a cost savings (-$18,149.80).
4.) Unstable soils were encountered in the trench due to poor drainage from Interstate 70.
The contractor replaced soils in order to achieve adequate compaction (+13,411.13).
5.) At the request of the Greater Eagle Fire Protection District, the fire hydrant northeast
of the pavilion was relocated to be accessible from the east entrance of the
fairgrounds (+ 16,842.50).
6.) A manhole and an additional stick of irrigation pipe were installed in the ditch by
Wapiti Road to provide adequate cover for the fire hydrant along Fairgrounds Road
(+$1,850.00).
7.) The service line to the scale house and the fire hydrant along Fairgrounds Road were
relocated resulting in a cost savings (-$10,118.35).
--------------------------------------------------
--------------------------------------------------
These changes result in the following adjustment of Contract Price and Contract Time:
Original Contract Price $ 636,713.50
Net Increase Resulting from Change Order #1 $ 328,592.65
Net Increase Resulting from this Change Order #2 $ 6,408.73
Current Contract Price Including Change Orders $ 971,714.88
--------------------------------------------------
--------------------------------------------------
Contract Time Prior to this Change Order June 15, 2006
Net Increase Resulting from this Change Order (0) Calendar Days
Current Contract Time Including this Change Order June 15, 2006
--------------------------------------------------
--------------------------------------------------
The above changes are recommended:
County Engineer
Date:
--------------------------------------------------
--------------------------------------------------
The above changes are accepted: Martinez Western
By:
Title:
Date:
Fairgrounds Utility Line Extensions
Change Order No.2