Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutC05-152 Cruz Construction
e~6- 162- ~O
AGREEMENT FOR GUARDRAIL PROJECT
THIS AGREEMENT is dated as of the 29 day of March , 2005,by and
between Eagle County, Colorado, a body corporate and politic, acting by and through its
Board of County Commissioners (hereinafter called "Owner"), and Cruz
Construction, Inc. (hereinafter called "Contractor"),
Owner and Contractor, in consideration of the mutual covenants set forth, agree as
follows:
ARTICLE 1 - WORK
Contractor shall complete all work as specified or indicated in the Contract Documents
("Work"), The Work is generally described as: 2005 GUARDRAIL PROJECT AS
SPECIFIED IN EXHIBIT "A" which is attached hereto and incorporated by this
reference,
ARTICLE 2 - OWNER'S REPRESENTATIVE
The Project is under the authority of the Eagle County Road & Bridge Department, the
Director of which, or his designee, shall be Owner's liaison with Contractor with respect
to the performance of the Work.
ARTICLE 3 - CONTRACT TIME
3.1 The Work will be completed and ready for final payment in accordance with the
Contract Documents on or before OCTOBER 15, 2005,
3.2 LIQUIDATED DAMAGES: Owner and Contractor recognize that time is of the
essence of this Agreement and that Owner will suffer financial loss if the Work
is not substantially complete within the time specified in paragraph 3,1 above,
plus any extensions thereof allowed in accordance with the General Conditions.
They also recognize the delays, expense, and difficulties involved in proving a
legal or arbitration proceeding the actual loss suffered by Owner if the Work is
not substantially complete on time, Accordingly, instead of requiring such proof,
Owner and Contractor agree that as liquidated damages for delay (but not as a
penalty) Contractor shall pay Owner Three Hundred dollars ($300,00) for each
day that expires after the time specified in paragraph 3.1 for completion until the
Work is complete.
Agreement Page 1
ARTICLE 4 - CONTRACT PRICE
4.1 The funds appropriated for this project are equal to or in excess of the contract
amount.
4,2 Owner shall pay Contractor for performance of the Work in accordance with the
Contract Documents in current funds as follows: PROGRESSIVE PAYMENTS
UPON COMPLETION OF EACH AREA AS SPECIFIED IN EXHIBIT "A",
4.3 Pursuant to the provisions S24-91-103.6, C.R.S., and notwithstanding anything
to the contrary contained elsewhere in the Contract Documents, no change
order or other form of order or directive by Owner, and no amendment to this
Agreement, requiring additional compensable work to be performed which work
causes the aggregate amount payable under the Agreement to exceed the
amount appropriated for the original Agreement, shall be of any force or effect
unless accompanied by a written assurance by Owner that lawful appropriations
to cover the costs of the additional work have been made or unless such work
is covered under a remedy-granting provision in the Agreement.
4.4 The Board of County Commissioners for Eagle County is a governmental entity,
All obligations beyond the current fiscal year are subject to funds being
budgeted and appropriated.
ARTICLE 5 - PAYMENT PROCEDURES
Contractor shall submit Applications for Payment in accordance with the General
Conditions, Applications for Payment will be processed as provided in the General
Conditions.
5,1 PROGRESS PAYMENTS: Owner shall make monthly progress payments on
account of the Contract Price on the basis of Contractor's Applications for
Payments, as provided below. All progress payments will be on the basis of the
progress of the Work,
5,1.1 Prior to Completion, progress payments will be in an amount equal to:
0 90% of the Work completed until fifty percent (50%) of the Work is
performed, after which no additional retaining shall be withheld, and
90% of materials and equipment not incorporated in the Work but
delivered and suitably stored,
less in each case the aggregate of payments previously made,
Agreement Page 2
5,1,2 Progress payments and retained funds shall occur in compliance with
Paragraph 19 of the General Conditions attached hereto and C,R.S, S24-91-
103. The Owner shall authorize partial payments of properly requested
amounts of at least ninety percent of the calculated value of the work completed
until fifty percent of the work required under the Agreement has been
performed, Thereafter, the Owner shall authorize partial payments of any other
properly requested amounts without retaining additional funds if, in the opinion
of the Owner, satisfactory progress is being made in the work. The withheld
amounts of the contract price will be retained by the Owner until the contract is
completed satisfactorily and accepted by the Owner.
5,2 FINAL PAYMENT: Upon final completion and acceptance in accordance with
the General Conditions, Owner shall pay the remainder of the Contract Price.
The final payment shall not be made until after final settlement of this contract
has been duly advertised at least ten days prior to such final payment by
publication of notice thereof at least twice in a public newspaper of general
circulation published in Eagle County, and the Board of County Commissioners
has held a public hearing, thereupon and complied with the C,R.S, S38-26-107,
Final payment shall be made in accordance with the requirements of the
aforesaid statute,
ARTICLE 6 - Contractor's REPRESENTATIONS
In order to induce Owner to enter into this Agreement Contractor makes the following
representations:
6,1 Contractor has familiarized himself with the nature and extent of the Contract
Documents, Work, locality, and with all local conditions, and federal, state, and
local laws, ordinances, rules and regulations that in any manner may affect
cost, progress, or performance of the Work,
6,2 Contractor has made, or caused to be made, examinations, investigations, and
tests and studies of such reports and related data as he deems necessary for
the performance of the Work at the Contract Price, within the Contract Time,
and in accordance with other terms and conditions of the Contract Documents;
and no additional examinations, investigations, tests, reports, or similar data
are, or will be required by Contractor for such purposes,
6,3 Contractor has correlated the results of all such observations, examinations,
investigations, tests, reports, and data with the terms and conditions of the
Contract Documents.
6.4 Contractor has given Owner written notice of all conflicts, errors, or
discrepancies that he has discovered in the Contract Documents and the
written resolution thereof by Owner is acceptable to Contractor.
Agreement Page 3
6,5 In performing the work under this Agreement, the Contractor acts as an
independent contractor and is solely responsible for necessary and adequate
worker's compensation insurance, personal injury and property damage
insurance, as well as errors and omissions insurance. The Contractor, as an
independent contractor, is obligated to pay federal and state income tax on
moneys earned. The personnel employed by the Contractor are not and shall
not become employees, agents or servants of the Owner because of the
performance of any work by this Agreement.
ARTICLE 7 - CONTRACT DOCUMENTS
The Contract Documents which comprise the entire Agreement are made a part hereof,
and consist of the following:
7.1 This Agreement.
7.2 Contractor's Bid.
7.3 Performance and other Bonds.
7.4 Notice of Award and, if any, Notice to Proceed.
7.5 General Conditions (Pages 1 to 10, inclusive),
7,6 Specifications and Drawings.
7,7 Any modification, including Change Orders, duly delivered after execution of
Agreement.
7.8 The parties acknowledge and agree that the terms and conditions of this
Agreement (7.1) and the General Conditions (7,5) attached hereto, shall
supersede and control over any inconsistent or contrary provision in any other
attachment or agreement.
There are no Contract Documents other than those listed above in this Article 7, The
Contract Documents may only be altered, amended, or repealed by an executed,
written amendment to this Agreement.
ARTICLE 8 - BONDS
Not later than five business days following the execution of this Agreement, Contractor
shall deliver to the Owner the bonds required by the Contract Documents, and,
notwithstanding anything to the contrary contained in the Contract Documents, Owner
shall have no liability or obligation hereunder unless and until the bonds have been so
delivered.
Agreement Page 4
ARTICLE 9 - MISCELLANEOUS
9,1 No assignment by a party hereto of any rights under, or interests in the Contract
Documents will be binding on another party hereto without the written consent
of the party sought to be bound; and specifically, but without limitation, moneys
that may become due and moneys that are due may not be assigned without
such consent (except to the extent that the effect of this restriction may be
limited by law), and unless specifically stated to the contrary in any written
consent to an assignment, no assignment will release or discharge the assignor
from any duty or responsibility under the Contract Documents.
9,2 Owner and Contractor each binds himself, his partners, successors, assigns
and legal representatives to the other party hereto, in respect to all covenants,
agreements, and obligations contained in the Contract Documents.
9,3 ATTORNEY'S FEES: In the event of litigation between the parties hereto
regarding the interpretation of this Agreement, or the obligations, duties or
rights of the parties hereunder, or if suit otherwise is brought to recover
damages for breach of this Agreement, or an action be brought for injunction or
specific performance, then and in such events, the prevailing party shall recover
all reasonable costs incurred with regard to such litigation, including reasonable
attorney's fees,
9.4 APPLICABLE LAW: This Agreement shall be governed by the laws of the State
of Colorado. Jurisdiction and venue of any suit, right, or cause of action arising
under, or in connection with this Agreement shall be exclusive in Eagle County,
Colorado.
9,5 INTEGRATION: This Agreement supersedes all previous communications,
negotiations and/or contracts between the respective parties hereto, either
verbal or written, and the same not expressly contained herein are hereby
withdrawn and annulled. This is an integrated agreement and there are no
representations about any of the subject matter hereof except as expressly set
forth in the Contract Documents.
9.6 NOTICE: Any notice and all written communications required under this
Agreement shall be (i) personally delivered, (ii) mailed in the United States
mails, first class postage prepaid, or (iii) transmitted by facsimile machine
together with a hard copy conveyed by delivery or mail, to the appropriate party
at the following addresses:
To Contractor:
Cruz Construction, Inc.
4850 Geiger Blvd,
Colorado Springs, CO 80915
Agreement Page 5
To Owner:
Brad Higgins - Director
Road & Bridge Department
Eagle County
P,O, Box 250
Eagle, CO 81631
telephone: 970-328-3540
telefax: 970-328-3546
Mailed notices will be deemed given three business days after the date of
deposit in a regular depository of the United States Postal Service, and FAX
notices will be deemed given upon transmission, if during business hours, or
the next business day, Either party can change its address for notice by notice
to the other in accordance with this paragraph,
. ..
.. ,
[signature page next page]
.. ,
.. .
Agreement Page 6
IN WITNESS WHEREOF, the parties hereto have executed this Agreement effective on
the date first above written,
"Owner":
COUNTY OF EAGLE, STATE OF
COLORADO, By and Through Its
ATTEST BOARD OF COUNTY
COMMISSIONERS
By:
Clerk of the oard of
County Commissioners
"Contractor":
Cruz Construction Inc.
STATE OF COLORADO
) ss:
County of Eagle )
On this 5th day of April ,2005, came before me, a notary
public, Joe M. Cruz known to me to be the President
of Cruz Construction Inc. , who acknowledged to me
that he executed the foregoing document, that he executed it in that capacity,
and that the same was the act of the entity identified in the document as
"Contractor" ,
My commission expires: January 17, 2009
~ !
k' .~ 4,,' . r'-~"~:..\..l ," :" ~
l jJ1~Si ~J4A Itlfl--"
Notary Public
Agreement Page 7
EXHIBIT A
2005
NEW CONSTRUCTION
ITEM DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
1 Guardrail, Type 3
Colorado River Rd.
Mile marker 13 1200 L.F. 16.08 19,296.00
2 Guardrail, Type 3
Colorado River Rd.
Mile marker 16 800 L.F. 16.08 12,864.00
3 Guardrail, Type 3
Colorado River Rd,
Mile marker 29.5 850 L.F, 16.08 13 ,668.00
4 Guardrail, Type 3
Colorado River Rd.
Mile marker 25 300 L.F, 16.08 4,824.00
5 End anchorage, Type 3 8 Each 850.00 6 ,800. 00
REPAIRS TO EXISTING GUARDRAIL
ITEM DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
6 Repair & replace post and rail
Mile marker ,5
Frying Pan River Rd.
1 post and 1 rail Each Each 820.00 820.00
7 Repair & replace posts and rail
and end section,
Mile marker 3,5
Frying Pan River Rd.
3 posts, 1rail, 1end section. Each Each 2,030.00 2,030~00
8 Repair & replace post, rail
and end section
Mile marker 25 (approx)
Colorado River Road
1 post, 1 rail, 1 end section. Each Each 1,720.00 1 ,720.00
9 Repair & replace posts, rail
and end section.
