Press Alt + R to read the document text or Alt + P to download or print.
This document contains no pages.
HomeMy WebLinkAboutC04-252 Elam Construction
".
.,' "
>;",r
, STATE OF: COLORADO
NAME OF AIRPORT: EAGLE COUNlY REGIONAL
CONTRACTOR:Elam Construction, Inc.
AlP PROJECT NO.3-0B-0020-35
LOCATION: GYPSUM, COLORADO
SCHEDULE NO. II
CHANGE ORDER NO. THREE
o Elam Construction CONTRACTOR: YOU ARE HEREBY ORDERED TO MAKE THE FOLLOWING CHANGE IN THE PLANS
AND/OR SPECIFICATIONS FOR THE ABOVE DESIGNATED PROJECT.
1. DESCRIPTION OF CHANGE TO BE MADE: Provide profile/leveling partial pavement removal on Taxiway "A" and
connector Taxiways "Al", "Cl", "C2", "C3", "A2", "A3", "A4", "AS", and "A6" to provide required depth oftop surface cou
and leveling course of asphalt. This change cost estimate Is consistent with that provided In PCO No.7. Also included In
this change order are the delay costs to Elam.
2. REASON FOR ORDERING CHANGE: The original benchmark and existing ground elevations were found to be in error
with intlal survey Information taken at the start of this project. Without adjustment of the original benchmark the top
surface of the taxiway would have been, on average, 0.1 foot too high resulting in an overrun of asphalt quantity and
therefore costs. This change mitigates that overrun with a change to the partial pavement removal required for
profile/leveling prior to application of the top surface of bituminous pavement.
3. SETTLEMENT FOR THE COST OF THE MENTIONED CHANGE IS TO BE MADE AS FOLLOWS: Payment shall be made In
accordance with the price quoted in the original contract bid quantities. The quantity of pavement removal under Pay Item
P-140b Asphalt Pavement Removal (Partial Leveling) was bid at 37,200 square yards at $6.00 per square yard. The
additional partial pavement removal area totals 81,095 square yards or 43,895 square yards additional. At the contract uni
price of $6.00 per square yard the pay item is increased $263,370 or a total for the pay item of $486,570.00. Delay costs
are shown on PCO No. 16 for $23,007.25. Total increase on this change order is $4286,377.25. Final construction time is
HIS CHANGE ORDER (INCREASES) (DECREASES) THE CONTRACT TIME (17) (SEVENTEEN) CALENDAR DAYS,
4. SUMMARY OF COST:
NET ( INCREASE) (DECREASE) OF THIS AGREEMENT
TOTAL (INCREASE) (DECREASE) OF ALL PREVIOUS AGREEMENTS
TOTAL (INCREASE) (DECREASE) OF ALL AGREEMENTS TO DATE
TOTAL ESTIMATED CONTRACT COSTS
$286,377.25
$264,670.85
$551,048.10
$4,651,382.10
NOTE: THIS CHANGE ORDER IS NOT EFFECTIVE UNTIL SIGNED BY THE ENGINEERING SECTION AIRPORTS DMSION
FEDERAL AVIATION ADMINISTRATION.
AGREED TO BY, b -C+i l\i~(IIl'/tJ
SPONS 'S AUTHO ED REP. TITLE
'b /,) 0 l.j
DATE
~.e:, A
AGREED . - 4~ ~..r _ t!"- ,
C CTOR'S AUTHORIZED REP TITLE'
?""-t> 9
DATE /'
AGREED TO BY:
cf./7, 0 V
DATE
(INCREASE) (DECREASE) - STRIKE OUT THE ONE WHICH DOES NOT APPLY
".
'.
><
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AIP Project No. 3-08-0020-35
PCO # 7
Additional Profile Milling
ArchitectlEngineer:
Date of Plans:
We hereby propose:
Additional Profile Milling
Work to be done at Pay Item amount on bid schedule.
43895.00
Sy
5263.370.00
1 of 2
, ,
AD.ofthe above work to be completed in a substantial and workmanlike manner for the sum ofS263.370.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc., 30 days from above date, or it shall expire.
