HomeMy WebLinkAboutC87-066 GMCO change order for Town of Redcliff road improvement projectEngineering Offic(-'
EAGLE COUNTY
550 Broadway
P.O. Box 850
EAGLE, COLORADO 81631
(303) 328-7311 Ext. 545
TO Eagle County Attorney Office
WE ARE SENDING YOU 0 Attached 171 Enclosed
0 Copy of letter [2 Change order
Dinformation 0
DATE May 5, 1987 TOB
NO -ecdpw - 8609
ATTENTION Lisa Huffman
RE: Change Order No. 2
4/20/87
Change Order No. 2 and Change Order No. 2 (Alternate A)
El Under Seperate Cover El Plans
0 Application for Payment
COPIES
DATE
DESCRIPTION
2
4/20/87
Change Order No. 2 and Change Order No. 2 (Alternate A)
E, GOL C y
THESE ARE TRANSMITTED as checked below:
REMARKS
COPY TO
El For approval For your use
0 For review and comment ❑
0 As requested
Please file in last years Contract for
Red Cliff Road Improvement. GMCO Corporatinn
is the Contractor for this work. Thank YoiL2
SIGNED:
If enclosures are not as noted, kindly notify us at once.
CHANGE ORDER
Dated . April 20, .1.987
OWNER's Project No ..... ZMPW-.Zrig-$649 .....
No. ...?.....
C87-66-21 �-
Town of Redcliff Road Improvement Project
Project , ,
CONTRACTOR ...... QIQQ.Ci4-j;poration
... ....................
Contract For . ,Chip Seal (Altaxriate. A)...... Contract Date ....September 23, 1986
To: ...................Dick Stephenson..............................................
CONTRACTOR
You are directed to make the changes noted below in the subject Contract:
Nature of the Changes
Work to begin June 8,1987, with work to be
complete June 30, 1987. Work to begin after
receipt of Notice To Proceed.
Enclosures:
These changes result in the following adjustment of Contract Price and Contract Time:
Contract Price Prior to This Change Order $ .... 20, 9Q8, 80 ....... _ .
Net (Increase) (Decrease) Resulting from this Change Order $ ......... 0.00 _ ....... .
Current Contract Price Including This Change Order $ .... 20 , 908.80 ..... _