Mile marker ,5
Valley Road (EI Jebel)
3 posts, 1 rail, 1 end section. Each Each 2,030.00 2,030.00
Exhibit A continued on next page,
Exhibit A continued.
TRAFFIC CONTROL
ITEM DESCRIPTION QTY UNIT UNIT PRICE AMOUNT
10 Construction zone
traffic control all Lump sum 5,580.00 5,580.00
TOTAL OF ALL WORK (items 1 through 10) 69,632.00
Note: For the "repairs to existing guardrail" section, the quantity, unit, and unit price shall be the
amount that it will cost to do all the repairs at that location,
Note: Mile markers on Frying Pan River Rd. are measured from Sopris Dr,
Note: Approximate locations are marked by item # on the vicinity map and will be marked
in the field at the location with white paint.
ROAD & BRIDGE DEPARTMENT
GENERAL CONDITIONS
1. Contractor shall provide and pay for labor, materials, equipment, tools, utilities,
permits, licenses, transportation, and other facilities and services necessary for
proper execution and completion of the Work.
2, If Contractor fails to obtain the tax exemption(s) applicable to public works
projects from sales, consumer, use and similar taxes, Contractor shall pay the
same. Owner will cooperate with Contractor to obtain tax exemption for this
project.
3. Contractor shall be responsible for having taken steps reasonably necessary to
ascertain the nature and location of the Work, and the general and local
conditions which can affect the Work or the cost thereof. Any failure by
Contractor to do so will not relieve him from responsibility for successfully
performing the Work without additional expense to the Owner. Owner assumes
no responsibility for any understanding or representations concerning conditions
made by any of its officers, employees or agents prior to the execution of this
Agreement, unless such understanding or representations are expressly stated
in the Agreement.
4. Before commencing activities, Contractor shall: (1) take field measurements and
verify field conditions; (2) carefully compare this and other information known to
Contractor with the Agreement; and (3) promptly report errors, inconsistencies or
omissions discovered to Owner.
5. Contractor shall supervise and direct the Work, using Contractor's best skill and
attention. Contractor shall be solely responsible for and have control over
construction means, methods, techniques, sequences and procedures, and for
coordinating all portions of the Work,
6. Contractor, as soon as practicable, shall furnish in writing to the Owner the
names of subcontractors and suppliers for each portion of the Work.
7. No charge shall be made by Contractor for hindrances or delays from any cause
whatever during the progress of any portion of the Work, unless such hindrance
or delay is caused in whole or in part by acts or omissions within the control of
Owner. In any event, Owner may grant an extension of time for the completion
of the Work, provided it is satisfied that delays or hindrances were due to causes
outside Contractor's control, e.g., weather, or to acts of omission or commission
by the Owner, provided that such extensions of time shall in no instance exceed
the time actually lost to Contractor by reason of such causes, and provided
further that Contractor shall have given Owner immediate (as determined by the
circumstances, but not exceeding 48 hours) notice in writing of the cause of the
detention or delay.
_ a_..~.__~__ ----
8. Contractor shall deliver, handle, store and install materials in accordance with
manufacturers' instructions.
9. Contractor shall comply with and give notices required by all federal, state and
local laws, statutes, ordinances, building codes, rules and regulations applicable
to the Work. If the Contractor performs Work knowing it to be contrary to laws,
statutes, ordinances, building codes, rules or regulations without notice to
Owner, Contractor shall assume full responsibility for such Work and shall bear
the attributable costs, Contractor shall promptly notify Owner in writing of any
conflicts between the specifications for the Work and such governmental laws,
rules and regulations.
10. The Contractor shall be responsible for initiating, maintaining and supervising all
safety precautions and programs, including all those required by law in
connection with performance of the Agreement. The Contractor shall promptly
remedy damage and loss to property caused in whole or in part by the
Contractor, or by anyone for whose acts the Contractor may be liable.
11. Contractor shall keep the premises/work site and surrounding area free from
accumulation of debris and trash related to the Work,
12. Contractor shall furnish performance and payment bonds, each in an amount at
least equal to the contract price as security for the faithful performance and
payment of all Contractor's obligations under the contract documents, These
bonds shall remain in effect at least until two years after the date of final
payment, except as otherwise provided by law. Contractor shall also furnish
other bonds as are required by the supplementary conditions. All bonds shall be
in forms satisfactory to Owner, and be executed by such sureties as (a) are
licensed to conduct business in the state where the project is located, and (b) are
named in the current list of "Companies Holding Certificates of Authority as
Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring
Companies" as published in Circular 570 (amended) by the Audit Staff Bureau of
Accounts, U.S. Treasury Department. All bonds signed by an agent must be
accompanied by a certified copy of the authority to act.
If the surety on any bond furnished by Contractor is declared bankrupt, or
becomes insolvent, or its right to do business is terminated in any state where
any part of the project is located, or it ceases to meet the requirements of
clauses (a) and (b) of the preceding paragraph, Contractor shall within five days
thereafter substitute another bond and surety, both of which shall be acceptable
to Owner.
13. Contractor shall be solely responsible for the protection of the Work until its final
acceptance by Owner. Contractor shall have no claim against Owner because of
any damage or loss to the Work, and shall be responsible for the complete
restoration of damaged Work to its original condition. In the event Contractor's
-. _.-----~ .,- -~-~_..__... "--'-~-~
Work is damaged by another party, not under his supervision or control,
Contractor shall make his claim directly with the party involved. If a conflict or
disagreement develops between Contractor and another party concerning the
responsibility for damage or loss to Contractor's Work, such conflict shall not be
cause for delay in Contractor's restoration of the damaged Work,
14. Contractor's Insurance:
The Contractor shall purchase and maintain such insurance as will protect him
from claims set forth below which may arise out of or result from the Contractor's
operations under the contract, whether such operations be by himself, or by any
subcontractor, or by anyone directly or indirectly employed by any of them, or by
anyone for whose acts any of them may be liable. All such insurance shall
remain in effect until final payment, and at all times thereafter when Contractor
may be correcting, removing, or replacing defective Work, In addition,
Contractor shall maintain such completed operations insurance for at least two
years after final payment, and furnish Owner with evidence of continuation of
such insurance at final payment and one year thereafter.
Insurance coverage shall be as follows:
Claims under Workmen's Compensation, disability benefits, and other similar
employee benefit acts, with coverage and in amounts as required by the laws of
the State of Colorado;
Claims for damage because of bodily injury, occupational sickness or disease, or
death of his employees, and claims insured by usual personal injury liability
coverage;
Claims for damage because of bodily injury, sickness, disease, or death of any
person other than his employees; and
Claims for damages because of injury to or destruction of tangible property,
including loss of use resulting therefrom;
Contractor's Liability Insurance issued to and covering the liability for damage
imposed by law upon the Contractor and each subcontractor with respect to all
Work performed by them under the Agreement;
Contractor's Protective Liability Insurance issued to and covering the liability for
damages imposed by law upon the Contractor and each subcontractor with
respect to all Work under the Agreement performed for the Contractor by
subcontractors.
Completed Operations Liability Insurance issued to and covering the liability for
damage imposed by law upon the Contractor and each subcontractor arising
.'-~~..- . -_.---
between the date of final cessation of the Work, and the date of final acceptance
thereof out of that part of the Work performed by each.
Comprehensive Automobile Insurance:
All liability and property damage insurance required hereunder shall be
Comprehensive General and Automobile Bodily Injury and Property Damage
forms of policies, as the case may be,
The Contractor shall in addition, and in the amounts required under the above,
obtain protective Liability Insurance issued to and covering the liability for
damages imposed by law upon the Owner with respect to all operations under
the construction contract by the Contractor or his subcontractors, including
omissions and supervisory acts by the Owner,
Builder's Risk Insurance: Insofar as the Work to be performed under this contract
consists entirely of new construction removed and separated from any existing
facility used by Owner, Contractor shall procure and maintain, for the duration of
the Work of this project, Builder's Risk Insurance, including the perils ottire,
extended coverage (loss due to vehicles, explosion, wind, flood, riot, etc,),
vandalism and malicious mischief, and special extended coverage (loss due to
falling objects, collapse, water damage from faulty or leaking systems, etc.) in
the full amount of the contract price plus the cost of authorized extras, Said
amount of insurance coverage shall be considered to cover the insurable value
of the Work under this contract which is considered not to exceed one hundred
percent (100%) of the amount of this contract and authorized extras, Such
policy shall not insure any tools or equipment, or temporary structures erected at
the site and belonging to any person or persons, or their subcontractors who are
obliged by contract with the Owner to do Work on the projects.
Comprehensive Risk Policy Option: In lieu of the several policies specified for
Contractor's Liability Insurance, a comprehensive liability and property damage
insurance policy inclusive of all the insurance and requirements herein set forth,
subject to the approval of the Owner, will be permissible.
Insurance covering claims for damages to persons or property shall at a
minimum provide coverage of the larger of (i) $500,000 each person/$1 ,000,000
each occurrence, for bodily injury and $600,000 each occurrence for property
damage, (ii) the maximum liability of a local government provided in the Colorado
Governmental Immunity Act, 24-10-101, et seq., CRS (1973) as that may be
amended from time-to-time, or (iii) such greater amount(s) as may be required by
law.
Insurance shall be placed jointly in the names of the Owner, Contractor, and any
and all subcontractors, and any and all others obliged by contract with the Owner
to do Work on this project, and, at the Owner's option, any other person or
--~---'--~-
persons whom the Owner deems to have an insurable interest in said property,
or any part thereof, payable as their several interests may appear. Any proceeds
obtained from insurance provided for by this paragraph shall be paid to and held
by the Owner as trustee, The Owner shall have the right to withhold payment of
such proceeds until such time as the Work destroyed or damaged and covered
by such insurance shall be reconstructed and shall pay such proceeds on an
installment basis similar to that provided for by progress payments covering the
original Work,
Certificates of Insurance: Certificates of Insurance acceptable to the Owner shall
be filed with the Owner prior to commencement of the Work. These Certificates
shall contain provisions naming the Owner as an additional insured under
Contractor's insurance, as more fully required by the General Conditions herein,
and that coverage afforded under the policies will not be canceled until at least
thirty days prior written notice has been given the Owner. Contractor and his
subcontractors shall not permit any of his subcontractors to start Work until all
required insurance have been obtained and certificates with the proper
endorsements have been filed with the Owner. Failure of the Contractor to
comply with the foregoing insurance requirements shall in no way waive the
Owner's rights hereunder.
15. Owner, at its option, may purchase and maintain such liability insurance as will
protect him against claims which may arise from operations under this contract.
Purchasing and maintaining such insurance, however, will not relieve the
Contractor from purchasing and maintaining the insurance hereinbefore
specified.
16. Before permitting any of his subcontractors to perform any Work under this
contract, Contractor shall either (a) require each of his subcontractors to procure
and maintain during the life of his subcontracts, Subcontractor's Public Liability
and Property Damage Insurance of the types and in the amounts as may be
applicable to his Work, which type and amounts shall be subject to the approval
of the Owner, or (b) insure the activities of his subcontractors in his own policy.
17, To the fullest extent permitted by law, Contractor shall indemnify and hold
harmless Owner, its board, commissioners, employees and the agents of any of
them, from and against claims, damages, losses and expenses, including but not
limited to attorneys' fees, arising out of or resulting from performance of the
Work, provided that such claim, damage, loss or expense is attributable to bodily
injury, sickness, disease or death, or to injury to or destruction of tangible
property (other than the Work itself) including loss of use resulting therefrom, but
only to the extent caused in whole or in part by negligent acts or omissions of the
Contractor, a subcontractor, anyone directly or indirectly employed by them or
anyone for whose acts they may be liable, regardless of whether or not such
claim, damage, loss or expense is caused in part by a party indemnified
hereunder.