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perform aU of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications.
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may <;top work or terminate thi~ ("J)nt.ract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, mike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon aU past due payments. Customer agrees to pay
all co!l1:!I of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection,
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract hecome!l due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to cany Workmen's Compensation and public liability insurance and to pay aU sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
Elam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract has been created only when confirmed by Elam Co~ction.
Inc. Customer may be required to provide satisfactory evidence of adequate financing before confirmation by contractor.
ACCEPTEDtbis 3~da Of--1!.'~VS- 2OQ'J
Owner Stgnature: __ _ _
~ntName: E
Contractor hereby confirms the proposal.
CONFIRMATION by CONTRACTOR
Date
by
2 of 2
. .
SUBMITTED TO:
Eagle County ReigonaJ Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum. CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AIP Project No, 3-08-0020-35
PCO # 16
ArchitectlEngineer:
Date of Plans:
We hereby propose:
Additional Costs for milling' paving delay 17 days
Total Delay
1
2
3
4
5
6
7
8
9
Jobsite Trailer
Foreman and Truck
Water Truck approx. 3 hrslday
Gate Guard
Traffic Control Devices
Glass Grid Tractor
Fax, Copier, Telephones
Rental Loader for Milling Placement I Cleanup
Re Mobilization for Milling Subcontractor
$ 175.00
$ 5,950.00
$ 3,825.00
$ 2,805.00
$ 1,262.25
$ 1980.00
$ 525.00
$ 4,235.00
$ 2,250,00
Total
523,007.25
Milling 14 days
Paving 3 days
1 of 2
"
All of the above work to be completed in a substantial and workmanlike manner for the sum of See Scbedule
This proposal must be accepted as provided and delivered to Elam Construction, Inc" 30 days from above date, or it shall expire,
The contract amount is payable to EIam Construction, (nc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perfonn all of the work in a substantial
and workmanlike manner and in accordance with the tenns of the plans and specifications.
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may stop work or tenninate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection,
If the customer disposes of the real estate by sale or otherwise, the fu1J amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal,
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is perfonned.
Respectfully submitted,
EIam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract bas been created only when confinned by EIam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before confirmation by contractor.
ACCEPTED tIUs ---2- day of Ifll C;(J~ 'f
Owners~, ~
Print Name, . T"::-. c r. f!!.e
Contractor hereby confinns the proposal.
CONFIRMATION by CONTRACTOR
Date
by
2 of 2
AlP PROJECT NO.3-08-oo2o-35
E OF AIRPORT: EAGLE COUNTY REGIONAL LOCATION: GYPSUM, COLORADO
SCHEDULE NO. D
CHANGE ORDER NO. TWO
Sam Construction CONTRACTOR: YOU ARE HEREBY ORDERED TO MAKE THE FOllOWING CHANGE IN THE PLANS
DfOR SPEOFICATIONS FOR THE ABOVE DESIGNATED PROJECT.
1. DESCRIPTION OF CHANGE TO BE MADE: Provide all labor, materials and equipment to accomplish the following work:A)
loose pavement on Taxiways "A3", "A4", "AS', and "A6". (PCO No 3.) B) Adjust two addItiOnal manholes. (PCO No.
). C) Additional edge drain work to accommodate burled electrical ducts. (PeO No.8). D) Remove existing striping on
nwav to taxiway lead-in lines prior to permanent painting. (PCO No. 10). E) Reinstall additional retro-reflectlve markers.
PCO No. 12) F) Instan additional Concrete Encased Bectrlcal Duct. (PCO No. 13).
