HomeMy WebLinkAboutC88-104 In Line Traffic Marking Change OrderCHANGE ORDER
Dated September 9, 1988
CONTRACTOR IN -LINE TRAFFIC MARKING COMPANY
F C88- 104 -21
No.ONE (FINAL)
Contract Forl988 Roadway Pavement Contract Date August 15, 1988
Centerline Marking & Beads
To: IN -LINE TRAFFIC MARKING COMPANY
Contractor
You are directed to mane the changes noted "below in the subject Contract
MMEWINUT ■ . 07-212011111
Um
EY
Chairman, George A. Gates
Dated /Z , 19
Nature .of the Changes:Reduce final contract amount from $14,445.00 to
$ 13,742.01.
ITEM NO. DESCRIPTION DECREASE
(1.) Pavement Marking Roadway Paint & Beads
From: 1500 gal @ 9.63/gal = 14,445.00
To: 1427 gal @ 9.63/gal = 13,742.01 702.99
These changes res-.ilt in the following adjustment
of Contract Price and Contract Time:
Contract Frice Prior to This Change Order
Net (/ hkk Abk ) ( Decrease ) Resulting from this Change order
8 14,445.00
S , 702.99
Cii_rent Contract Price Including This Change Order 8 13,742.01
Contract Time Prior to This Change Order August 31, 1988
"Days or Date)
Netllncrease)(p�gyr y��)Resulting from This Change Order ONE
I (Days)
Current Contiract Time Including This Change Order September 1, 1988
(Days or Date)
The Above Changes Are Recommended:
Phill Scott
ENGINEER
By
Date ��n, �2r /� '1989
The Above Changes Are Accepted: IN -LINE TRAFFIC MARKING COMPANY
CONTRACTOR
Michael L. Stephan - General Manager
Date September 15 , 1988