.~~~
--~'- ..._---~
18. After execution of the Agreement, changes in the Work may be accomplished by
Change Order of by order for a minor change in the Work. Owner, without
invalidating the Agreement, may order changes in the Work within the general
scope of the Agreement consisting of additions, deletions or other revisions.
a. No Change Orders or other form of order or directive which requires
additional compensable work to be performed may be issued or be
effective unless accompanied by a written assurance to the Contractor
that lawful appropriations to cover the costs of the additional work have
been made.
b. A Change Order shall be a written order to the Contractor signed by
Owner to change the Work.
c. Owner will have authority to order minor changes in the Work not involving
changes in the Contract Price or the Contract Time, Such changes shall
be written orders and shall be binding on the Contractor and Owner.
Contractor shall carry out such written orders promptly.
19. Progress Payments:
If the project is subject to progress payments, not more often than once a month,
Contractor shall submit to Owner an application for payment filled out and signed
by Contractor covering the work completed as of the date of the application, and
accompanied by such supporting documentation as Owner may reasonably
require, If payment is requested on the basis of materials and equipment not
incorporated in the work, but delivered and suitably stored at the site or at
another location agreed to in writing, the application for payment shall also be
accompanied by such data, satisfactory to Owner, as will establish Owner's title
to the material and equipment, and protect Owner's interest therein, including
applicable insurance. Each subsequent application for payment shall include an
affidavit of Contractor stating that all previous progress payments received on
account of the work have been applied to discharge in full all of Contractor's
obligations reflected in prior applications for payment. The amount of retainage
with respect to progress payments will be as stipulated in the Agreement.
Owner will, with ten days after receipt of each application for payment, either
indicate in writing a recommendation of payment, or return the application to
Contractor indicating in writing its reasons for refusing to recommend payment.
In the latter case, Contractor may make the necessary corrections and resubmit
the application. Owner shall, within twenty days of recommendation of payment,
pay Contractor the amount recommended.
-~_._.__.~
20. Final Payment:
Upon written notice from Contractor that the work is complete, Owner will make a
final inspection with Contractor, and will notify Contractor in writing of all
particulars in which this inspection reveals that the work is incomplete or
defective. Contractor shall immediately take such measures as are necessary to
remedy such deficiencies.
After Contractor has completed all such corrections to the satisfaction of Owner,
and delivered all maintenance and operating instructions, schedules,
guarantees, bonds, certificates of inspection, marked-up record documents or
as-built drawings covering all of the Work, Contractor may make application for
final payment following the procedure for progress payments. The final
application for payment shall be accompanied by all documentation called for in
the contract documents, and such other data and schedules as Owner may
reasonably require, together with complete and legally effective releases or
waivers (satisfactory to Owner) of all liens arising out of, or filed in connection
with the work, In lieu thereof, and as approved by Owner, Contractor may
furnish receipts or releases in full; an affidavit of Contractor that the releases and
receipts include all labor, services, material, and equipment for which lien could
be filed, and that all payrolls, material, and equipment bills, and other
indebtedness connected with the work, for which Owner or his property might in
any way be responsible, have been paid or otherwise satisfied; and consent of
the surety, if any, to final payment. If any subcontractor, manufacturer,
fabricator, supplier, or distributor fails to furnish a release or receipt in full,
Contractor may furnish a bond or other collateral satisfactory to Owner to
indemnify against any lien,
21. Final payment shall not become due until Contractor submits to Owner releases
and waivers of liens, and data establishing payment or satisfaction of obligations,
such as receipts, claims, security interests or encumbrances arising out of the
Work. Final payment is subject to the Final Settlement requirements and time
periods set forth in C.R.S, S38-26-107.
22. Contractor warrants and guarantees that title to all work, materials, and
equipment covered by any application for payment, whether incorporated in the
project or not, will pass to Owner at the time of payment free and clear of all
liens, claims, security interests, and encumbrances (in these General Conditions
referred to as "Liens").
23. Contractor's obligations to perform and complete the Work in accordance with
the contract documents shall be absolute. Neither the recommendation of any
progress or final payment nor the payment by Owner to Contractor under the
contract documents, nor any use or occupancy of the Work or any part thereof
by Owner, nor any act of acceptance by Owner, nor any failure to do so, nor any
correction of defective Work by Owner shall constitute an acceptance of Work
. ~---,--,-,,-,-,-"_.~---~--
not in accordance with the contract documents or a release of Contractor's
obligation to perform the Work in accordance with the contract documents.
24. If Contractor fails to correct Work which is not in accordance with the Agreement,
the Owner may direct the Contractor to stop the Work until the correction is
made.
25. Contractor shall promptly correct Work rejected by Owner as failing to conform to
the requirements of the Agreement and Contractor shall bear the cost of
correcting such rejected Work.
26. Contractor warrants to Owner that: (1) materials and equipment furnished under
the Agreement will be new and of good quality; (2) the Work will be free from
defects not inherent in the quality required or permitted; and (3) the Work will
conform to the requirements of the Agreement.
27. Contractor warrants and guarantees to Owner that all Work will be in accordance
with the Contract Documents and will not be defective. Prompt notice of all
defects shall be given to Contractor, If, within one year after the date of
completion, or such longer period of time as may be set forth in the Agreement
(including the Bid), prescribed by law, prescribed by the terms of any applicable
warranty given by a materials supplier or required by or a part of the Agreement,
any Work is found to be defective, Contractor shall promptly, without cost to '
Owner, and in accordance with Owner's written instructions, either correct such
defective Work, or, if it has been rejected by Owner, remove it from the site, and
replace it with nondefective work. If Contractor does not promptly comply with
the terms of such instructions, or in an emergency where delay would cause
serious risk of loss or damage, Owner may have the defective Work corrected or
the rejected Work removed and replaced, and all direct and indirect costs of
such removal and replacement, including compensation for additional
professional services, shall be paid by Contractor,
28, If Contractor defaults or neglects to carry out the Work in accordance with the
Agreement and fails within a seven day period after receipt of written notice from
the Owner to correct such default or neglect with diligence and promptness, the
Owner may, without prejudice to other remedies, correct such deficiencies. In
such case, the Agreement may be terminated by Owner or a Change Order shall
be issued deducting the cost of correction from payments due the Contractor.
29. The performance of the Work may be terminated at any time in whole, or from
time-to-time in part, by Owner for its convenience. Any such termination shall be
effected by delivery to Contractor of a written notice ("Notice of Termination")
specifying the extent to which performance of the Work is terminated and the
date upon which termination becomes effective. After receipt of a Notice of
Termination, and except as otherwise directed by Owner, Contractor shall, in
good faith, and to the best of its ability, do all things necessary, in the light of
_..~--~--_.._~~ --"---_.._-~_._---~ --.-
such notice and of such requests in implementation thereof as Owner may
make, to assure the efficient, proper closeout of the terminated Work (including
the protection of Owner's property). Among other things, Contractor shall,
except as otherwise directed or approved by Owner:
a. stop the Work on the date and to the extent specified in the Notice of
Termination;
b. place no further order or subcontracts for services, equipment or materials
except as may be necessary for completion of such portion of the Work as
is not terminated;
c. terminate all orders and subcontracts to the extent that they relate to the
performance of Work terminated by the Notice of Termination;
d. assign to Owner, in the manner and to the extent directed by it, all of the
right, title and interest of Contractor under the orders or subcontracts so
terminated, in which case Owner shall have the right to settle or pay any
or all claims arising out of the termination of such orders and
subcontracts;
e. with the approval of Owner, settle all outstanding liabilities and all claims
arising out of such termination or orders and subcontracts; and
f. deliver to Owner, when and as directed by Owner, all documents and all
property which, if the Work had been completed, Contractor would be
required to account for or deliver to Owner, and transfer title to such
property to Owner to the extent not already transferred.
In the event of such termination, there shall be an equitable reduction of the Contract
Price to reflect the reduction in the Work and no cost incurred after the effective date of
the Notice of Termination shall be treated as a reimbursable cost unless it relates to
carrying out the unterminated portion of the Work or taking closeout measures.
~--,.~.~~- _..._---_.~
SPECIFICATIONS
GUARDRAIL
Description
Per Colorado Department of Transportation's "Standard Specifications for Road and
Bridge Construction, 1999", Subsection 606.01.
Materials
Per Colorado Department of Transportation's "Standard Specifications for Road and
Bridge Construction, 1999", Subsection 606.02, and October, 2000 Standard Plan
M-606-1, Sheets 1,2,3, and 14 of 15 and November, 1992 Standard Plan M-606-1, Sheet
5 of 12. Beams shall be core 10. Posts shall be wood.
The Contractor is required to re-use existing posts where they are found to be in good
reusable condition. The Contractor will credit the County for each post re-used, Ifthe
reused posts have to be adjusted in height, the resulting voids under the posts will be
filled with a lean concrete mixture consisting of one part cement and ten parts sand,
Construction Requirements
Per Colorado Department of Transportation's "Standard Specifications for Road and
Bridge Construction, 1999", Subsection 606,03, and attached October, 2000 Standard
Plan M -606-1, Sheets I, 2, 3, and 14 of 15 and November, 1992 Standard Plan M -606-1,
Sheet 5 of 12,
Other Requirements
Contractor will be responsible for obtaining any necessary approvals and permits from
the Colorado Department of Transportation including, but not limited to traffic control
plan and permits for construction in the State right-of-way.
Method of Measurement
Per Colorado Department of Transportation's "Standard Specifications for Road and
Bridge Construction, 1999", Subsection 606,05,
Page 2
Specifications - Guardrail
Basis of Payment
The accepted quantities of guardrail will be paid for at the contract unit price for the type
specified. Payment will be made under:
Pay Item Pay Unit
Guardrail, Type 3 Linear Foot
Raise Linear Foot
Repair Each
End Anchorage, Type 3E Each
All work and materials necessary and incidental to the temporary treatment of guardrail
ends will not be measured and paid for separately, but shall be included in the work.
Partial payments will not be made for partially completed guardrail runs that do not
conform to the end treatments specified in subsection 606,03 (C),
***********************************
CONSTRUCTION ZONE TRAFFIC CONTROL
Construction Zone Traffic Control per the Colorado Department of Transportation's
"Standard Specifications for Road and Bridge Construction, 1999", Subsections 630.01
through 630,15, inclusive except as follows:
630.14 METHOD OF MEASUREMENT: Delete everything. Replace with the
following:
Construction Zone Traffic control will be measured
on a lump sum basis,
Page 3
Specifications - Guardrail
630.15 BASIS OF PAYMENT: Delete everything following the second
paragraph and replace with:
Payment will be made under:
Pay Item Pay Unit
Construction Zone Lump Sum
Traffic Control
~ THE AME~,CAN INSTITUTE OF ;t,CHITECTS
Bond #717399
AlA Document A311
Performance Bond
KNOW ALL MEN BY THESE PRESENTS: that CRUZ CONSTRUCTION, INC,
(Here insert full name and address or legal title of Contractor)
4850 GEIGER BLVD.
COLORADO SPRINGS, CO 80915
as Principal, hereinafter called Contractor, and, UNIVERSAL SURETY COMPANY
(Here insert full name and address or legal title of Surety)
p, O. BOX 80468
LINCOLN, NE 68501-0468
as Surety, hereinafter called Surety, are held and firmly bound unto
EAGLE COUNTY ROAD & BRIDGE, ATTN: BRAD HIGGINS
(Here insert full name and address or legal title of Owner)
PO BOX 250
EAGLE, CO 81631
as Obligee, hereinafter called Owner, in the amount of
SIXTY NINE THOUSAND SIX HUNDRED THIRTY TWO AND 00/100 Dollars ($ 69,632.00),
for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators,
successors and assigns, jointly and severally, firmly by these presents.
WHEREAS,
Contractor has by written agreement dated March 29th, 2005, entered into a contract with Owner for
(Here insert full name address and description of project)
2005 Guardrail Project
in accordance with Drawings and Specifications prepared by
" ,
(Here insert full name and address or legal title of Architect)
which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
AlA DOCUMENT A311 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND AlA 0 1
FEBRUARY 1970 ED THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 N,Y. AVE., NW" WASHINGTON, D,C, 20006
/OERFORMANCE BO~Q
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and
faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force
and effect.