. REASON FOR ORDERING CHANGE: A) Remove loose pavement on Taxiways "A3", ~A4", "PS', and "A6". following profile
llIing to proper depth, it was found that the existing pavement layer left: was delaminating from the pavement layer beneath
I of the delaminated pavement was required prior to paving to ensure proper adhesion between layers. B) Adjust two
nholes. Manholes were raised approximately 6 Inches to match elevation of nearby light bases and maintain required
radient of shoulclers. C) Additional edge drain work to accommodate burled concrete encased eIectrlcal ducts. existing CE
uct banks encountered In flow line of edge drains. Edge drain elevations could not be adjusted to miss existing duct banks.
rltal removal and/or replacement of Concrete Encased Duct was required. D) Remove existing striping on runway prior to
nent painting. Existing taxiway lead-In lines from runway centerline to connecting taxiway centerllnes did not match
provided on drawings. ExIsting markings must be removed prior to painting permanenet markings. E) Reinstall
dltiOnal retro-refIectlve markers. Contract calls for removal of 476 each markers but provides for
nstallatlon of 160 each markers. The delay In procurement of new light fixtures necessilc}ted the reinstallation of
rkers In order to reopen Taxiway "A" west of Taxiway "A3". F) Install additional CE Duct. Contract drawings did
call for CE Duct on south access road, east of Taxiway "A". Ducts under haul road require protection from
traffic to prevent damage.
. SETTLEMENT FOR THE COST OF THE MENTIONED OlANGE IS TO BE MADE AS FOLLOWS: Payment shall be made in
nee with the prlce quoted on PeDs # 3, 4, 8, 10, 12 and 13 as noted. A) Add pay item P-l4Oc Remove Loose
Pavement 1 Lump Sum for $8,785.85. B) Increase Pay Item D-751a Adjust Manhole quantity to 9 each at $2,000.00 each or
,000.00. C) Additional Edge Drain work to accommodate burled ducts. Add pay item D-70Sd Adjust Edge Drain to
mmodate Becbical Duct, 1 Lump Sum at $4,315.00. D) Add pay item P-62OC Obliterate Pavement Markings, 1 Lump
um at $7,200.00. E) Increase Pay Item L-126b ReInstall L-853 Retro-reflectlve Marf<ers to 460 each at $40.00 each or $18,
.00 total ($12,000.00 Increase). F) Increase Pay Item L-llOc 1-2-inch PVC Duct, Concrete Encased from 25 LF to 46 LF
$20.00 per linear foot or $920.00 ($420.00 increase).
OfANGE ORDER (INCREASES) (DECREASES) THE CONTRACT TIME (0) (zero) CALENDAR DAYS.
. SUMMARY OF COST:
NET ( INCREASE) (DECREASE) OF THIS AGREEMENT $36,720.85
TOTAL (INCREASE) (DECREASE) OF ALL PREVIOUS AGREEMENTS $227,950.00
TOTAL (INCREASE) (DECREASE) OF ALL AGREEMENTS TO DATE $264,670.85
TOTAL ESTIMATED CONTRACT COSTS $4,592,954.85
: THIS CHANGE ORDER IS NOT EFFECTlVE UNTIL SIGNED BY THE ENGINEERING SECTION AIRPORTS DMSION
AVIATION ADMINISTRATION.
,
C-~I#-, (ltn"J
,
TITLE
~/}/o'1
DATE '
e-~
7- 9"1P~
DATE
? I~ D</
DATE
INCREASE) (DECREASE) - STRIKE OUT THE ONE WHICH DOES NO! APPLY
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AIP Project No. 3-08-0020-35
PeO # 3
Removal of loose asphalt mat at connectors
Architect/Engineer:
Date of Plans:
We hereby propose:
Removal of thin layer of asphalt at connectors that is showing no sign of bond with sub layers. Work to be completed on
time and materials basis, rates as follows.
I. Supervision $ 50.00 DR
2, Labor $ 38.00 DR
3, Skidsteer loader I operated $ 75.00 DR
4. Wheel Loader I operated $ 11 0.00 DR
5. Tandem Dump I leased $ 70.00 DR
6. Dump Fees / waste asphalt at gravel pit $ 25.00 LD
7. Sweeper / operated $ 85.00 DR
Price not to exceed: $ 2000.00 Each Connector
Note: Pricing is for removal only, additional asphalt will be paid at bid unit prices.
