HomeMy WebLinkAboutC01-256 Elam Construction change order number 1CHANGE ORDER NUMBER 1
CONTRACTOR Elam Construction, Inc.
Contract for 2001 Overlay Project
Contract Date April 10, 2001
TO: Elam Construction, Inc.
You are directed to make the changes noted below in the Subject Contract. Appropriations
to cover the costs of additional work have been made.
Nature of Changes: Final adjusting change order
ITEM DESCRIPTION
1. Hot Bituminous Pavement on Frying Pan
Road: From 11,358± Ton @ $41.00 /ton
to 11,272 Ton @ $41.00 /ton
2. Hot Bituminous Pavement on Colorado
River Road: From 9,926± Ton @ $35.00 /ton
to 9,400 Ton @ $35.00 /ton
INCREASE DECREASE
$ 3,526.00
$18,410.00
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to this Change Order $915,900.00
Net DECREASE Resulting from this Change Order ($ 21,936.00j
Current Contract Price Including this Change Order $893,964.00
Change Order No. 1
Page 2
Contract Time Prior to this Change Order September 1, 2001
Net Resulting from this Change Order No change
Current Contract Time Including this Change Order September 1, 2001
The above changes are recommended:
The above changes are accepted
.• ••
Date:
Elam Constr tion, Inc.
Title: Harold F. Elam President
!. - MT • 1/