The Surety hereby waives notice of any alteration or defaults under the contract or contracts of completion
extension of time made by the Owner, arranged under this paragraph) sufficient funds to pay
Whenever Contractor shall be, and declared by the cost of completion less the balance of the contract
Owner to be in default under the Contract the Owner price but not exceeding, including other costs and
having performed Owner's obligations thereunder, the damage for which the Surety may be liable hereunder,
surety may promptly remedy the default, or shall the amount of the contract price", as used in this
promptly paragraph shall mean the toral amount payable by
Owner to Contractor under the contract and any
1) Complete the Contract in accordance with its terms amendments thereto, less the amount properly paid
and conditions, or by owner to Contractor.
Any suit under this bond must be instituted before
2) Obtain a bid or bids for completing the Contract in the expiration of two (2) years from the date on which
accordance with its terms and conditions, and upon de- final payment under the Contract falls due.
termination by Surety of the lowest responsible bidder,
or, if the Owner elects, upon determination by the
Owner and the Surety jointly of the lowest responsible No right of action shall accrue on this bond to or for
bidder, arrange for a contract between such bidder and the use of any person or corporation other than the
Owner, and make available as Work progresses (even Owner named herein or the heirs, executors, adminis-
though there should be a default or a succession of trators, or successors of the Owner.
Signed and sealed this 7th day of April, 2005
C') ;1 r C"), CRUZ CONSTRUCTION, INC.
\..-/C>~V-t.L .1 ~ju\..-I[{,.\.,-. al Seal
Witness/
, /\ UNIVERSAL SURETY COMPANY
\UJ,VU l{ ( liJi Surety Seal
Witness
Jas
AlA DOCUMENT A311 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND AIAO 2
FEBRUARY 1970 ED THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 N, Y. AVE., N,W" WASHINGTON, D,C. 20006
THE AMEplCAN INSTITUTE OF Jt~CHITECTS
\ I,.
Bond #717399
AlA Document A311
labor and Material Payment Bond
THIS BOND IS ISSUED SIMUL TANEOUSL Y WITH PERFORMANCE BOND IN FAVOR OF THE
OWNER CONDITIONED ON THE FULL AND FAITHFUL PERFORMANCE OF THE CONTRACT
KNOW ALL MEN BY THESE PRESENTS: that CRUZ CONSTRUCTION, INC.
(Here insert full name and address or legal title of Contractor)
4850 GEIGER BLVD,
COLORADO SPRINGS, CO 80915
as Principal, hereinafter called Contractor, and, UNIVERSAL SURETY COMPANY
(Here insert full name and address or legal title of Surety)
P. O. BOX 80468
LINCOLN, NE 68501-0468
as Surety, hereinafter called Surety, are held and firmly bound unto
EAGLE COUNTY ROAD & BRIDGE, ATTN: BRAD HIGGINS
(Here insert full name and address or legal title of Owner)
PO BOX 250
EAGLE, CO 81631
as Obligee, hereinafter called Owner, for the use and benefit of claimants as hereinbelow defined, in the
amount of SIXTY NINE THOUSAND SIX HUNDRED THIRTY TWO AND 00/100 Dollars ( 69,632.00),
(Here insert a sum equal to at least one-half of the contract price)
for the payment whereof Principal and Surety bind themselves, their heirs, executors, administrators,
successors and assigns, jointly and severally, firmly by these presents,
WHEREAS,
Principal has by written agreement dated March 29th, 2005 entered into a contract with Owner for
(Here insert full name address and description of project)
2005 Guardrail Project
in accordance with Drawings and Specifications prepared by
" ,
(Here insert full name and address or legal title of Architect)
which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
AlA DOCUMENT A311 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND AIAO 3
FEBRUARY 1970 ED THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 N,Y, AYE., N,W" WASHINGTON, D.C. 20006
LABOR A'''~D MATERIAL PAYI\P~NT BOND
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Principal shall promptly make
payment to all claimants as hereinafter defined, for all labor and material used or reasonably required for use in
the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and
effect, subject, however, to the following conditions:
1. A claimant is defined as one having a direct con- party to whom materials were furnished, or for whom
tract with the Principal or with a Subcontractor of the the work or labor was done or performed. Such notice
Principal for labor, material, or both, used or reasonably shall be served by mailing the same by registered mail
required for use in the performance of the Contract, or certified mail; postage prepaid, in an envelope
labor and material being construed to include that part addressed to the Principal, Owner or Surety, at any
of water, gas, power, light, heat, oil, gasoline, telephone place where an office is regularly maintained for the
service or rental of equipment directly applicable to the transaction of business, or served in any state in
Contract. any manner in which legal process may be served
in the state in which the aforesaid project is located,
2. The above named Principal and Surety hereby save that such service need not be made by a
jointly and severally agree with the Owner that every public officer.
claimant as herein defined, who has not been paid in
full before the expiration of a period of ninety (90) b) After the expiration of one (1) year following
days after the date on which the last of such claimant's the date on which Principal ceased Work on
work or labor was done or performed, or materials were said Contract, it being understood, however, that
furnished by such claimant, may sue on this bond for the if any limitation embodied in this bond is prohibited
use of such claimant, prosecute the suit to final judgment by any law controlling the construction hereof such
for such sum or sums as may be justly due claimant limitation shall be deemed to be amended so as to be
and have execution thereon. The Owner shall not be equal to the minimum period of limitation permitted
liable for payment of any costs or expenses of any such by such law.
suit.
c) Other than in a state court of competent for the
3. No suit or action shall be commenced hereunder by jurisdiction in and for the county or other political
any claimant: subdivision of the state in which the Project, or
any part thereof, is situated, or in the United States
a) Unless claimant, other that one having a direct District Court for the district in which the project or
contract with the Principal, shall have given written any part thereof is situated, and not elsewhere.
notice to any two of the following: the Principal, the
Owner, or the Surety above named, within (90) day 4. The amount of this bond shall be reduced by
after such claimant did or performed the last of the and to the extent of any payment or payments
work or labor, or furnished the las of the materials made in good faith hereunder, inclusive of the
for which said claim is made, stating with substantial payment by Surety of mechanic's liens which
accuracy the amount claimed and the name of the may be filed of record against said improvements
whether or not claim for the amount of such lien
be presented under and against this bond,
Signed and sealed this 7th day of April , 2005 .
CRUZ CONSTRUCTION, INC,
(Principal) (Seal)
, UNIVERSAL SURETY COMPANY
U;\ It,, r' I, 'J (Surety) (Seal)
, , 4V1U"
~ 11'-
v (Witness)
AIADOCUMENT A311 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND AIAo 4
FEBRUARY 1970 ED THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 N.Y. AVE" N.W" WASHINGTON, D,C, 20006
Ii"
t
UNIVERSAL SURETY
Lincoln, Nebraska
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS:
That the UNIVERSAL SURETY COMPANY, a corporation of the State of Nebraska having its principal office in the City of Lincoln, Nebraska, pursuant to the
following Bylaw, which was adopted by the Board of Directors of the said Company on July 23, 1981,to wit:
"Article V-Section 6. RESIDENT OFFICERS AND A TIORNEYS-rN-FACT, The President or any Vice President, acting with any Secretary or Assistant Secretary,
shall have the authority to appoint Resident Vice Presidents and Attorneys-In-Fact, with the power and authority to sign, execute, acknowledge and deliver on its behalf, as
Surety: Any and all undertakings of suretyship and to affix thereto the corporate seal of the corporation. The President or any Vice President, acting with any Secretary or
Assistant Secretary, shall also have the authority to remove and revoke the authority of any such appointee at any time."
does hereby make, constitute and appoint
Jason J. Yezek or Kori L. Green or Mindy M. Sheble
or Mary Arboneaux or Ned Flemke, Colorado Springs, Colorado
its true and lawful Attomey(s)-in-Fact, to make, execute, seal and deliver for and on its behalf, as Surety:
Any and all undertakings of suretyship
And the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon said Company, as fully and amply, to all intents and purposes,
as if they had been duly executed and acknowledged by the regularly elected officers of the Company at its offices in Lincoln, Nebraska, in their own persons.
The following Resolution was adopted at the Regular Meeting of the Board of Directors of the UNIVERSAL SURETY COMPANY, held on July 23, 1981:
"RESOLVED, That the signatures of officers of the Company and the seal of the Company may be affixed by facsimile to any Power of Attorney executed in
accordance with Article V-Section 6 of the Company Bylaws: and that any such Power of Attorney bearing such facsimile signatures, including the facsimile signature of a
certifYing Assistant Secretary and facsimile seal shall be valid and binding upon the Company with respect to any bond, undertaking or contract of suretyship to which it is
attached."
All authority hereby conferred shall remain in full force and effect until terminated by the Company.
IN WITNESS WHEREOF, UNIVERSAL SURETY COMPANY has caused these presents to be signed by its Vice President and its corporate seal to be hereunto
affixed this 16 day of April ,20 04
UNIVERSAL SURETY COMPANY
IltJI/hv - ~~~
Secretary By Vice President
State of Nebraska )
) ss.
County of Lancaster)
On this 16 day of April ,20 04 before me personally came Robert L. Privett, to me known, who being by me duly sworn, did
depose and say that (s)he resid~s."in the C~\.Illty of Seward, State of Nebraska; that (s)he is the Vice President of the UNIVERSAL SURETY COMPANY, the corporation
described in and which executl#cfthe aoove Instrument; that (s)he knows the seal of the said corporation; that the seal affixed to the said instrument is such corporate seal;
that it was so affixed by order Qfthe Board of Directors of said corporation; that (s)he signed (his) (her) name by like order; and that Bylaw, Article V-Section 6, adopted by
the Board of Directors of said c.:ornpany, referred to in the preceding instrument, is now in force.
~C.~ ~NOTNW._ar__
My COrnlni~ion Expires April 12, 2007. CHElM.A.1ROWN
Notary Public A\' c.m. e,... If._
I, Jeanne~Bower, Assistant~tary of UNIVERSAL SURETY COMPANY, do hereby certify that the above and foregoing is a tnle and con-ect copy of a Power of
Attomey~xecuted by said i1l'l1VERSM~J!R,E1IY fOMP~ which is still i1;1I frn;cr and effect. ~
Signed and sealed at the City of Lincoln, NebraskatKls '7 day of Or I ,20.
I
.) ~:)
t1{1,.2u~-~,,~, .~-G:~'7 !..:c.At>~
/' Assistant Secretary
/ /
~
- - ---r - -...Y......'- ..l. "5\,.1 Page 1 of1
Guardrail Repair - Colo. River Rd.
~ #8
I j\
\
~l
<l) / ( I
JWNM:ltlRt. -..~Qlt~ . . ....
.. Legend
t ';J;, /V' Strftl:$
Copyright 2004
Eagle County GIS
PO Box 850
~~~ Eagle, CO 81631
~()Jtf:ntImMRlf
DISCLAIMER: This map was created by the Eagle County GIS Department. Use of this map should be
for general purposes only, Eagle County does not warrant the accuracy of the data contained herein.
http://gisweb.eaglecounty,us/servlet!com.esri.esrimap ,Esrimap ?ServiceN ame=ecgis&Client.,. l/i/?()O';
~ _ _ -....J HU"P "-'UlpUl rage Page 1 of 1
Guardrail repair - Valley Road
" "''''''''
L~g~ntl
Copyright 2004 ;VS1$Hfs
Eagle County GIS
PO Box 850
Eagle, CO 81631
DISCLAIMER: This map was created by the Eagle County GIS Department. Use of this map should be
for general purposes only, Eagle County does not warrant the accuracy of the data contained herein,
I
http://gisweb,eaglecounty.us/servlet/com,esri, esrimap ,Esrimap ?Service N f1mp=pf'''';'' .Q.r'l: ---'- ..... 1- ._ -
l:3IU CUMPAKI~UN
DESCRIPTION:
2005 Guardrail Project
QTY I I MAKE! ICOST 10 MAKE!