I of 2
AU of the above work to be completed in a substantial and workman6ke manner for the sum of See Above Priciot!
This proposal must be accepted as provided and delivered to Elam Construction., Inc., 30 days from above date, or it shall expire.
The contract amount is payable to Elam Construction., Inc. monthly for work as it. progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perfonn all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications.
The customer may order additional work or changes in writing at any time, at an agreed price or at the oo~tractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may stop work or terminate this contract ll1'ld recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages, It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 11% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The oontrlit:tor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is perfunned.
Respectfully submitted,
EIam Construction., Inc.
By
Palrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof-are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract has been created only when confirmed by Elam Construction,
h1c. Customer may be required to provide sitUflldory tvideliee eJf adequate filialicilig before tonfirdiatieJli by tolitrador.
ACCEPTEDthi. L~ 20 0'1,
~SignalUre _ ~ ~
Print Name: 10- -----P.,.J~
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
20f 2
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wdson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No. 3-08-0020-35
PCO#4
Raise manholes at "A3"E. sideand "AS" E. side
Architect/Engineer:
Date of Plans:
We hereby propose:
Raise Manhol~ approx 6" to match elevation of adjacent light base.
Work to be done at Pay Item amount on bid schedule.
2000.00
EA
$4.000.00
I of 2
. '
AD' of the above work to be completed in a substantial and workmanlike manner for the sum ofS4.000.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc., 30 days from above date, or it shall expire.
The contract amounl is payable to Elam Construction. Inc. munthly for work as it progresses with the entire balance payable upun
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications, if any, are expressly made a Part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work.
If payments for work are not made when due, the contractor may stop work or terminate this contract and recover from the
cU5l0I11~1 pl1Ylluml rUJ all wUlk t:}\,~ul~ WIU lUlIli ~U~Laill~ and reasonable profit and damages, It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss. damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
EIam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract has been created only when confirmed by EIam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before confirmation by contractor.
ACCEPTED tIUs ~ day of ~1l 'I
Owner S_ure ~ ==---. t~
Print Name: -=r 6 vt1 C- ~
Contractor hereby confirms the proposal,
CONFIlW".ATION by CONTRACTOR
by
Date
2 of 2
SUBMITIED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No. 3-08-0020-35
PCO#8
Additional underdrain work to accommodate burried ducts
ArchitectlEnginecr:
Date of Plans:
We hereby propose:
Extra work perfonned to deal with concrete encased ducts in flow line of proposed underdrain..
Work performed to date including all of phase 1.
Long's Excavation
S 4.315.00
1 of 2
'.
'.
All of the above work to be completed in a substantial and workmanlike manner for the sum of S4.31S.00
This proposal must be accepted as provided and delivered to Etam Construction, Inc" 30 days from above date, or it shall expire.
The contract amount is payable to E1am Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perform aU of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work.
If payments for work are riot made when due, the contractor may stop work or terminate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the fuU amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
EIam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By thisacceptance, I understand that a binding contract has been created only when confirmed by EIarn Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before confirmation by contractor.
ACCEPTED this ~ day of /HI G () ~ 'I ,20 () 'j
~~, STONE
Owner Signature:
Print Name:
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
2 of 2
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No, 3-08-0020-35
PCO# 10
Striping Removal
Architect/Engineer:
Date of Plans:
We hereby propose:
Description
Quantity
Units
Price
Amount
Striping Removal 6" wide
4000
LF
1,80
$ 7.200.00
I of 2
AD of the above work to be completed in a substantial and workmanlike manner for the sum of 57.200.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc" 30 days from above date, or it shall expire,
The contract amount is payable to Elam Construction, Inc, monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications. if any, are expressly made a part of this contract. The contractor shall perfonn all of the work in a substantial
and workmanlike manner and in accordance with the tenns of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may stop work or terminate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages, It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection,
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is perfunned.
Respectfully submitted,
Elam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, tenns and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract has been created only when confirmed by EIam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before conrU'Dlation by contractor.
