HomeMy WebLinkAboutC93-006 Contract between Eagle County EMS and B&B CommunicationsCl C i
C93 -06 -23
B &B Communications, Inc.
Contract Agreement
Project Name: Eagle County EMS Master Plan Project Number: 8300 -81
Project Manager: James Boyd
Client Name: Eagle County EMS Council Billing Address: Same
Address: 42 West Meadow Drive
Vail Co 81657
Attn.: County Commissioners Telephone No.: (303) 328 -86
Scope of Services: See attached December 17 1992 letter to Council members.
Prior to the commencement of work, a retainer of $8000.00 will be received and
placed in escrow to be credited against the final billing. The balance of the $9000.00
fee is to be paid within 30 days of the completion of this project. A monthly statement
will be submitted to the EMS council showing professional services rendered for that
period and a year to date total. Should work beyond the scope of service be required,
it will be paid as extra work at a cost to be agreed upon prior to commencement of the
additional work. The liability of B &B Communications for losses or damages arising
out of errors, omissions, or negligence of B &B Communications while providing the
professional services described herein shall be limited to the total fee due B &B
Communications pursuant to this contract.
Acceptance:
For :
U
B &B Communication, Inc.
Signature v
( Title )
Date: January 11, 1993 Date: 12 IS
Z?
The Undersigned represents and warrants that he is the duly appointed and authorized
agent of Eagle County hereinafter referred to as "Client" and that he is authorized, by
the Client , to enter into this Agreement, in the amount specified, in behalf of the
Client.
I'
( Title )
e
B m COMMUNICATIONS, &L
Drawer 249
Vail, CO 81658
926- 5275•Faa 926 -2344
December 17, 1992
Eagle County
P.O.Box 850
Eagle, CO 81631
INVOICE# 830001
JOB # 8300 -81 EMS Master Plan
DATE DESCRIPTION AMOUNT
BILLED
12 -17 -92 EMS Consulting Fee $ 8000.00
TOTAL DUE INVOICE # 830001
AMOUNT
DUE
$ 8000.00
$ 8000.00
PLEASE RETURN A COPY WITH YOUR PAYMENT AND REMITTANCE ADVICE
THANK YOU
CO"
B B COMMUNICATIONS '. DEC l 8 1992
Drawer 249
Vail, CO 81658 RD OF cOdll r mw Mes a `
A. J. Johnson
926- 5275•Fax 926 -2344 December 17, 19 ,
Kraige Kinney
Tom Collins .
EMS Communication Council
Eagle County
Council Members:
}
B &B Communications, Inc., hereafter referred to as B &B, in entering into an
agreement with Eagle County agrees to perform the consulting service as listed
scope of work below: .�
• Design County wide EMS channel to communicate in
UHF band, allowing ambulance and paramedic services to
communicate with hospitals in both Glenwood Springs
and Vail.
• Design County wide EMS disaster channel for
coordinating EMS response teams.
• Design centralized control of base station repeaters .
• Work with EMS council to develop grant request for Feb.
15 due date.
• Survey county agencies for current inventory of radio
equipment.
• Develop five year communication plan for Eagle county
government agencies.
• Perform necessary site surveys for base stations and
dispatch locations.
• Perform frequency coordination with APCO and other
agencies.
• Define system requirements .
• Develop detail bid specifications.
• Supervise final acceptance test . (attachment 1)
EMS Communication Council
Eagle County
December 17, 1992
Page 2
Eagle County will make available all pertinent drawings and equipment inventories and
any other information that will assist in accomplishing this project.
The cost for these services will be fixed at $9000.00 and is based on our good faith
estimate of services necessary to complete the previously described tasks. This
estimate consists of two hundred ( 200 ) hours of service performed.
B &B will not be responsible for any costs associated with:
Tower stress analysis for additional microwave dishes.
• Microwave path analysis fee required for new microwave licensing.
• FCC licensing fees required.
• Lease or ownership agreements for equipment locations.
• Any fees not directly implied in the above listed tasks.
B &B will provide the EMS council a sign -off sheet for each stage of the project. An
authorized signature indicates satisfactory completion of that task of the project. Upon
completion or approval of the final acceptance test, B &B will not be held liable for any
damage or failure of the system components .
All of the services provided, as listed above, will be completed by December 31,
1993. B &B will not be obligated to provide any additional services 15 days after the
final acceptance test.
B &B will provide a detailed monthly statement for professional services rendered and
draw from an escrow account the amount of funds required to cover those
expenditures. B &B will obtain written consent prior to entering into any agreements
for contracting services necessary for the completion of this project. Any additional
costs or fees required for the completion of this project will be the responsibility of
Eagle County.
a $
EMS Communication Council
Eagle County
December 17, 1992
Page 3
Thank you again for the opportunity to provide services to Eagle County. If you have
any questions please contact me at (303) 926 -5275.
Respectfully,
B &B Communications, Inc.
By:
James Boyd
Manager
EMS Communication Council
Eagle County
December 17, 1992
(Attachment 1)
Acceptance Test Proposal
The following is a guideline for the services B &B will provide concerning the final
acceptance test. B &B will meet with the EMS council within 20 days of the completed
installation of equipment and perform the necessary tests to evaluate the systems
performance. The basis of these test will consist of the following:
• Confirmation of the coverage area of the UHF medical channel per the counties
requirements.
• Confirmation of the coverage area of the UHF disaster response channel per the
counties requirements.
• Dispatch control of both UHF channels per the counties requirements.
• Confirmation of the communication link from the base station sites to the control
site.
• Portable and mobile radio interface with the base station equipment.
• B & B will be required to perform an acceptance test only on equipment installed
by December 31, 1993.