VENDOR VENDOR MODEL COST
MODEL
Ideal Fencing $69,990,00 Gonzales Construction $73,870.19
Total $69,990,00 Total $73,870.19
IVENDOR I MAKE! ICOST 10 MAKE!
QTY VENDOR MODEL COST
MODEL
Adarand Constructors $72,838.50 Cruz Construction $69,632.00
Total $72,838,50 Total $69,632,00
RECOMMENDATION:
{ THE A~ltlCAN INSTITUTE OF A(<::HITECTS
(
AlA Document A3l 0
Bid Bond
BOND # CC032105
KNOW ALL MEN BY THESE PRESENTS, that we
CRUZ CONSTRUCTION. 1Ne.
4850 GEIGER BLVD, COLORADO SPRINGS, CO 80915
(Here insert full name ,and address or legal title of Contractor)
as Principal, hereinafter called the Principal, and
UNIVERSAL SURETY COMPANY
P. 0, BOX 80468 LINCOLN, NE 68501-0468
a corporation duly organized under the laws of the State of NEBRASKA as Surety, hereinafter called the Surety, are held and fmnly
bound unto EAGLE COUNTY ROAD & BRIDGE, ATTN: BRAD HIGGINS
PO BOX 250 EAGLE, CO 8163]
(Here insert full name ,and address or legal title of Owner)
as Obligee, hereinafter called the Obligee, in the sum of Five Percent of Amount Bid-------------Dollars ($ 5%), for the payment
of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators,
successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, the Principal has submitted a bid for
2005 Guardrail Project
(Here insert full name. address and description of project)
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with the Obligee
in accordance with the terms of such bid and give such bond or bonds as may be specified in the bidding or Contract Documents with
good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor and material furnished in
the prosecution thereof, or in the event of the failure of the Principal to enter such Contract and give such bond or bonds, if the
Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such
larger amount for which the Obligee may in good faith contract with another party to perform the Wark covered by said bid then this
obligation shall be null and void, otherwise to remain in full force and effect.
Signed and sealed this 21st day of March. 2005.
c~ eeL Ag< ILN"-- ~? (Seal)
\: }Lt",-' , ',: " " ,-------"
(Witness) f/
D
\lmt( (1 r lJJ\ (Title)
(Witness) , Attorney-in-Fact
AlA DOCUMENT A310 BID BOND ALA@ FEBRUARY 1970 ED TIlE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NY A VB., N,W, WASHINGTON, D,C, 20006 1
WARNING: Unlicensed photocopying violates US, copyright laws and is subject to legal prosecution,
UNIVERSAL SURETY COMPANY
Lincoln, Nebraska
POWER OF A TTORi'J'EY
KNOW ALL MEN BY THESE PRESENTS:
That the UNIVERSAL SURETY COMPANY, a corporation of the State of Nebraska having its principal office in the City of Lincoln, Nebraska, pursuant to the
foi/owing Bylaw, which was adopted by the Board of Directors of the said Company on July 23,1981, to wit:
"Article V-Section 6, RESIDENT OFFfCERS AND A TTORNEYS-rN-F ACT. The President or any Vice President, acting with any Secretary or Assistant Secretary,
shall have the authority to appoint Resident Vice Presidents and Attorneys-In-Fact, with the power and authority to sign, execute, acknowledge and deliver on its behalf, as
Surety: Any and ail undertakings of suretyship and to affix thereto the corporate seal of the corporation, The President or any Vice President, acting with any Secretary or
Assistant Secretary, shall also have the authority to remove and revoke the authority of any such appointee at any time."
does hereby make, constitute and appoint
Jason J. Yezek or Kori L. Green or Mindy M. Sheble
or Mary Arboneaux or Ned Flemke, Colorado Springs, Colorado
its true and lawful Attorney(s)-in-Fact, to make, execute, seal and deliver for and on its behalf, as Surety:
Any and ai/ undertakings of suretyship
And the execution of such bonds or undertakings in pursuance ofthese presents, shall be as binding upon said Company, as fully and amply, to all intents and purposes,
as if they had been duly executed and acknowledged by the regularly elected officers of the Company at its offices in Lincoln, Nebraska, in their own pel'SQns.
The following Resolution was adopted at the Regular Meeting of the Board of Directors ofthe UNIVERSAL SURETY COMPANY, held on July 23, 1981:
"RESOLVED, That the signatures of officers of the Company and the seal of the Company may be affixed by facsimile to any Power of Attorney executed in
accordance with Article V-Section 6 of the Company Bylaws: and that any such Power of Attomey bearing such fucsirniie signatures, including the facsimile signature of a
certifYing Assist:\nt Secretary and facsimile seal shall ~ valid and binding upon the Company with respect to any bond, undertaking or contract of suretyship to which it is
attached, "
All authority hereby conferred shall remain in full force and effect until terminated by the Company,
IN WITNESS WHEREOF, UNIVERSAL SURETY COMPANY has caused these presents to, be signed by its Vice President and its corporate seal to be hereunto
affixed this 16 day of April ,20 04
UNIVERSAL SURETY COMPANY
!/Q/;JkMJ - ~~~
Secretary By Vice President
State of Nebraska )
) ss,
County of Lancaster)
On this 16 day of April ,20 04 before me personally came Robert L. Privett, to me known, who being by me duly sworn. did
depose and say that (s)he resides in the County of Seward, State of Nebraska; that (s)he is the Vice President of the UNIVERSAL SURETY COMPANY, the corporation
described in and which executed the above instrument; that (s)he knows the seal of the said corporation; that the seal affixed to the said instrument is such corporate seal;
that it was so affixed by order of the Board of Directors of said corporation; that (s)he signed (his) (her) name by like order; and that Bylaw, Article V-Section 6, adopted by
the Board of Directors of said Company, referred to in the preceding instrument, is now in force,
~C~~ ~NOTMY._IfI__
CHElM.A. BROWN
My Commission Expires April 12,2007. Notary Public lit Comm. &,J... ft,_
I, Jeanne Bower, Assistant Secretary of UNIVERSAL SURETY COMPANY, do hereby certi/}' that the above and foregoing is a true and correct copy of a Power of
Attorney executed by said UNIVERSAL SURETY COMPANY, which is stili in full fo;J1 and effect. ,20 tJS-.
Signed and sealed at the City of Lincoln, Nebraska this 21ft' day of /Ylllt'
/ '-), ~:)
L_?u2tf2o.:'~><"" /.::.1-7 ::'-""____
/ Assistant Secretary
-
Lab.l'- vVLUH) .lnap Vu~pu~ r <11:;;!; Page 1 of 1
New Guardrail - Colo. River Rd.
/
'~, [J
'---......
~,J''''.....~''''>~-'''''
-
#1
"'"--........
'-,
@ (,~ '>'---(f'..~
~. "1,-
.........~.~~<W~.r-..., /'~
Copyright 2004 ,/,/,
Eagle County GIS
PO Box 850
Eagle, CO 81631
DISCLAIMER: This map was created by the Eagle County GIS Department. Use of this map should be
for general purposes only, Eagle County does not warrant the accuracy of the data contained herein.
http://gisweb.eaglecounty,us/servlet!com,esri, esrimap ,Esrimap ?ServiceN ame=ec gis&Client.,. 3/3/2005
.... L.t.6"" 1. V.L J.
New Guardrail - Colo. River Rd.
#2-
Cl>
., OH'....
If".'."<.\' Legend
,.' ...,! ,'< /V' S1ftHI.ts
Copyright 2004
Eagle County GIS
PO Box 850
_, " E.,I., CO 81631
~,~
(~m~
DISCLAIMER: This map was created by the Eagle County GIS Department Use of this map should be
for general purposes only. Eagle County does not warrant the accuracy of the data contained herein,
http://gisweb.eaglecounty ,usl serv let! com. esri, esrimap ,Esrimap ?ServiceN ame=ecgis&Client." 3/3/2005
- -L U.5'-' .1 V.l .1
. .
New Guardrail - Colo. River Rd.
NW DlSTR1CT SHO~
@
~.......~G'IIt~ . ,,0....
Il Legend
/~i .... /V' SkU!.
Copyright 2004
Eagle County GIS
PO Box 850
Eagle. CO 81631
'h"",1c4"_ ."'"
~LE~iY
'Urr1ft~r'
DISCLAIMER: This map was created by the Eagle County GIS Department Use of this map should be
for general purposes only. Eagle County does not warrant the accuracy of the data contained herein.
http://gisweb,eaglecounty, US/ servlet! com, esri.esrimap ,Esrimap ?ServiceN ame=ecgis&Client.,. 3/3/2005
- rage 1 or 1
New Guardrail - Colo. River Rd.
"
0
~ #4
I
\
(1) I
~..-.......QII!t~ . ...:,,:+-
~ LeQf)nd
if Copyright 2004 # S1rHts
Eagle County GIS
PO Box 850
,"--"'-,-' Eagle, CO 81631
t~ t::OJNf'(
"c.bfl't~
DISCLAIMER: This map was created by the Eagle County GIS Department. Use of this map should be
for general purposes only. Eagle County does not warrant the accuracy of the data contained herein,
http://gisweb,eaglecounty, usl servletl com, esri. esrimap.Esrimap ?ServiceN ame=ecgis&Client". 3/3/2005
.1 abc; 1 Ul 1
Guardrail . Frying Pan Rd.
repair -
~~---~ J
( ~
409
.....
.../
d"
._.~-?\ ) ~~~~,~
~'1f
~~d'c ,
J'" ~~
'iC_
'"$: 'iY {t
"
ii'W:~ ~
c~ V':i i&",,~ '~'''--''~ _,~~
_*':~ i*.'}" -4'~f,':4 \%" Y_,-~' "'I':r:'fiNGP^"" FlO",,4 -,~
~
* '"
i%t-f'M
,-jf> -MOuN'rAlH-cr~
ft)~""'~ ,~~ % -#,
" (;..,.. >.
""1\. "':s;:)
~.~~-~. . Q.l......
II Legend
Copyright 2004 IV" Stlaets
Eagle County GIS
PO Box 850
~~rY Eagle, CO 81631
~~
DISCLAIMER: This map was created by the Eagle County GIS Department Use of this map should be
for general purposes only, Eagle County does not warrant the accuracy of the data contained herein,
http://gisweb,eaglecounty. usl servletl com, esri, esrimap ,Esrimap ?ServiceN ame=ec gis&Client.., 3/3/2005
. _ rage 1 OJ 1
Guardrail Repair - Frying Pan Rd.
~
--~~
/-.#7
----./'
o 0. t01W
... i'~' ;V SflM;AItAnd
Copyright 2004 --
Eagle County GIS
PO Box 850
: '"",: _ Eo.". CO 81631
~i,~C'1~t!fY
''''~QJ;Ot$@&4t~~Yfg'Nr''
DISCLAIMER: This map was created by the Eagle County GIS Department. Use of this map should be
for general purposes only, Eagle County does not warrant the accuracy of the data contained herein.
http://gisweb.eaglecounty, usl serv let! com. esri, esrimap .Esrimap ?ServiceN ame=ec gis&Client.,. 3/312005
Guardrail Installation I ,,- " " u_ - ---- -------- ~i --------~~'-'~-~---~-'~--------"l
1 I
"
,
I
& Repair Locations I I
I I
2005 [ i
I I
I
I
N I
I
A
i Legend
I
Eag Ie _ cou nty _roads.sh p
COUNTY w
STATE
Counties_sp.shp !
Muni_bd.shp I
~
( !
~q
This map was created by Eagle County
Weed & Pest. Use of this map is for general PITKIN I
purposes only. Eagle County does not warrent '\
I
the accuracy of the information contained i
i I
herein. !