ACCEP~DthiS~~dayof ItVhtlSI20f2'i
Owner SIgnature: __ _
Print Name: II) vt7 C.. 5 TOw C-
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
20f 2
An of the above work to be completed in a substantial and workmanlike manner for the sum ofSI2.000.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc" 30 days from above date, or it shall expire.
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications. Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications.
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may stop work or terminate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
Elam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract has been created only when confirmed by Elam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before confirmation by contractor.
ACCEPTEDthis~dayof AVGV5T ,20~.
=~ ~~ SUoJe-
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
20f 2
SUBMITIED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wtlson Rd.
Gypsum. CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No. 3-08-0020-35
PCO # 13
Additional CE duct
ArchitectlEngineer:
Date of Plans:
We hereby propose:
Additional CE duct (east end of Taxiway)
Work to be done at Pay Item amount on bid schedule.
11.00
EA
$410.00
1 of 2
"
AU 'of the above work to be completed in a substantial and workmanlike manner for the sum ofS420.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc" 30 days from above date, or it shall expire,
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications. Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perform aU of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications.
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work.
If payments for work are not made when due, the contractor may stop work or tenninate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or militlU)' authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection,
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is perfonned.
Respectfully submitted,
Elam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By thisacceptance, I understand that a binding contract has been created only when confirmed by Elam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before conf'mnation by contractor.
A~dDs~~~V~O~.
Owner SIgnature: ~__
Print Name: - TfJ l'tI. Co . S Tis tV e
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
2 of 2
, ,
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd,
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No. 3-08-0020-35
PCO # 12
Reinstall Retroflective Markers
ArchitectlEngineer:
Date of Plans:
We hereby propose:
Increase in number of retroflective markers to be reinstalled
Work to be done at Pay Item amount on bid schedule.
300.00
EA
512.000.00
I of 2
, ,
AlP PROJECT NO.3-08-oo2o-35
E OF AIRPORT: EAGLE COUNTY REGIONAL LOCATION: GYPSUM, COLORADO
SCHEDULE NO. D
CHANGE ORDER NO. TWO
Sam Construction CONTRACTOR: YOU ARE HEREBY ORDERED TO MAKE THE FOllOWING OfANGE. IN THE PLANS
D/OR SPEOFICATIONS FOR THE ABOVE DESIGNATED PROJECT.
1. DESCRIPllON OF CHANGE TO BE MADE: Provide all labor, materials and equipment to accomplish the following work:A)
loose pavement on Taxiways "AJ", "A4", "AS', and "A6". (PCO No 3.) B) Adjust two additional manholes. (PCO No.
). C) Additional edge drain work to accommodate burled electrfcal ducts. (PCO No.8). D) Remove existing sb1plng on
nway to taxiway lead-In lines prior to permanent painting. (PCO No. 10). E) Reinstall additional retro-refIective markers.
PCO No. 12) F) Install additional Concrete Encased 8ectrlcal Duct. (PCO No. 13).
. REASON FOR ORDERING CHANGE: A) Remove loose pavement on Taxiways "AJ", "M", "AS', and "A6". following profile
IIlIng to proper depth, it was found that the existing pavement layer left was delaminating from the pavement layer beneath
I of the delaminated pavement was required prior to paving to ensure proper adhesion between layers. B) Adjust two
nholes. Manholes were raised approximately 6 inches to match elevation of nearby light bases and maintain required
radlent of shoulders. C) Additional edge drain work to accommodate burled concrete encased eJectrical ducts. existing CE
uct banks encountered in flow line of edge drains. Edge drain elevations could not be adjusted to miss existing duct banks.
rltal removal and/or replacement of Concrete Encased Duct was required. D) Remove existing striping on runway prior to
nent painting. Existing taxiway lead-In lines from runway centerline to connecting taxiway centerlines did not match
provided on drawings. Existing markings must: be removed prior to painting permanenet markings. E) Reinstall
dditlonal retro-reflectlve markers. Contract calls for removal of 476 each markers but provides for
reinstallation of 160 each markers. The delay In procurement of new light fixtures necessildlt:d the reinstallation of
rkers in order to reopen Taxiway "A" west of Taxiway "AJ". F) Install additional CE Duct. Contract drawings did
call for CE Duct on south access road, east of Taxiway "A". Ducts under haul road require protection from
vy traffic to prevent damage.
