CHANGE ORDER NUMBER 1
CONTRACTOR United Rentals Highway Technologies, Inc.
Contract for 2002 Centerline 1V~arldng Project
Contract Date April 23, 2002
TO: United Rentals Highway Technologies, Inc.
You are directed to make the changes noted below in the Subj ect Contract. Appropriations to cover
the costs of additional work have been made.
EAGLE COUNTY BOARD
By: y v ~
Michael L.
DATE: ~
Nature of Changes: Final adjusting change order
ITEM DESCRIPTION
1. Pavement Marking Paint with Beads (Yellow)
From 2,705 Gal. @ $17.00/gal to 2,549.3 Gal.
@ $17.00/gal
2. Pavement Marking Paint with Beads (White,
edge lines and turn lanes) From 125 Gal. @
$17.00/gal to 95.8 Gal. @ $17.00/gal
3. Pavement Marking Paint with Beads (White,
words, symbols, crosswalks and stop lines)
From 2,539.04 SF @ $2.00/SF to 2,173.54 SF
@ $2.00/SF
INCREASE
DECREASE
$2,646.90
$ 496.40
$ 731.00
:"
. -.
• •
Change Order No. 1
Page 2
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to this Change Order $53,188.08
Net Decrease Resulting from this Change Order -$ 3,874.30
Current Contract Price Including this Change Order $49,313.78
Contract Time Prior to this Change Order September 30, 2002
Net Resulting from this Change Order No Change
Current Contract Time Including this Change Order September 30, 2002
The above changes are~recommended:
f a
Brad Higgins
Road and Bridge Director
Date:
The above changes are recommended:
Peter T. Sulmeisters
Project Manager
Date: /2 /i q/o ~
The above changes are accepted: United Rentals Highway Technologies, Inc.
By:
Title:
Date:
M
CHANGE ORDER NUMBER 1
CONTRACTOR United Rentals Highway Technologies, Inc.
Contract for 2002 Centerline Marking Project
Contract Date Apri123, 2002
TO: United Rentals Highway Technologies, Inc.
f~
~~ ~
You are directed to make the changes noted below in the Subj ect Contract. Appropriations to cover
the costs of additional work have been made.
EAGLE COUNTY BOARD OF COUNTY COMMISSIONERS
~~,i'~ ~
C , ~ ~ ~ By.
~~~ ° Michael L. Gallagher, Chairman
~j ~ ~ ~~ ~ DATE:
Nature of Changes: Final adjusting change order
ITEM DESCRIPTION
1. Pavement Marking Paint with Beads (Yellow)
From 2,705 Gal. @ $17.00/gal to 2,549.3 Gal.
@ $17.00/gal
INCREASE DECREASE
2. Pavement Marking Paint with Beads (White,
edge lines and turn lanes) From 125 Gal. @
$17.00/gal to 95.8 Gal. @ $17.00/gal
3. Pavement Marking Paint with Beads (White,
words, symbols, crosswalks and stop lines)
From 2,539.04 SF @ $2.00/SF to 2,173.54. SF
@ $2.00/SF
N
$2,646.90
$ 496.40
$ 731.00