L_,~_~____,. I
--_.----- -,----------, ~~--_.._._...__._._-_._-_.------~---- .~
Map Created: 03/04/2005
Map Scale
20 0 20 Miles
E~~ ~~-~_ -~=r=~~ -~-~'., ..... - .. -=.='-=~='~
(SEE NOTE 3) 'h --; -NERAL NOTES
t--* -----,
lAIN, 7' POST IDENTIFICATION I. RATE or SLOPE DEPEN05 ON GUARDRAIL LOCATION:
1"
li- OBSTRUCTION (SEE NOTES ON SHEET 2) - FOR GUARDIWL FAtE ~. FT, OR LESS FROM THE NORMAL EDGE OF PAVED
TF 2' MIN. SHOULDER, CONTINIf \!'IE RATE OF SLOPE OF THE NORMAl PAVED SHOULDER
(SEE NOTE ~) TO THE BREAKPOINT,
*27" - FOR GUARDfIAIL FN:I: t>RE THAN 2 FT. FROM THE NORMAL EDGE OF THE PAVED
' , OJ
NORMAl EDGE SHOULDER, /HE SLoPE'.3lHALL BE 10:1 OR FLATTER,
*27" "
OF PAVED WHEN SPEClf[D ONrnr:,ptJ,NS, EXTEND A 2 IN. MINIMUM THICKNESS PAVED SURFACE re
21- SHOUlDER 2_
. 1. .
1 FT. BEHIND THEGUAiR~ POSTS OR TO THE EROSION CONTROl CURB AS SHOWN 0/1
ASWLT ctJTTJ1KJ& PAQNG OR OTHER N'PRMD METHOD SI-WJ. BE USED TO MINlldlE I
, ,
TO All PAVED SlJRf'ItE$: UNDER GUARDRAIl: INSTAllATIONS, COST FOR AlL REPAIRS TO TIfE
1.5: I MAX. stOPE PAW AREA MiL NOt af MEASURED AND PAID FOR SEPARATElY BUT SHAlL BE INCltJDED
,/ AT POST THE COST OF.THE wORk; ,A MINIMUM J IN, THICK FIBER REINFORCED CONCRETE PAVEMENT'
- 2" MIN. HB~~ AlSO BE USED FORPAVliic BENEAm THE GUARDRAIL INSTAlL POST IN A J1 IN. OVERS/2m
(5Er NOTE 2) ~ FORMED P.otE tOR IfAll:~NS AND TERMINAlS AS DIRECTED. PAYMENT FOR THIS PAVED SVR
EARTH SHOULDER WlLL BE MADE UNDER A iPAVEMfNT OR CONCRETE PAY ITEM WITH OUANTITIES SHOWN ON WE
OR 2- MIN. HBP 6' POST~
(SEE NOTE 2) 7' POST~ . J. . THE MINIMUM GI{/'RDRA1l~SU FROM PAVED SHOULDER EDGE SHAlL BE:
o FT, FOR SHWtDERS FT. OR WIDER
NORMAL ROADSIDE INSTAlLATION 2 Fr. FOR SHlXlLDERS;1; FT. OR lESS
RESTRICTIVE ROADSIDE INSTAlLATION THE' ABWE.. 2 FT. ~ TO SHOULDER OFFSrr IS DE'SIRABlE aUT NOT REOUIRED FOR~
. . D I WITH 7, fOOT GUARD A OSTS f. EXISTING lIIGllWAY ~ DESIGN SPEED OF lESS THAN 50 MPH. MINIMUM OFFSET
* FOR OVERLAY PROJECTS, RESET Of GUARDRAIlS (SEE NOTE 4) Of RAIL IS 0 FT, ^ Am WIDTH PAVED SHOULDER OR 4 FT, FROM TRAVElED WAY,
II. ~ ONE-WAY bNE~ RAMP AND:
ARE REQUIRED IF H < 24 IN,
- THE 1lO1I-0fF!iifr GUARDRAIL OCGlNS AT lEAST 100 fT_ BEYOND RAMP NOSE.
n J' MIN. -:- - THE HOtt-OFfS9t GUARDRAIlfS NOT LOCATED eN THE RAMP EXIT OR ENTAANCE
CURVE <lONf.EGItofl TO THE: MAJOR HIGHwAY,
OBSTRUCTIoN - THE /WdP. ~ ARE 4 fT. OR WIDER.
2' MlH. I
*2r TYPE 6 CURB USE OFGRE'A1ER THAA.,ijlNllMI 0ffSf:T DBIENSIONS IS 'ENCOORAGED TO L/ffT THE
DESIRABlE GQlL or ~ THE GUARDRAl. AS FAR AS PQSS/9tt FROI./THE TRAVEUD
aRtAKPoINT WAY, EVtH FOR SWRT ~ANCES, WHIlE PRO\IIOING A SMOOTH ~E IN GUARDRAIl.
. AUGflMENT. (
J ' !
,"'-~=' oJ. F 2 IT; CAHNOr 9E '~DED ,BETWEEN nE BACK Of lHE GlJARORAIl POST AND
'THE BREAI<POtIT. USE' i' FT. GUARORAIl POSTS, REFER TO THE "RESTRICTIVE
ROADSIDE /NSTAIlArKJt( ptrA/t.
1:::f 5, WHEN SPECIfEl) Ot>l ~ P!J\NS, INSTAll 4 IN.. HIGH TYPE 6 CURB WITH 1TS FACE AT OR. BEHIND
(SEE NOTE 5) TH,E RAIL fN;(. AS, AHft/-TERNATlVE WHEN SPECIFIED ON THE P\JoHS, INSTAll A 2 IN, x 6 IN, .
OPTION ,B TREATED (MSlITO 1.1 1ll) WOOO CURB FASTENED WITH A 4 IN. lAG BOLT AND WASHER
OPTION ROADSIDE INSTALLATION AT EACH WOOD POST, ~ WJTH A Yl/N,' w.. BOlT WITH WASHER AND NUT AT EACH STEEL posr.
WITH EROSION CONTROL CURB IF 1HE 2 '1'1, x 6 It ~ CURB IS SPECIflED, IT WIlL BE INClUDED IN THE COST OfTHEGUARO~
IF APPROVEfJ BY TJI( EJ.;(ifNffR, A 2 IN, x 4 IN. TREATED WOOD CURB MAY BE SUBSTII1JfED
RAIL FN;E TO BE '8' MIN, FOR mE 2" x 6" CUrt;(1ND SET ON TOP OF PAVEMENT SURfACE AND A1TACHED AS DESCR/BEO ABO
AT ORIN FRONT ~ IF RAIL FACE IS NOT NO SPUCING SIIAlL St ,a.LOWED IN WOOD CURBS. ADJACENT BOARDS SHAlL BE BUTTED TOGETHER
OF CURB FACE AT OR IN fRONT 151 AND SOl TED AT A POSt-OCAllOl'I. JOINTS SHAll. BE LOCATED AT THE POSTS.
(SEE NOTE 7) ~ OF CURB FACE , BREAf<PO/IfT ONE POST MAY BE OMRt:O IN A GUARDRAIl RUN, SUCH AS AT A PIPE CULVERT
6.
2?" (NOTE J) WITH MINIMUM COVER:. HE W-BEAM RAIl SPANNING THE OMITTED-POST GM> SHAlL BE
. C::::=... DOUBLED (ONE RAIl MSff:O IN'THE OTHER) AND SHALL EXTEND A MINIMUM OF 6 FT,-J IN_
~ i / I ----. -:---.::: ON EJ1I-JER SlOE OF T/fGAP, USING 12 FT.-6 IN. RAIl SECTIONS. 'ONE OMITTED POST.
I DEPENDING ON SPUfE 1iCAmN, REQUIRES 25 FT, OR 37 FT. - 6 IN, OF NESTED RAIL
PO/NI OF SLOPE SEE NESTED RAIl AT imrrD POST OETAll ON THIS SHEff,
URBAN ROADSIDE INSTALLATION WITH CURB AND GUTIER SElEGnON (POSS)
N!!RMAl' FlttStDPE ], SEE SHEET 6 FOR cum TREATMENTS. AT GUARDRAIL TERMINAlS.
t OMrrITo~r: r'-J'~~R5, NORMN.. CATCHPO!NT NORMAL CEf\1J1.R- TO-CENTER POST SPACING
Wi = RAIL SPUCE
~~ EMBANk;M.ENT WITH GUARDRAIL -----
WCATION SPACING
~T --',--
l (NOTE: THE CATC/JPOINT REMAINS THE SAME AS THAT FOR ALL LOCATIONS 8cEPT 5' -3-
I..... NESTED RAlL "NORMAL" Fill StOPE, FOR THE WIDER "z" DISTANCES, THE BRIDGE RAIl Loqi(lNS
--.....;.---- -
NESTED RAIL AT OMITTED POST VARIABLE SLOPE MAY "CATCHn AT THE POSS.) BRIDGE OR STRlJ(T;ffZE APPROACH SEE: SHEErS
10 & 15
(5EE NOTE 6) -.~
Colorado Department of Transportation Computer File Information StandiJrd Plan Revised GUARD RAIL TYPE 3 STANDARD PLAN NO
--.
Dote: Comments:
~ () 1'/ 4201 East Arkansas Avenue Path: www,dot.state:co,usjDevelopprojecls jDesignSupparl jMStandards j ~,
W-BEAM M -606-1
u, Denver, Calarodo 80222 (30J) 757-9820 Drawing File Name: 606010101S.dwg
=--=-~ Phone: (J03) 757-908J FAX: -
;'~~~,,:'.'':'.' .::' '.l,.'.~ :.... .r,". --- Issued By: Project Development Bronch O<:\obe( 1,2000 Sheet No" 1 of 15
D...", jo.-~ no\/ol,-,nrn.ant Rrnnr:h so Acad Version: R 14 Scole: NA Units: Eng/ish
- -
GENERAL NOTES
1. ALL W,BEAM SPLICES, AND SPLICES OF TERI.~ CONNECTORS 9. WOOD BL0CKS SHAlL at: CUT FROM THE SAME CROSS-SECTION, SPECIES,
I 191/4 n TO VI-BEAM SHALL BE LAPPED IN THE" DIRECTRJI'/ OF TRAFFlC AND GRADE AND SIiA.ll RECElVE THE SAME PRESERVATIVE TREATMENT
UNLESS OTHERWISE MOTED. ?S THE POSTS WHf/4 WOOD POSTS ARE USED.
16" TWO 16d CALVo 2. MATERIAL TYPE AND SHAPE OF POSTS AND BLOCKS SHAll BE THE SAME 10, RU'ERtNCES SUCH AS "PDB01". "POEDl", AND "PWE01"
NAilS (TYPICAL) THROUGHOUT THE PROJECT EXCEPT WHEN SPECIFIC POSTS AND BLOCKS iN THIS STANDARD $PEGIFY HARDWARE DETAilS ARE FROM "A GUIDE TO
-----r ARE SPECIFIED SUCH ?S AT END ANCHORAGES AND BOX CULVERTS. STIWDAROIZE[) HIGhWAY BARRIER HARDWARE" PREPARED BY THE
I AASHTO"-AGc--ARTBA JOINT COOPERATIVE COMMrITEE.
' 14" 3. CONCRETE MAY BE READY-MIXED OR FIELD-MIXED AND SHAll CONSIST "
BLOCK Of A' MINIMUM Of 1 PART CEMENT TO 6 PARTS AGGREGATE BY VOLUME, 11. NOTCHED PAll BLOCKOUTS MANUfACTURED fROM SYNlHETlC MATERiAl
Will BE AllCEP1tD AS AlTERNATIVES TO WOOD NOTCHED BLOCKS
" . % . HEX /oIUT 4, WHEN' $PEClFlED IN THE CONTRACT, 7 FT. POSTS' SHAlL BE , FOR USE WITH STEEl POSTS PROVIDED mAT THE BLOCl<OUTS HAVE
% D/A. x 18 BOLT AND WASHER INSTAllED INSTfAD OF THE STANDARD 6 FT, POSTS, 7 FT. POSTS RECEIVED fHWA AP1>ROVAl AND ARE CERTIFIED AS IDENTICAL TO THE,
IN 3/4 . HOLE SHAll. BE MARKED WITH mE NUMBER 7 TO ENSURE Sf'ECiMENS USED FOR TESTING AND APPROVAl,
PERMANENT IDENTIFICATION. THE NUMBER 7 SHAil. BE A MINIMUM '
2 IH. li\ll AND lOCATED ?S SHOWN IN THE ElEVATION VIEWS f2. WOOD POSTS. SHALl; BE MADE OF TIMBER. WITH AN EXTREME FIBER, STRESS
SEE NOTE * ON SHEEr I. IN BENDING OF 12CO psi. STRESS GRADING AND POST DIMENSIONS SHALL BE IN
, IN ACCORDANCE WITIi mE RUlES OF THE' WEST COAST INSPECTION BUREAU OR
5. THE ST..4.NOARD J" x 1 %" X JA6' RECTANGUlAR WASHER THE SOUTHEkN PlNIi BUREAU OR THE WESTERN WOOD PRODUCTS ASsocllinON.
