CHANGE ORDER NUMBER _ 5
CONTRACTOR Elam Construction, Inc.
Contract for Eagle-Vail Pedestrian Trail Improvements
Contract Date August 5, 2003
TO: Elam Construction, Inc.
You are directed to make the changes noted below in the Subject Contract. Appropriations to
cover the costs of additional work have been made.
EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS
By:
Tom C. one, Chairman
DATE: ~ ~ -5 " ` `~
Nature of Changes: Due to right-of--way width and the construction of the roundabout at Post
Blvd. and Highway 6, a portion of the trail was removed from the project eliminating the need
for removing a portion of stone wall. In addition, there were some final adjustments made to
reflect as-built conditions. An itemization of the changes for this change order is attached as
Exhibit "A". Due to winter weather conditions certain final portions of the work were not
completed prior to the previous ending date of December 31, 2003, and were completed this
spring. An increase in contract time is warranted.
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to this Change Order $477,754.07
Net Decrease Resulting from this Change Order -$ 9,518.00
Current Contract Price Including this Change Order $468,236.07
Change Order #5 Page 1 of 2
Contract Time Prior to this Change Order December 31, 2003
Net Increase Resulting from this Change Order 150 Days
Cur; ent Contract Time Including this Change Order May 30, 2004
The above changes are recommended:
.~ 1 ~
r 1 r,
l ~~ G
Helen Migchelbrink
County Engineer
Date: L ~`
The above changes are accepted: Elam Construction, Inc.
By:
Title:
Date:
Change Order #5 Page 2 of 2
Change Order #5
Contract dated August 5, 2003
Eagle-Vail Pedestrian Trail Improvements
~ ~.
Peter T. ulmeisters Date
EAGLE COUNTY Project Manager
Original Adjusted
Contract Change Quantity Unit Price Contract
Item Descri tion Qt Unit Unit Price Amount Order Chan a Chan a Net Chan a Price
1 Clearin & Grubbin 1 LS $20,000.00 $20,000.00 $0.00 $20,000.00
2 Excavation and Embankment 1 LS $53,790.00 $53,790.00 1 -0.4796% -$258.00 $57,184.00
2 6.7894% $3,652.00
3 Aggregate Base Course (Class 6) 2283 Tons $28.00 $63,924.00 1 -81.2600 -$2,275.28 $61,704.72
$28.00 2 2.0000 $56.00
4 Asphalt (HBP) 773 Tons $55.00 $42,515.00 1 -43.5300 -$2,394.15 $40,120.85
$55.00 2 0.0000 $0.00
5 Top Soil: Remove/Replace/Dispose
1 LS $15,000.00 $15,000.00 $0.00 $15,000.00
6 Reve etation & Seedin 1 LS $4,500.00 $4,500.00 $0.00 $4,500.00
7 Install Storm Manhole 1 EA $4,500.00 $4,500.00 4 -1.0000 -$4,500.00 $0.00
8 Ad'ust Manholes 8 EA $275.00 $2,200.00 $0.00 $2,200.00
9 Relocate Ped Heads 2 EA $1,350.00 $2,700.00 $0.00 $2,700.00
10 Relocate Electric Meter 1 EA $2,000.00 $2,000.00 $0.00 $2,000.00
11 Relocate Si nal Control Box 1 EA $2,800.00 $2,800.00 $0.00 $2,800.00
12 Install 18" CMP Culvert 90 LF $92.00 $8,280.00 2 -60.0000 -$5,520.00 $0.00
4 -30.0000 -$2,760.00
13 F.E.S. 4 EA $450.00 $1,800.00 2 -1.0000 -$450.00 $450.00
4 -2.0000 -$900.00
14 Ri ra 1.5 CY $1,000.00 $1,500.00 4 -1.5000 -$1,500.00 $0.00
15 T e C Inlet 1 EA $4,500.00 $4,500.00 2 -1.0000 -$4,500.00 $0.00
16 Extend 24" HDPE Pie 10 LF $200.00 $2,000.00 $0.00 $2,000.00
17 Connectin Band 1 EA $250.00 $250.00 $0.00 $250.00