. SETTLEMENT FOR THE COST OF THE MENTIONED CHANGE IS TO BE MADE AS FOLLOWS: Payment shall be made In
nee with the price quoted on PCOs # 3,4,8,10,12 and 13 as noted. A) Add pay item P-l4Oc Remove Loose
vement 1 Lump Sum for $8,785.85. B) Increase Pay Item D-751a Adjust Manhole quantity to 9 each at $2,000.00 each or
,000.00. C) Additional Edge Drain work to accommodate buried ducts. Add pay item D-70Sd Adjust Edge Drain to
8ectrlcal Duct, 1 Lump Sum at $4,315.00. D) Add pay Item P-62OC Obliterate Pavement Markings, 1 Lump
um at $7,200.00. E) Increase Pay Item L -126b ReInstall L -853 Retro-refIectIve Markers to 460 each at $40.00 each or $18,
.00 total ($12,000.00 increase). F) Increase Pay Item L-llOc 1-2-inch PVC Duct, Concrete Encased from 25 LF to 46 LF
$20.00 per linear foot or $920.00 ($420.00 inaease).
IS CHANGE ORDER (INCREASES) (DECREASES) THE CONTRACT TIME (0) (zero) CALENDAR DAYS.
. SUMMARY OF COST:
NET ( INCREASE) (DECREASE) OF THIS AGREEMENT $36,720.85
TOTAL (INCREASE) (DECREASE) OF ALL PREVIOUS AGREEMENTS $227,950.00
TOTAL (INCREASE) (DECREASE) OF ALL AGREEMENTS TO DATE $264,670.85
TOTAl ESTIMATED CONTRACT COSTS $4,592,954.85
OTE: THIS CHANGE ORDER IS NOT EFFEC11VE UNTIL SIGNED BY THE ENGINEERING SECTION AIRPORTS DMSION
AVIATION ADMINISTRATION.
G~4-''tl'"'';
,
TITLE
<0/'/00/
,
DATE
e-,-,-
7- 9..tfJy
DATE
e: 17. oLl
DATE
INCREASE) (DECREASE) - STRIKE OUT THE ONE WHICH DOES M:l[ APPLY
SUBJECT TO AVAlLAB'
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum. CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No, 3-08-0020-35
PCO # 3
Removal of loose asphalt mat at connectors
ArchitectlEngineer:
Date of Plans:
We hereby propose:
Removal of thin layer of asphalt at connectors that is showing no sign of bond with sub layers. Work to be completed on
time and materials basis, rates as follows.
1. Supervision $ 50.00 DR
2. Labor $ 38.00 DR
3, Skidsteer loader! operated $ 75.00 DR
4, Wheel Loader! operated $ 110.00 DR
5, Tandem Dump !leased $ 70.00 DR
6. Dump Fees! waste asphalt at gravel pit S 25.00 LD
7. Sweeper I operated $ 85.00 DR
Price not to exceed: S 2000.00 Each Connector
Note: Pricing is for removal only, additional asphalt will be paid at bid unit prices.
I of 2
AD of the above work to be completed in a substantial and workmanlike manner for the sum of See Above PriciDt!
This proposal must be accepted as provided and delivered to Elam Construction, Ine" 30 days from above date, or it shall expire.
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications. Unless otherwise specified herein, the plans
and specifications. ifany, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications.
Th" custom<< RUly order additional work or changes in writing at any tim", at an llgI'eed price or at the oo~tractor's regular rates
for the time and material work.
If payments for work are not made when due, the contractor may stop work or terminate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by tire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon aU past due payments. Customer agrees to pay
all costs ofeottection and a reasonable attorney's fee if the account becomes delinquent and is referred for cottection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such dispulial.