USED UNDER POST BOLT HEADS IN THE PAST MAY REMAIN IN . TIMBER fOR posis SHAlL BE EITHER ROUGH SAWN (UNPLANED) OR
EXISTING INSTAllATIONS BUT SHAlL NOT BE USED IN NEW S4S (SURFA$> FOQ'R SIDES) WITH NOMiNAl DIMENSIONS, INDICATED.
6' WOOD POST CONSTRUC1l0N, REPAIRS, OR RESETTING Of RAIL mERE ARE EXCEPTIONS ONLY ONErWt Of;SURFACE FINISH SHALl BE USED FOR POSTS AND
REflECTOR TAB WHtHE RECTANGUlAR WASHER lOCATIONS ARE SPECIFlCAlLY IDENTIFIED BLOCKOUTS IN ANY 'ONE CONlINUOUS lENGTH OF GUARDRAIL
(SEE NOTE B) ON THIS STANDARD PIAN. ,
, 13. PRESSURE TRE'AThIE'ff Of POSTS AND BLOCKS SHAll BE IN ACCORDANCE
6. STANM'lD GALVANIZED ROUND STEEl WASHERS SHALL BE USED UNDER Wffil AASHrO U1.ll ExCEPT THAT BlOCKS NEED NOT BE INCISED,
AlL NUTS IN COIffACT WITH WOOD POSTS, PffiSERVAllON ASsAY RETENTION REPORTS SHAll BE fQWA/IDEIl TO
.. THE ENGlNEI1'r.~COUTRACTOR SHALl CERTIFY THE SPECIES AND GRADE
7. REFlECTOR TABS SHALl BE INSfALLED AT 25 FT. I~ALS . MEET THE REOUlllf}.i~ OF THE CONTRACT.
(SEE SHEETS.5 AND 7 OF M-60IH fOR EXCEPTIONS), . .
(PDBO 1 & PDEO 1 ) REFl.ECTOR TABS WU NOT BE PAID FOR SEPARAffiY 14. W-BE'AM AND lHRlEfSOO GUARDRAIL POSTS SHAlL BE MANUFACTURED
. . BUT SHALL BE INCLUDED IN mE COST Of THE GUARDRAIL, USING MSHTO M27{} (ASTM A709) GRADE 36 STEEL UNlESS CORROSION
5/8 OIA. x 18 BUTTON HEAD BOLT .1HE TABS 'SHAll BE MOUNlED SO THAT mE BOLT SLOT STEa IS REQUIRED ilN WHICH CASE lHE POST SHALL BE MANUFACTURED
WOOD POST & BLOCK F.A.CfS AWAY FROM TRAFFlC AND THE REFLECTOR/ZED SURFACE, FROM AASHTir M27c1.(ASTM A709) GRADE SOW STEa THE DIMENSIONS '
FACfS mE APPROACHING TRAFFIC FOR ONE-WAY ROADS, FOR, Of mE CRoss.-SE<;jJON SHAll CONFORM TO A WIi x 9SECTlON AS DEFlHED
(DIMENSIONS SHOWN ARE FOR NOMINAL 6"x 8" POSTS. & BLOCKS) ': 1\'IO-WAY ROADS, BOTH SIDES OF THE TABS. SHAlL BE REFLECTORIZED IN AASHTOI.I160 (A$M AS). W6 x 8,5 W10EFLANGE POSTS ARE AN
. SO THAT DEUNEAlION IS PROVlOED FOR BOTH DlRECllONS Of TRAVEL 'ACCEPTABlE AlTERNA;TIVE .THAT IS CONSIDERED, EQUIVALENT TO THE
REarcroRIZAlION COLOR SHAll MATCH' THE COLOR OF lHE: ADJACENT W6 . 9 ?
TRAVElED WAY EDGE UHf. SEE TAB DETAIL ON SHEET 3. x .
* NOTE: AN AOOITlONAl HOLE SHAll BE PROVIDED 8. AT THE TIME A POST 'OR BlOCK IS INSTAlLED, NO SEASONING CHEC/{ 15. AfTER mE SEcnOlflS CUT AND AlL HOlES ARE DRIUfD OR PUNCHED
IN POST TO FACIlITATE FUTURE RAISING Will BE: PERMITTED wHICH EXCEEDS 1/ IN IN WIOlH WHEN THE THE CPMPONENf ~ BE ZINC-COA1ID ACCORDING TO MSHTO MIll
OF mE RAIL FOR OVERLAYS, .. ' . /4' , . (ASTMA12J) UN!IS~ CORROSION RtslsrANT Slffi IS USED, WHEN
CHeCK EXTENDS THE fUll lENGTH OF THE PIECE. CORROSION RESIS'fA.>(r STEEl IS USED mE PORTION OF mE POST TO' f1E
SEE NOTE EMBED[lED'IN sOil SHAll BE, ZINC-~OA1ED ACCORDING TO MSHTO Ml f 1
* (ASTM AI2J) AND TrlE PORllON ABOVE THE SOil SHAlL NOT BE
ZINC-CDATtlJ, PAINT{:D OR OTHERWISE TREA1ED.
~~~ .
~W w
W J~' 21/"
/2 31;'"
~ 1"'1 4
31/4"1~ -. . r . ..
- ]]~6~CHED zt. (
BLOCK '7" I
.. ~%' HE! NUT
s;a" DfA. x 10' BOLT . AND WAsHER.
IN 3/4' HOLE W6 x 9 POST 6' WOOD POST !
10 __. ______ ,. ~ ....~ .'_y~ y'.. . . . .... """ ......",v....,,~,".
5/8 ~;;H~~T'0;~\y/,.}i)):,,)>y);>>';0 . ?,'Y>;YA ,,>,W),'y)' '''0~<<R::;~k~2;~~ ~~~~~~~'<<<~
AND 3/4" Of A. HOLE IN BLOCK .
SEE NOTE 15
(PWE01) TIMBER r=J ~ 0
STEEL POST & NOTCHED BLOCK DOUBLE BLOCK AND RA/L MEDIAN BAPR/ER
. (NOMINAL DIMENSIONS ARE SHOWN FOR THE POSTS &: BLOCKS) GUARDRAIL TYPE 3 (DOUBLE)
, '
"'a/arado Department of Transportation Computer File Information Date:Standard P/~o~m~~~~ised GUARD RAIL TYPE 3 STANDARD PLAN NO.
~ 0 D 4201 East ArKansas Avenue ' Path: www.dotstate.ca.us/DevelopProjects/DesignSupport/MStondords/ - . W BEAM. , M - 606 - 1
~~~. - J
~=--~ Phone: (303) 757-9083 FAX: (303) 757-9820 Drawing File Name: 6060102015.dwg .
~~j;;~'PoR~:velopment Branch SO Acod VersiDn: RH Scole: NA Units: English .~~ Issued By: Project Development Branch October L 2000, Sheet No. 2 of 15
-58-
12,5' SPAN t 12.5' , ,
1 08STRUCTlONr N:]' J7.5 - 12.5 Fill REOUIRING GENERAL NOTES
TO NEAREST FT uR FT OR
12'-6" ,NFT I'IFT GUARDRAiL L THE 2 FT. OFFSET FROM THE EDGE OF THE PAVED
,/' ",,- SHOUlCtR TO THE FACE OF THE GUARDRAIL (FOR
' ,6'-J" / - /- ......--/' SHOUlDeRS 6 FT. OR LESS IN WIDTH) IS DESIRABLE
,01. 0 0 .0., . . .. ... .-:1...... -- /- '. // aUT >lqt MANDATORY WHEN lliE RDAfYNAY DE~GN SPEED
, t, '\ IS LES~1c.THAN 50 MPH. THE MINIMUM OFFSET OF GUARDRAIL
VARIES t 10:/ OR FlATTER FROM T~E EDGE OF TRAVELED WAY IS 4 FT. '0" IS THE EOGE OF
AN 8 Ff. OR 10 IT. SHOULDER. "b" IS THE EDGE OF .AN 6 IT,
DR IfS~ SHOULDER. SEE NOTES AND DETAILS ON SHEETS I, 13, &
~ 2, THf 1Yfk 3G OR 3H TRANSITIONS (i:e. SHITT 10)
ONE-WAY ONE-WAY ONE-WAY sl'fAU $E USED TO CONNECT A TYPE J W-BEAM TO
. A TYPE f4 OR TYPE 7 CONCRETE BARRIER OR TO A TYPE 4, 7, B
H N OR to BRIDGE RAIL FOR A TRANsmON FROM A RONJWAY ,
'f l SPAN r -:r 7 ' RLL REQUIRING TYPE J Uv-BEAM TO A BRIDGE RAIL lYPE 3 WITH BACKING WBES
37.5 N OBSTRUCTION N FTJ 0.5R GU'AODRAIL ' FILL REQUIRING THE TR.1N" SIT/ON TYPE,3L SHOWN ON SHEET 15 SHALL BE USED. .
FT OR TO NEAREST fV\ FT OR GUARDRAIl '
12' 6" NFT - NFT ' .
NFT, - _-...--.--- (IN Fli) __--.----- ~--" ",,- 3. 'TR" \\1tL BE 18. FT,-9 IN, FOR THE TRANSmONS1YPE 3G
_ 0 0 0 J'. 6'-3"-{ .-//_v . '. /~ AND 3H!.ANO 25 IT. FOR THE TRANSITION TYPE JL
. . , . ~ 4-. "FT" IS THE END ANCHORAGE (FlARED) AND
. . _ 1,1>., OR flAm:. , "NfT' 'i THE END ANCHORAGE (NO NflARED).
. / / ' /" b 5. rHEo GU.kDRAIL lENGTH DIMENSION "N- IS THE lENGTH
~~}591'tjJ5 ~~:Jf_ 15 Dt.tF.RMINED BY THE LENGTH OF NEED COMPUTATION
~ '-< <' .AND IS .'SHOWN ON THE PLAN, S, THE MINIMUM IS 12 FT.-6 IN.
""' <' WHERE SfTE CONDmONS ALLOW. THE OVERAll REQUIRED lENGTH
- - - - - TWO-WAY - - - - - - - TWO-WAY - - - - - - TWO-WAY _ _ _ OF NEf;D CAN INCLUDE TH~ LENGTH OF TRANsmON,
.. ,. )> 1HE lEf,4GTH' OF RAIL (N), AND ANY REDIRECTNE
.lENGTH:/N THE RAIL END TREATMENT.
D DE OBSTRUCTIONS GUARDRAIL FOR GUARDRAil FOR
GUARDRAil FOR ROA S/ , ' ROADSIDE FILL CONSTRUCT/ON ROADSIDE CUT-TO-FlLL CONDmON
J~5' J~5'l
/F[AR DRIVEWAY FfJR J7'5'1rx::rTRt" BRlDGE1TR I = g ~R~
Ff QR 0 m LENGTH
NFT . " .
3D (FOR I.IUlntANE) . R .. ~ 'TO FIT
, . flEIJ) eoNflITlONS
o 0 (MIll, ~. = 6.5 Ff,)
b b
.(
------..--...p-
>
b b
LAYOUT FOR DRIVEWAY APPROACH a. i- 6:-r '. .,. ", a
1625' ~ ~7;;; t " mL BRIDGE J m J. L,fd: GLIARlJIWl WE , WITH BlDCKEll OUT POSTS SP",,"
125' * J7S' NFT NFT AT 37 FT.-l/2 IN. FROM STRUCTURE AROUND CURVE
I . APPROACH .