18 Stona Wall Removal 1 LS $3,000.00 $3,000.00 5 -1.0000 -$3,000.00 $0.00
19 Remove Trees 15 EA $300.00 $4,500.00 4 -4.0000 -$1,200.00 $3,300.00
20 Hand Rail Over Tunnel 65 LF $115.00 $7,475.00 $0.00 $7,475.00
21 Si n Relocation 8 EA $65.00 $520.00 $0.00 $520.00
22 New Signs 52 EA $100.00 $5,200.00 4 -8.0000 -$800.00 $2,900.00
5 -15.0000 -$1,500.00
Eagle-Vail Pedestrian Trail Improvements
Change Order #5
F-
W
.saIQ9e1
Page 1 of 3
Original Adjusted
Contract Change Quantity Unit Price Contract
Item Descri tion Qt Unit Unit Price Amount Order Chan a Chan a Net Chan a Price
23 Si n Posts 43 EA $50.00 $2,150.00 4 -31.0000 -$1,550.00 $600.00
Retaining Wall, Concrete Walk,
Railin
24 Structure Excavation 30 CY $150.00 $4,500.00 $0.00 $4,500.00
25 Structure Backfill Class 1 30 CY $200.00 $6,000.00 $0.00 $6,000.00
26 A re ate Base Course Class 6 21 CY $125.00 $2,625.00 $0.00 $2,625.00
27 Concrete Block Facin MSE Walls 1645 SF $32.00 $52,640.00 $0.00 $52,640.00
28 Bikewa Railin Steel 595 LF $90.00 $53,550.00 1 -$8.61 -$5,123.00 $48,427.00
29 Concrete Class D 136 CY $275.00 $37,400.00 $0.00 $37,400.00
30 Reinforcin Steel E ox Coated 9750 LBS $1.00 $9,750.00 $0.00 $9,750.00
31 Guardrail, Type 3 290 LF $32.00 $9,280.00 2 185.0000 $5,920.00 $12,416.00
4 -87.0000 -$2,784.00
32 End Section 1 EA $2,200.00 $2,200.00 4 -$1,200.00 -$1,200.00 $1,000.00
33 Pedestrian Rub Rail 50 LF $14.00 $700.00 4 231.0000 $3,234.00 $3,934.00
34 Sanita Facilit 1 EA $400.00 $400.00 $0.00 $400.00
35 Erosion Control 1 LS $7,500.00 $7,500.00 $0.00 $7,500.00
36 Traffic Control 1 LS $20,000.00 $20,000.00 $0.00 $20,000.00
37 Surve in .1 LS $12,000.00 $12,000.00
$0.00
$12,000.00
38 New Item: Remove Existin HBP SF 2 1330.0000 $0.50 $665.00 $665.00
39 New Item: Sawcut LF 2 75.0000 $1.50 $112.50 $112.50
40 New Item: Struxture Excavation LS 2 1.0000 $1,000.00 $1,000.00 $1,000.00
41 New Item: Structure Backfill LS 2 1.0000 $1,500.00 $1,500.00 $1,500.00
42 New Item: Riprap section at 84" pipe
for stabilizaion of slope. Time LS 3 1.0000 $20,000.00 $20,000.00 $14,982.00
and materials not to exceed rice 5 -25.09% -$5,018.00
43 New Item: Rase Existing Manhole
' LS
a proximate 1 4 1.0000 $700.00 $700.00 $700.00
44 New Item: Increase cost to excavate LS
ier holes due to rock soil 4 1.0000 $440.00 $440.00 $440.00
45 New Item: Remove and Replace 6
LF of 2' curb and utter LS
4
1.0000
$500.00
$500.00
$500.00
46 New Item: Plug Culvert at Eagle Rd
with concrete LS
4
1.0000
$250.00
$250.00
$250
00
47 New Item: Wedge Patching E. of .
Stone Creek intersection LS
4
1.0000
$2,150.00
$2,150.00
$2,150.00
Eagle-Vail Pedestrian Trail Improvements
Change Order #5 Page 2 of 3
Original Adjusted
Contract Change Quantity Unit Price Contract
Item Descri tion Qt Unit Unit Price Amount Order Chan a Chan a Net Chan a Price
New Item: Winter Protection for
48 LS
Concrete Walk
4
1.0000
$1,640.00
$1,640.00
$1,640.00
TOTAL $473,649.00
-$9,518.00
$468,236.07
Change Order #4 Summary
Original Contract Amount $473,649.00
Change Order #1 DECREASE -$10,050.43
'Change Order #2 INCREASE 2,435.50
,Change Order#31NCREASE $20,000.00
Change Order #4 DECREASE
( -$8,280.00
Change Order #5 DECREASE -$9,518.00
New Contract Amount $468,236.07
Eagle-Vail Pedestrian Trail Improvements
Change Order #5 Page 3 of 3