HomeMy WebLinkAboutC88-121 change order to GMCO contract for chip sealr
C,
No. Three (Final)
CHANGE ORDER C88- 121 -21
Date: October 11, 1988
CONTRACTOR: GMCO Corporation, P.O. Box 1106, Glenwood Springs, CO 81602
Contract For:1988 Chip Seal Program Contract Date: April 25, 1988
To: GMCO Corporation
Contractor
You are directed to make the changes noted below in the subject Contract
Eagle County
Owner
By
George Gates-, Chairman
Dated /(%lrrJ?.s.,�X�it Y ,190_
Nature of the Changes: Addition of the Town of Eagle's portion of work to be
done on Brush Creek Road
SEE ATTACHED
These changes result in the following adjustment
of Contract Price and Contract Time:
Contract Price Prior to This Change Order
Net (Increase)( ) Resulting from this Change Order
Current Contract Price Including This Change Order
$ 419,013.32
$ 10,304.69
$ 429,318.01
Change Order No. THREE
ITEM NO. DESCRIPTION INCREASE DECREASE
16. From: 3.24 Miles @ 23,419.75 = $75,879.99
To: 3.68 Miles @ 23,419.75 = $86,184.68 $10,304.69
TOTAL = $10,304.69