CHANGE ORDER NUMBER 1
CONTRACTOR American Civil Constructors
Contract for Berry Creek Skatepark and Playground
Contract Date October 12, 2004
TO: American Civil Constructors
You are directed to make the changes noted below in the Subject Contract. Appropriations to
cover the costs of additional work have been made.
EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS
By:
Tom C. Stone, Chairman
DATE: ~~~/y~t%~
Nature of Changes:
1) In order to eventually install restroom facilities on the Berry Creek Skatepark and
Playground site, water and sewer lines must be installed. This change order covers the
cost of utility installation. A cost itemization is attached as Exhibit "E".
2) Due to the additional work directed by Eagle County, the contract date,must be
extended by twenty (20) working days from July 15, 2005, to August 12, 2005, for
substantial completion.
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to this Change Order $943,552.50
Net Increase Resulting from Change Order No. 1 $126,845.00
Current Contract Price Including this Change Order $1,070,397.50
Change Order No. 1
Page 2
Contract Date Prior to this Change Order
Net Increase Resulting from Change Order No. 1
Current Contract Time Including this Change Order
The above changes are recommended:
July 15, 2005
20 Working Days
August 12, 2005
r
4;~> • ~ ' ~
Helen Migchelbrink
Interim Facilities Management Director
Date: ~~~' ~,~ ..7~ ~, ~ U?~- `~
T
The above changes are accepted: American Civil
Title: ~ 1 G ~ ~ ~-S ~
Date: ~ ~' 6 ` D S
. .'
EXHIBIT "E"
merican
ivil
or~s~ructors
pocky Mountain Heavy Civil
4901 South Windermere -Littleton, Colorado. 80120
Phone (303) ?95.2582 Fax (303)347.1844
uate: ~ ~/z~/zuu
Submitted To: Eagle County Bid Title: Berry Creek Utilities -Proposal 017
Address: Eagle, CO Bid Number:
Project Location:
Contact: Project City, State:
Phone: Fax: Engineer/Architect:
American Civil Constructors is pleased to quote the following items on the above referenced project.
Line No. Item No. Item Description Estimated Quantity Unit Unit Price Total Price
eason 1
01 4" SDR 35 150.00 LF $30.000 $4,500.00
02 6" SDR 35 345.00 LF $33.000 $11,385.00
03 8" C900 PVC 380.00 LF $40.000 $15,200.00
04 4" Line Cleanouts 2.00 EACH $700.000 $1,400.00
05 6" Line Cleanouts 1.00 EACH $775.000 $775.00
06 4' Dia Sewer Manholes 2.00 EACH $1,650.000 $3,300.00
07 8" CL52 DIP 660.00 LF $60.000 $39,600.00
08 6" CL52 DIP 15.00 LF $57.000 $855.00
09 10" CL52 DIP 165.00 LF $66.000 $10,890.00
10 10 "Gate Valves 3.00 EACH $2,800.000 $8,400.00
11 2" Copper 280.00 LF $33.000 $9,240.00
12 1" Copper 175.00 LF $24.000 $4,200.00
13 Meter Vault 1.00 EACH $5,000.000 $5,000.00
14 Hydrant Assemblies 2.00 EACH $4,800.000 $9,600.00
15 Surveying 1.00 LS $2,500.000 $2,500.00
Total Price for the above Season 1 Items: $126,845.00
Total Bid Price: S1Z6,845.00
Notes: 'Meter Pit does not include meter. Meter is to be provided by ERWSD.
" All Ductile Iron Pipe is to be Class 52.
" Quantities and pricing is per layouts on plan sheet C4.1 Revision 2 by PLC dated 10126/04
" Meter pit does not include optional venting
' Pricing will be for acual quantities installed. Any additions or deletions will be made at these established prices.
' Services are terminated underground and marked with a steel T post for future location
' All Pipe Bedding is Class 6 Base
' Permits are by Owner
Page 1 of 2
.. ~ . ~` ~t ~ ` r
" ACC will require an additional 20 days be added to contract.
' 2" Copper price is increased due to the fact it no longer has a common trench to be installed into.
' Ductile Iron prices are set to rise by the end of the month. If change order is not approved prior to this increase
pricing will have to be adjusted.
Payment Terms: Net 30
ACCEPTED:
The above prices, specifications and conditions
are satisfactory and are hereby accepted.
Buyer
Signature
Date of Acceptance
CONFIRMED:
Rocky Mountain Civil
Authorized
Signature: ~ ~
Estimator:
jV1 ~~~i..~~~'-~- ~
Page 2 of 2