The ootltJ'lk,.'(or agrees to carry Workmen's Compenlllllion and public liability insurance and to pay aU sales laXeS, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
Elam Construction, Inc.
By
Palrick Bow'ke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof.are satisfactory and are hereby
accepted. By thisacceptance. I understand that a binding contract has been created only when confinned by EIam Construction,
lIte, Customer may be required to provide sati8faetoty evidenet of adequate financing before confirdla.ioll by contractor.
ACCEPTEDthisL~~ ~.~~20 0'1,
Owner Signature: _ 0_ __
Print Name: ,. 0 0";
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
20f 2
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No, 3-08-0020-35
PCO#4
Raise manholes at If A3 "E. sideand "AS" E. side
Architect/Engineer:
Date of Plans:
We hereby propose:
Raise Manholes approx 6" to match elevation of adjacent light base.
Work to be done at Pay Item amount on bid schedule.
2000.00
EA
$4.000.00
1 of 2
AD' of the above work to be completed in a substantial and workmanlike manner for the sum of $4.000.00
This proposal must be accepted as provided and delivered to Elam Construction. Inc" 30 days from above date. or it shall expire,
The contracl amounl is payable lo Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications.. if any, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work.
If payments for work are not made when due, the contractor may stop work or tenninate this contract and recover from the
~uslumt:l pl1ymt:l1L fUl wI wUlk eJlt:\;uLc:U l11nllultll ~ulilwllc:U tUld reasonable profit and damages, It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its contro\'
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal,
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract. as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
EIam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contr~ has been created only when confirmed by EIam Construction,
Inc. Customer may be required to provide satisfaetory evidence of adequate financing before confirmation by contractor.
ACCEPTED this ~ day of ~Q 1-
Owner SIgnature ~ ==-_ \~
Print Name: -:f ~ vt) "- ~
Contractor hereby confirms the proposal.
CONFIRMATION by CONTRACTOR
by
Date
2 of 2
.'
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AIP Project No. 3-08-0020-35
PCO#8
Additional underdrain work to accommodate burried ducts
Architect/Engineer:
Date of Plans:
We hereby propose:
Extra work performed to deal with concrete encased ducts in flow line of proposed underdrain..
Work performed to date including all of phase I.
Long's Excavation
S 4.315.00
1 of 2
AU of the above work to be completed in a substantial and workmanlike manner for the sum ofS4.31S.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc" 30 days from above date, or it shall expire,
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications. ifany, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work.
If payments for work are not made when due, the contractor may stop work or tenninate this contract and recover trom the
customer payment for all work executed and loss sustained and reasonable profit and damages, It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss., damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes. old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
EIam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By thisacceptance, 1 understand that a binding contract has been created only when confirmed by EIam Construction,
Inc. Customer may be required to provide satisfactory evideuce of adequate financing before confirmation by contractor.
ACCEPTED this 3- day of /HI6 () ~ r ,20 t> lj
~~. STONE.
Owner Signature:
Print Name:
CONFIRMATION by CONTRACTOR
Contractor hereby continns the proposal.
Date
by
2 of 2
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AIP Project No, 3-08-0020-35
PCO# 10
Striping Removal
ArchitectlEngineer:
Date of Plans:
We hereby propose:
Description
Quantity
Units
Price
Amount
Striping Removal 6" wide
4000
LF
1.80
$ 7.200.00
10f 2
.'
.-
AD of the above work to be completed in a substantial and workmanlike manner for the sum of 57.200.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc" 30 days from above date, or it shall expire,
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications. ifany, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may stop work or terminate this contract and recover 'from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal,
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
Elam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract has been created "only when confirmed by Elam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate fmandng before confll'lllation by contractor.
ACCEP~ this ~~dayof !tV hI/51 2OQ'i
Owner SIgnature: __ _
Print Name: To Yn c. 5 nw E-
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
2 of 2
AD of the above work to be completed in a substantial and workmanlike manner for the sum ofSt2.000.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc., 30 days from above date, or it shall expire.