NARROW STRAIGHT FlARE FROM BRIDGE FT EXIT
BRIDGE I- TR . .-1 I-- ' ' INTERRUPTED
I 6 -J .1 J ,t>""~1';"\'-':--"~'SHOULDER~ 2-WAY NORMAL BRIDGE APPLICATION STRUCTURE APPROACH
~ BRIDGE WIDTH OF
- - - - TWO-WAY WIDTH - - - TRAVElLED - (USE 1YPE 3J ON SHEEr 11 WHEN PRACTICAL)
~ . WAYS
I-TR '
* RAlL LENGTHS ARE MINIMUM. ADOmONAL LENGTH
TO SATISfY GUARDRAIL WARRAmS SHAll BE PROVIDED.
2-WAY NARROW APPLICATION
Colorado Department of Transportation Computer File. Info~mation Date:Stondard Pl~~~llf\~:~ised GUARD RAIL TYP E 3 STANDARD' PLAN NO.
~ 0 Tf 4201 East Arkansas Avenue Path: www,dot.stote,co.usjDevefopProjectsjDesrgnSupportjMStandords/ '
~.- Denver, Colorado 80222 W BEAM M - 6 0 6 - 1
===----== Phone: (303) 757-9083 FAX: (303) 757-9820 Drawing File Nome; 60601014015,dwg -
~~~....P.PJ~r ':;r "".J;H::i,"OIi'.llll)."
Project Development Branch SO AcodVersion: R14 Scale: NA Units: English - Issued By: Project Development Bronch October 1, 2(:00 Sheet No. 14 of 15
-70~
/ t ~~V!SIONS
POST NO.1. '! , ' ,
o'-j" ~ , 0" . 6' WOOD ....-12 GAGI. STm TO Bl' TAD< ,I . . . . ' .
2 J~. 'WELDfO AT j" SPACING INTO r'
I ' PO~ NO; -- ! -- 12 GAGE TERMINAL BREAKAWAY POST :. TERMINAL SECTION (BUrfER)
, 6' x 8 x.6 WOOD , ( ~16"---j SECTION (CONNECTOR)_,., 'Gj NOILS FOR TYPE 3E
BREAKAWAY POST" '. \ ! . 11" RADIUS TERMINAL , . Co '
.. u"" .. SECTION (BUFFER) . J '. .
<:I14141~ 1/2 12 GAGE r'~ ,D'AlNAG' HOLES L SEE sNtm J, 2 AND J FOR STANDARD TYPE 3 GUARDRAIL AN
I (SEE NOTE 4) /~~), DETAILS.
o /. .~ .
I :P , '-5" TO 6" j5 HOLE . 5" TO 6" 2. STANDARD WOOD POSTS WITH BLOCKS SHALL BE USED FOR PO~
'-ANCHOR PLATE' 18" WELDED 7" 1 HOLE ,7 OF THE TYF'F: 3E END ANCHORAGE. POSTS 1 AND 2 SHAll 8
. . DJAPHRAGM t . BREAKAWAY P€,STS (WITH 2%" P HOlE) ANO WITHOUT BlOCl<S,
' HEx NfAD BOLT '20'.... BOlTED WELDE.D 3 TAIlS WITH a AN "''''''''''' .i-o.-ATION m THE CONCRETE Fom"., FOR POS"
". ~ · DIA BOLT AND'M BOLT HOlE THE STEn:. wtlH 5 1/2" , 7 1/2" POSTS AS _ on s>
" RECTANGUlAR WASHER . 'CONTR;.GTOR ~y CONSTRUCT EITHER THE CONCRETE, OR STEEL ruE
- UNDER BUFFER (2 REQUIRED) HOWEVER, IHr!(SAME TYPE OF FOUNDATION SHALl, BE USED FOR E
1 r;- -; -:- -; ... .,- 1 &: 2 IN AN jSTAllATlON,
'~-='~~-Jt.-4. 0 TWO DIAPHRAGMS: 'BOLTED 'i'
I f. ~....-;r-~-.."..:'''O';;:::..... 8 + APART WElDro 4, THE TYPE 3P, NOSE MAY EITHER BE A SiNGlE PIEcE OR IT MAY cc
1'2..-J:..=.=16'~' .....~..... , 12 t APART BOLTED.' DIAPHRAGM TERMINAL st<ihoN (BUFFER}, RE-7-79 AND A TERMiNAl ~EcrION 1
~":t TWo lOd CALv. NAILS RE-8-79, ,1M EITHER CASE. ~O DIAPHRAGMS SHAll BE INClUDED
' BEARING PLATE 8" x 8" x %" S MAY BE BOLTED OR WELDED INTO THE NOSE.
(SEE' NOTE 7)- 2 HEX'NUTS AND WASHER FOR' 5, PAYMENT ,f'OR'rHE ADDED EMBANKMENT (APPROXIMATELY 60 CU. YO~
TIMBER WEDGE 1" SWD (SEE NOTE 7) FlARE SHAll BE AS FOLLOW$:
" (SEE NOTE 9) , '-~.. cROWN (TYPICAL) , J' 8" f' _ U~fR PAY ITEM 203 WHEN THE CONTRACT PlANS INCLUDE PAY 11
~:t 2" 1.0. x 6" STO, J,'L 4" . 1 %' _ INClUDED IN THE COST OF END ANCHORAGE, TYPE 3E, ITEM 606 P
PIPE SLEEVE IN ~'" 1:----1 i --4 r' WHENTf-fE: IX>NTRACT PLANS DO NOT INClUDE PAY ITEM 203,
2%" i1 HOLE . , f',; . . ' I, :. ..'
F-34-76---- lK 1 J ./ nr.; PHOlEllii ----r ~ 6, 37.S'P-o/?Af3OI;IC FlARE DIMENSIONS:
I "I I, I, Posr;NO.: 7 6 5 ' 4 .3 2
r--- " ' lY,~ DIA. _"-Jl 8" HORl;;PNTAt: 0,0' 6.25' 1-2.49' 18.72' 24.92' 31.09' .3
.. . 1 " ' . , -7 '.. J OFFSET: 0,0' 0,11' 0045' 1.01' 1.79' 2.79'
INSTAll POST '" l1i OIIERs/ZE.. 2Y. J J ./ ~ " . 2...... "All LEH<1H, 0,0'. 6.25' 12.50' la75' 25..... 31.25' 3;
FORMED HOLE (SEE NOTE 9) . ' I . , t",,' ,
L-~" " . ~ '% STEEL PLATE, 7. 'TiGHTEN 'CABlE; ASSEMBLY TO A TAUT.CONOITJON ON INITIAl INSTALLATION.
3" CLEAR. TYP. ' .. 1 8 '-% PLATE '. TENSION CJi1fCX' REQUIRED, AND TAUT CONDITION RESTORED IF NECE:SSAl
\...24.. DIA. CONCRETE FOOTING ON POST NO: t AND 2. . F-.3o(HOlE REVlSEPJ-79 DAYS AfTER IiSTALLATION OR BEFORE COMPlETION Of' . PROJECT. THE Ol
(SEE NOTE 3) " ,', . F-38-!9 , BEARING. PLATE NUT SHAlL, BE'TORQUEO SECURELY AGAINST THE INSIDE NUT.
. '-""";W1.4. W!.4 WELDED -.: FAB~~______________________________________________.EHJ:LELA1E ---------------;--mR-CO~--- ., 'H< ,... "" 'EET OF 1>IE w-a.... RAIL .. THE PARABOlIC FlARE ,,^Y
-'~ (LA. ONE SOlJ..RC) , : ENCASED' POSTS EITHER ONE 25 FOOT stenON OR lWO 12'-6~ SECTIONS
' TYPE 3E 'END ANCHORAGE ", .
' " . 9. USE crDA~ Of? PRESERVATIVE-TREATED nMBER WEDGES ON Tl;iRE,E SJDES
' 6" POST PLACED IN OVERSIZE: HOLE. OR WRAP EMBEDDED PORnON'Of' ORICl
I. 6 ~ ! " POST ONLY 'M!H POL YSTl'REJ<lE %?" THICK, TO FACILITATE POST -Rtf'LACEMl
~'" DIA. x 7" LONG STUD ;
: "THREAOED..ENTlRE LENGJ}f ! END PLATE...... 1--16" LONG.....>.<:-
5~ . , " ,
.... ! 1WO HEX NUTS AND (' 1 2" ."
SURFACE %" r r:J ..--* VIA. (6xI9) GALVANIZED., I WASHER FOR I" -STUD "i f. I
. '. / 1{-*1'1 ..... CAStE 10 BE SWAGE-CONNECTEO . (SEE NOTE 7) '.~.
. BAS~ ' P' .' ~ " " . 1"-35-76_ I:<:!:> G:)
. ... . _ ...-' W""_""'" WUu~~ " ;___' ..
SU!'lBASE f L .L 1/" '. , :X6 THICK
5......J 1/4, 5 ..
1%-, .. ....STANDARD SWAGEO 'CONNECTION. I STEEL PLATE Ya MACHINE BOLT'(.
115.1" ---l, FOR CABLE AND STI'D BOTH ENDS '--, REOUIRED) AND CUT
/16 J ,. / WASHER ON FRONT
POINT OF SLOPE SELECTION 1"-.37-76 , 1" DIA, STUD" FACE OF RAJl
W D-D ANCHOR CABLE \, ~.. DIA, (EIGHT)
VIE ,NORMAL CATCHPOlm (DOES Nor CHANGE) RE-71-79
, D-, ANCHOR. PLA TE DETAIL
+ (W-BEAM RNL NOT SHOWN)
'--7 J TYPE 3 GUARDRAIL PAY lENGTH I 10' ; ANCHOR PlA TE DETAIL
6" )C a" WOOD BREAKAWAY P.OST_____ ]"-7" -(END PLATE NOT SHOW)
I BREAKPOINT --.., MIN.' a: -: ~ EDGE OF PAVEMENT N
'. , I 1,1 w' I
',- ,2 ... C--J- 0 >" ; ,BREAKPOINT
t'O:I tAX, SLOPE ' :5;;5 / : \. --ANY CURB IN THIS AREA MUST C 0 LOR ADO
POST NO. 7-\ 2'1, 65 _~4 ~ m, i' -S ! ~~r-1' ;' BE AT THE: EXTENOED PAVW DEPARTMENT OF TRANSPORTATI
l.~l ~ ~ " . ":: lfl W....J ", !' SURFACE EDGE,
\ -101' 1.79 NJ a. u... ~-'~xTEND PAVED SURFACE. ,1 ,
CURB LOCATION l..' 00 ' . . , ~ ~ . GUARDR
SrrFONROTE 7 ON. SHEET T "'0.00' "0.11' '0,45' FACE OF RAIL FOR 2' DESIRED-. ~ v:g 'L 'ADO TO PAVEMENT . ~l....... AIL TYPE 3
( . ,~---j STRAIGHT SECTION O' MIN. I a.. OUANTJTJES FOR PAVEMENT ............
t ,/ l '--NO'RMAl SHOULDER EDGE LOCATION ~ W _ BEAM
O' MIN, \ 6 SPACES AT 6'-3" = 37'-6" PARABOLA - ~--40'---______ (TYPE 3 E)
. 2' DESIRED) . D .
(SEE SHEET 11) -- DO NOT USE RECTANGULAR WASHERS AND DEL/NEATOR TABS
UNDER BOLT HEAD AT RAIL FACE ON POSTS NO, 2 THROUGH No.7.. PLAN VIEW ISSUED BY STANDARD PLAN f'.,
STAFF DESIGN BRANCH M' 606 1
TYPE 3E END ANCHORAGE BREAKAWA Y CABLE TERMINAL (BCT) FLARE DATE. _ _ _
. REVISED pATE: NOY. 1, f992 SHEET.I:) n~ 1')
~n __