The contract amount is payable to Elam Construction. Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications. Unless otherwise specified herein, the plans
and specifications, ifany, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications.
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work. "
If payments for work are not made when due, the contractor may stop work or terminate this contract and recover from the
customer payment for all work executed and loss sustained and reasonable profit and damages. It is hereby mutually agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its control.
A late charge of 180/0 per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection,
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to carry Workmen's Compensation and public liability insurance and to pay all sales taxes, old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfully submitted,
EIam Construction. Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By thisacceptance, I understand that a binding contract has been created only when confirmed by EIam Construction,
Inc. Customer may"be required to provide satisfactory evidence of adequate financing before confirmation by contractor.
ACCEPTED this ~ day- of Ii &I G V 5T , 20!!.!t.
=::-- ~~ STDtJE.
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal.
Date
by
2 of 2
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wdson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No. 3-08-0020-35
PCO # 13
Additional CE duct
Architect/Engineer:
Date of Plans:
We hereby propose:
Additional CE duct (east end of Taxiway) ,
Work to be done at Pay Item amount on bid schedule.
11.00
EA
5420.00
1 of 2
AU'of the above work to be completed in a substantial and workmanlike manner for the sum of $420.00
This proposal must be accepted as provided and delivered to Elam Construction, Inc., 30 days from above date, or it shall expire.
The contract amount is payable to Elam Construction, Inc. monthly for work as it progresses with the entire balance payable upon
completion unless otherwise provided in this contract or in the plans and specifications, Unless otherwise specified herein, the plans
and specifications., ifany, are expressly made a part of this contract. The contractor shall perform all of the work in a substantial
and workmanlike manner and in accordance with the terms of the plans and specifications,
The customer may order additional work or changes in writing at any time, at an agreed price or at the contractor's regular rates
for the time and material work,
If payments for work are not made when due, the contractor may stop work or tenninate this contract and recover from tbe
customer payment for all work executed and loss sustained and reasonable profit and damages, It is hereby mutuany agreed that
the contractor shall not be held responsible or liable for any loss, damage, liquidated damages or delay caused by fire, strike, civil
or military authority or any other cause beyond its controL
A late charge of 18% per annum on the outstanding balance may be imposed upon all past due payments. Customer agrees to pay
all costs of collection and a reasonable attorney's fee if the account becomes delinquent and is referred for collection.
If the customer disposes of the real estate by sale or otherwise, the full amount remaining unpaid on this contract becomes due at
once and payable within forty-eight (48) hours after date of such disposal.
The contractor agrees to cany Workmen's Compensation and public liability insurance and to pay all sales taxes. old age benefit
and unemployment compensation taxes upon the material and labor furnished under this contract, as required by the United States
of America and the State in which this work is performed.
Respectfuny submitted,
Elam Construction, Inc.
By
Patrick Bourke, Area Manager
ACCEPTANCE OF PROPOSAL
The prices, specifications, terms and conditions stated above and on the reverse side hereof are satisfactory and are hereby
accepted. By this acceptance, I understand that a binding contract'bas been created only when confirmed by EIam Construction,
Inc. Customer may be required to provide satisfactory evidence of adequate financing before confU'IDation by contractor.
ACCFFrFDdns~~~.U~O~
Owner Slgnature: ~~_
Print Name: TfJ l'tI, Co . S n tV E
CONFIRMATION by CONTRACTOR
Contractor hereby confirms the proposal,
Date
by
2 of 2
SUBMITTED TO:
Eagle County Reigonal Airport
Attention: Rich Cunningham
0219 Elden Wilson Rd.
Gypsum, CO 81637
( )
JOB NAME & ADDRESS:
Eagle County Reigonal Airport Improvements
AlP Project No, 3-08-0020-35
PCO # 12
Reinstall Retroflective Markers
Architect/Engineer:
Date of Plans:
We hereby propose:
Increase in number of retrotlective markers to be reinstalled
Work to be done at Pay Item amount on bid schedule.
300.00
EA
$12.000.00
1 of 2